Escolar Documentos
Profissional Documentos
Cultura Documentos
286
ATK THIOKOL
287
ATK THIOKOL
Paul Teehan
MSFC Resident Office
Bruce Tams
Integration Design Engineering Manager
Ted Shaffner
KSC Operations Manager
Mike Evans
Quality Manager
288
ATK THIOKOL
Interfaces
The integration teams function is to assure ATK and MSFC requirements are incorporated into the motor processing at KSC The hands on work, i.e., build up, stack, close out, integrate, launch and disassemble the boosters is done by USA Because we work with an integrated vehicle and operate in a multi contractor environment our communication is with multiple elements
289
ATK THIOKOL
RSRM Processing
KSC Operations
CCAFS Operations
SRB Stacking
KSC Operations
290
ATK THIOKOL
Jay Jay Siding Suspect Siding Pads
Port Canaveral
291
ATK THIOKOL
SHUTTLE LANDING
HANGAR AF
SRB STACKING
ET STANDALONE
HYPERGOLIC FACILITY
Launch
292
ATK THIOKOL
Delivery
Segments arrive at Jay Jay siding via railcar Cars are 200-ton railcars with fiberglass covers
293
ATK THIOKOL
Segments and exit cones are rotated to vertical (flight orientation) in the rotation building at the Rotation, Processing and Surge Facility (RPSF)
294
ATK THIOKOL
Nozzle severance connection, checkout, and close out GEI and heater power cable installation and test Stiffener ring installation and close out Froth-Pak Application Systems tunnel installation and close out Storage until ready to stack
295
ATK THIOKOL
The aft skirt (USA supplied) is placed in the build up stand and the segment is mated
177 pins are installed and secured with a steel retainer strap
The joint is closed out with a pin band and cork
Cork
296
ATK THIOKOL
Aft exit cone is assembled to the forward exit cone at KSC (Joint No.1)
Phenolic mating surfaces are primed with DC1220 primer prior to assembly Primary and secondary O-rings are installed Exit cone is raised on an elevator and floated on an air bearing for mating The joint is bolted with 96 fasteners Leak test is performed at 83 and 30 psig with the Mass Flow Meter prior to joint backfill
Backfill
O-rings
297
ATK THIOKOL
Joint gap is backfilled (injected) with RTV sealant Spatulas are used to support the tape and aid in a deep fill of the joint Backfill is part of thermal barrier system Joint 1 is a static joint (opens less than 0.0005 in.)
Joint Interface
Backfill Nozzle
298
ATK THIOKOL
The function of the stiffener rings is to prevent case damage from splashdown due to cavity collapse
RT-455 Ablative
Stiffener Ring
Three sections are bolted to the integral stub and joined together by splice plates RT-455 is used to protect fasteners and the painted hardware from heat loads The foam ramp helps deflect the water geyser at splashdown
3 Stiffener Rings
Foam
299
ATK THIOKOL
Systems Tunnel
The aft segment systems tunnel is completed at the RPSF up to the ETA ring prior to transfer to storage
Cables are run and secured
Systems Tunnel
300
ATK THIOKOL
Segment Storage
All segments remain vertical on their pallets until they are transferred to the VAB for stack A KAMAG is used to pick up and transport the pallet Surges protect the hardware from rain, wind, etc.
301
ATK THIOKOL
SHUTTLE LANDING
HANGAR AF
SRB STACKING
ET STANDALONE
HYPERGOLIC FACILITY
Launch
302
ATK THIOKOL
Current joint mate process was developed through testing during the RSRM redesign program Joint assembly objective is to prevent tang/clevis flat-on-flat and protect the o-rings from being cut or damaged: capture feature O-ring is most susceptible Calculations are performed based on case diameter data to determine proper Field Joint Assembly Fixture (FJAF) configuration for each joint mate
Tang
Clevis
303
ATK THIOKOL
Pressure Sensitive Adhesive (PSA) is applied to the insulation interfaces Metal parts are inspected and greased O-rings are installed FJAF configured and installed
Tang
J-Joint
Requirement is for shapes to be within +/-0.210 in. for nominal mate Shape can be improved by adjusting the 4 point beam load distribution
Clevis
304
ATK THIOKOL
Crane lowering rate is controlled to 0.060 in./minute maximum Levelness and rate of engagement are continually monitored during segment lowering FJAF contact with the case is monitored during maximum engagement Leak test of the joint and the vent port plug are the final acceptance of a successful joint mate
305
ATK THIOKOL
Maintain an optimal temperature for O-ring tracking Prevent environmental contaminants such as rainwater from entering the joint area
Cork Joint Temperature Sensor Heater Retainer Strap and Thermal Barrier Joint Heater RT-455 Ablative
Cork
ATK THIOKOL
Forward and aft skirt JPS is primarily to provide thermal protection, weather protection and to retain the pins A flat steel strap is installed over the pin heads Cork is bonded with EA934 and painted with Acrymax paint A grease bead is applied to the clevis/tang exterior interface of the joint
