Escolar Documentos
Profissional Documentos
Cultura Documentos
The purpose of a pre-feasibility study is to select the preferred option (Base Case) for the project development. This base case option is then developed in sufficient detail to support decisions to commit the additional funds required to: collect additional information carry out a final project feasibility study complete the required project permitting efforts
- Technical feasibility
- Scoping social/environment safeguards analysis - Preliminary financial viability including expectations of required Government financial support - Institutional capability analysis - Identification of next steps required
The pre-feasibility study lays the foundation for the project work scope carried forward into the feasibility study
2008
2011 2021
854,001
905,221 1,076,042
14,441
15,307 18,195
653,862
693,093 873,298
11,057
11,720 14,767
482,362
511,303 607,776
8,157
8,646 10,277
Pphpd: peak period passengers per hour per direction PAX: passengers
Effect of Fare and Travel Time on Demand for Three Alternative Systems
Travel Time Effect on Demand for Three Mass Transit Systems Metro Monorail BRT
Time Savings(min)
Equivalent Value (INR) % savings Effect on Demand
17
2.8 41% +20%
17
2.8 41% +20%
21
3.4 49% +24%
Travel Cost Effect on Demand for Three Mass Transit Systems Metro Proj. Fare % difference from bus Effect On Demand 10.5 50% -25% Monorail 14 100% -50% BRT 7 0 0
The net effect of the differences in system characteristics between the three mass transit systems analyzed on demand is -5% for metro, -30% for monorail, and a +24% for BRT.
Monorail
2500 8910 45 162 1485
BRT
408
17 68
BRT Do not require large capital subsidies Adv: Low capital cost
Metro require large capital subsidies Adv: potentially higher capacity, but this level of capacity is unlikely to be required in Hyderabad High Fare price which will suppress demand
BRT can provide effective mass transit without requiring an increase in fare price. Thus, BRT has the highest potential to increase public transit mode share and relieve congestion in Hyderabad
BRT emissions benefits result from the use of cleaner buses, the shifting of passengers from private vehicles to public transit, and finally the use of fewer buses per passenger trip (because the buses have more capacity and are not stuck in congestion). BRT system would be constructed with safe pedestrian infrastructure in the entire corridor. Traffic fatalities in the Bogot BRT corridor dropped by 98% in the first year.
Bus capacity is basically a function of the length of the bus. The articulated bus used in TransMilenio (above) has become the BRT standard because as the buses get any longer (bi-articulated) they become much more expensive and have difficulties on turns.
Increasing the Load Factor Another way to increase the actual capacity of the system is to increase the number of passengers per bus, or the load factor. Shifting the bus routing system to a trunk and feeder system will increase the load factor of each bus.
In order to increase capacity further, there needs to be an additional lane in each direction at the bus station where the buses can go around other buses that are stopped to load passengers
Configuration 3: Median Two-Way BRT and One Mixed Traffic Lane Per direction. Example: Rouen, France
Configuration4. Curb-side bus lane on One- Way Street. Example: Quito, Ecuador
Configuration 5: Median One-Way BRT with Two Lane, two-way mixed traffic street. Example: Quito, Ecuador
Configuration 6. Side-Aligned TwoWay BRT Adjacent to Two Lane, oneway street. Example: Curitiba, Brazil.
Smart card ticketing systems may be adopted in order to: 1) allow easy discounted transfer to other systems or lines, 2) allow other commercial uses of the smart cards, 3) improve control over the revenue stream For speed and capacity of the BRT system alone, the current manual collection method with an independent collector inside the bus is old fashioned but very efficient External collection would accelerate the boarding process at critical points where many passengers board at the same time, like at terminals
Assessment of Costs
Estimated Capital Costs of 24km BRT Corridor in Hyderabad Per Km costs
Footpaths & Pedestrian Amenities Pavement Cost - Mixed Traffic lanes Pavement Cost - BRT Lanes Moving Poles Moving Transformers Bus Stations Dividers & Medians Overruns, miscellaneous
Lakh Rs/Km
15 25 19 2.5 12 80 0.35 50
#per Km
2 4 2 2 2 2 2 1
Sub-Total
Additional Costs - Terminal Stations 1250 (Lakh Rs. each) 2 (quantity)
98
25
Total Infrastructure
Bus Fleet Acquisition (averaged price of articulated and feeder buses) Land Acquisition - per ha (estimated as per market value)
Next Steps
Establish a permanent project management unit to oversee the implementation of the project, and to appoint a director with significant powers to see the project through
Complete the on-board origin-destination survey of bus passengers, and plug this into a traffic model to get more robust demand estimates for each corridor, to make critical decisions about the importance of route changes Decisions about where land acquisition and road widening are possible and where they are not possible, and to what extent, needs to be made quickly