TC = TFX + (UVC * X)
Where:
TC = Total Cost
TFC = Total fixed cost (per time period)
UVC = Unit variable cost (per unit of
volume)
X = volume of production
Cost-Volume-Profit Relationship
EQUATION METHOD
Revenues – Variable Costs – Fixed Costs = Operating
Income
X= TFC__
UP – UVC
Break-even revenues
BEP = TFC_____________
Contribution Margin (%)
Where Contribution Margin = (UP-UVC)/UP
BREAKEVEN POINT
I. Cost Concepts
I. Breakeven Point
Required.
Compute the breakeven point for each plan in terms of
tickets sold.
Compute the operating income of the event (a) if 150
people attend, and (b) if 300 people attend. Comment
on your results.
At what level of tickets sold will the two plans have the
CVP
Given:
Selling Price = PhP 8.50/pc.
Variable Cost = PhP 6/pc.
Fixed Costs = PhP400/period
Sales volume = 200 units
Calculate:
BE volume and revenues
Effect of the following changes on income:
10% increase in selling price
10% decrease in variable cost
10% decrease in fixed costs
10% increase in sales volume