Escolar Documentos
Profissional Documentos
Cultura Documentos
Submitted By: Group No 7 Members: FT 13422 Divya Ananthram FT 13219 Gagandeep Uppal FT 13125 Gajendra Sisodia FT 13221 Gaurav Parikh FT 13127 Gaurav Varshney
Background
Introduction
An underground tunnel 51.5 KM undersea double rail link connecting England and France. The largest privately funded project ever undertaken. Bankers underwriting the funding for the project.
Major Challenges
Cooperation of two national governments Bankers underwriting the funding for the project Bankers underwriting the funding for the project Numerous Contractors Several regulatory agencies Several regulatory agencies Overlapping design and construction Under ground construction
A. Inception Phase:Historical background, overall objectives, political climate, and pre-feasibility studies.
Evaluation of Project Management during this phase: Rating scale: 5- Excellent, 4-Very Good, 3-Good, 2-Poor, 1-Very poor
Project Management Area Scope Mangement Time Management Cost Management Quality Management Human Resource Management Communications Management Risk Management Procurement Management Integration Management 3 5 3 5 2 2 2 3 4
Inception Phase
Areas of strength:
Project was included to accommodate both through trains and special car and truck carrying shuttle trains Appropriate high level design and respective rough-order-of-magnitude estimates Time estimate to complete the tunneling was finished three months ahead of schedule Each team member had a responsibility for quality
Project Management Area Scope Mangement Time Management Cost Management Quality Management Human Resource Management Communications Management Risk Management Procurement Management Integration Management
Development Phase 2 2 2 5 3 2 3 3 3
Areas of strength:
Project team did a good job in planning the technical equipment and understanding the complexity involved The schedule planning during the development phase was adequate. The project finished a year late but due to things beyond the project teams control The project was delivered with a relatively high degree of quality because the free reign given to IGC, the quality aspects were handled well Most advanced technological equipment and very little margin of error allowed for quality to be an extremely important attribute The focus on fairness was followed by the both governments involved
Project Management Area Scope Management Time Management Cost Management Quality Management Human Resource Management Communications Management Risk Management Procurement Management Integration Management
Implementation Phase 1 2 2 4 3 1 1 2 2
Areas of strength:
This phase gave opportunities to learn lessons for future implementations. The project which faced many financial and operational issues has only one reassurance factor which is quality. The high degree of quality ascertained that project management practices were in place.
D. Closeout Phase :Reflection on overall performance, settlement of claims, financial status, and post-project evaluation.
Evaluation of Project Management during this phase: Rating scale: 5- Excellent, 4-Very Good, 3-Good, 2-Poor, 1-Very poor
Project Management Area Scope Management Time Management Cost Management Quality Management Human Resource Management Communications Management Risk Management Procurement Management Integration Management
Closeout Phase 3 3 2 5 4 3 3 2 3
Areas of strength:
Quality and schedule were two of the components that had significant impact on the overall good impression of the project in the eyes of public and all stakeholders. Scope of the project was increased in this phase Effective Change Management Safety measures helped in maintaining accident rate below industry average Hurdles on account of unavoidable conditions were overcome effectively This phase also had lot of areas from which lessons could have been learnt and would have helped in implementing in future assignments.
Project Management Area Scope Management Time Management Cost Management Quality Management Human Resource Management Communications Management Risk Management Procurement Management Integration Management
Inception Phase 3 5 3 5 2 2 2 3 4
Average 2.25 3.00 2.25 4.75 3.00 2.00 2.25 2.5 3.00
Thank You