Presentation Outline
OverviewofthePhilippineEISSystem AssessingthePhilippineEISSystem CurrentChallengesandCasesinPoint Current Challenges and Cases in Point PolicyDirections OpportunitiesforDevelopment p Cooperation
Legislative Framework g
Presidential Decree (PD) 1151
Philippine Environmental Policy of 1977
PD 1151
Requires an environmental impact statement (EIS) to precede all actions, projects or undertakings which may significantly affect the quality of the environment
PD 1152
Requires land use management regulating or enforcing agencies to consider the significant environmental impacts, as well as other aspects of locating industries.
PD 1586
No person, partnership or corporation shall undertake or operate any environmentally critical project (ECP) or locate a project within an environmentally critical area (ECA) without first securing an Environmental Compliance Certificate (ECC).
Regulatory Framework g y
Proclamation No. 2146 (1981) No
Environmentally Critical Projects (ECPs) Environmentally Critical Areas (ECAs)
Regulatory Framework g y
DENR Administrative Order 30 Series of 2003 (DAO 2003-30) Implementing 2003 30) I l ti Rules and Regulations for the PEISS Revised Procedural Manual
To achieve optimum economic development without delay To ensure that the present generation meets its needs without compromising the needs p g of the future generation
EIA and FS to be conducted at the same time Shorter processing time to obtain ECC Reduced requirements EMB to coordinate with Department of Trade and Industry
Procedural Manual
Screening Procedures EIS Requirements R i t Procedural Guide Review Process Administrative System
Social preparation Scoping process g Public consultation Public hearing/s Public participation
Attention to IPs and women Alternative dispute or conflict resolution
Preparedness
Rehabilitation
Response
Source: NDCC
Current Challenges
Institutional capacity of DENR/EMB
Monitoring and enforcement capability Accredited laboratories
Baseline environmental data ECAs mapping Compliance and enforcement Intent and timing of the EIA process C Coordination among NGA and overlapping of di i NGAs d l i f functions
Case in Point
Legal Challenges: Writ of Kalikasan
Issuance of ECC on the P38 B reclamation project along the coastline of Manila Bay Supreme Court issued a Writ of Kalikasan
Case in Point
Careful Review of Mining Projects
Denial of the issuance of the ECC for Tampakan Mining Project Open pit mining method
Case in Point
Careful Review of Mining Projects
S Suspension of i f processing of applications and issuance of ECC for all small scale mining projects (April 19 2011) 19,
Case in Point
Role of LGUs deniedissuanceofbusinesspermit lackofLGUendorsement devolvedfunctionstoLGUs (DENRMemoCircular200808: ClarificationoftheRoleofLGUsinthe Clarification of the Role of LGUs in the PEIS
Policy Directions
Policy Directions
Screening Procedures
Need to rationalize/update categorization Non-uniform enforcement at various regional offices
Policy Directions
Review Process
Uneven quality of EIA Reports and review process Legal challenges to ECC decisions Technical skills and capabilities
Policy Directions
Transparency and Disclosure
Need to improve transparenc (standardi ed impro e transparency (standardized environmental enforcement) Need to strengthen monitoring system
Expanded automation to include web access web-access by stakeholders Improve compliance and monitoring system
Technical Capability