Cork
Grease Bead
307
ATK THIOKOL
S&A Installation
The ignition Safe and Arm (S&A) devices are installed after the RSRM is stacked and the forward skirt is installed
S&A Gasket
Fluorocarbon seals contained within a steel retainer gasket are placed between the S&A and the igniter adapter surface Crushable preload measuring washers are used to control bolt preload Leak test is performed with the bolts partially torqued to prevent false positive due to a metal to metal seal Final torque and cable connections are then performed
S&A
308
ATK THIOKOL
Vehicle Integration
SRB integration
Joint heater and temperature sensor connections Thrust Vector Control (TVC) actuator to nozzle connections
The tank is mated to the SRB The orbiter is mated to the tank The assembled vehicle is rolled to the pad
309
ATK THIOKOL
SHUTTLE LANDING
HANGAR AF
SRB STACKING
ET STANDALONE
HYPERGOLIC FACILITY
Launch
310
ATK THIOKOL
Launch
Launch countdown begins about 3 days prior to launch RSRM systems begin to activate approximately 18 hours prior to launch
S&A rotation test at Launch (L)-60 hours The igniter heater is activated at L-18 hours Operational Pressure Transducers (OPTs) are powered up at L-9 hours Joint heaters are powered up at L-8 hours OPTs are checked out at L-1.5 hours The igniter heater is deactiviated and the S&A armed at L-5 minutes Main engine start is at L-6 sec SRB ignition and hold-down post-firing at L-0
311
ATK THIOKOL
SHUTTLE LANDING
HANGAR AF
SRB STACKING
ET STANDALONE
HYPERGOLIC FACILITY
Launch
312
ATK THIOKOL
Recovery
Ships crew gather parachutes and the frustum Divers install the Diver Operated Plug into the nozzle
The DOP system pumps water from the interior to get the booster into log mode
313
ATK THIOKOL
SRBs are floated into a wharf and lifted onto the disassembly dolly with a straddle lift SRB and RSRM components are disassembled by USA Assessments of the flown hardware are performed by ATK, USA SRB and MSFC representatives
314
ATK THIOKOL
The objective of postfire evaluation (disassembly and assessment) is to verify integrity of recovered RSRM hardware and identify any anomalous conditions in a timely manner
Did the hardware perform as expected? What is it telling us? Were engineering requirements violated, and if so how does this effect performance? Is the condition in family with past observations? Does the condition affect subsequent launches or tests?
315
ATK THIOKOL
Disassembling, evaluating, documenting, reporting, and databasing the condition of postfired RSRM hardware Identifying, reviewing, tracking, and resolving observed abnormal/anomalous conditions or trends
Engineering evaluation, hardware observation limits (allowable and reportable), and photo/video documentation Approved by NASA MSFC
316
ATK THIOKOL
Recovered solid rocket boosters initially assessed, including assessment for missing external insulation
Forward and aft skirts, S&A devices, igniters, nozzles, and exit cones removed and assessed
Case field joints demated and internal insulation assessed S&As disassembled and assessed Arming-Monitor and Barrier-Booster disassembled and assessed Internal nozzle joints demated and assessed
Nozzle bondlines, nozzle liner char/erosion measurements, case and igniter insulation measurements, and factory joints demated and assessed
317
ATK THIOKOL
Nose Inlet Assembly Flex Bearing Snubber Detail: Ring, Segment, Retainer Vented Positive Stop Set Screw Flex Bearing Protector Cowl Insulation Segment Fixed Housing Assembly Flexible Boot Assembly
318
ATK THIOKOL
Any observation that falls outside of established limits or is unexpected is reported on a Squawk (Florida) or Preliminary PFAR (Utah, California) Each Squawk/Preliminary PFAR is presented to SRB/RSRM Postflight Assessment Team (SPAT Board) for review
SPAT Board determines if violation should be elevated to PFAR which requires corrective actions and further reviews
PFAR corrective actions worked by component teams PFAR closure rationale approved by ATK Thiokol and MSFC All PFARs presented in FRR/TRR process including impact and rationale for upcoming flights/tests
319
ATK THIOKOL
(PEEP) (PEEPs)
TWR-50051/2
Defines standard hardware evaluation requirements, observation limits and photographic /video coverage requirements Defines motor-set unique evaluations based on specific changes & issues
Squawk (KSC) Preliminary Postflight Postfire Anomaly Record (Utah)
Elevate to PFAR
ATK THIOKOL
RSRM postfire data is entered into historical database Data is trended with historical data to verify performance within approved limits
321
ATK THIOKOL
Return to Utah
Segments are loaded onto the same type railcars as they were delivered Nozzle components, igniters, stiffener rings and other smaller components are shipped by truck The joint pins remain at KSC and are refurbished by ATK personnel
322