Escolar Documentos
Profissional Documentos
Cultura Documentos
Preliminaries
Mobile Phones: off or in silent mode
Facilities
Duration
10:00am 12noon First session 12 noon 12:30pm Lunch 12:30pm 3pm Second session Conclusion
Program
Part Part Part Part 1 2 3 4 Plan & Prepare Co-ordinate Traffic, Monitor, Remove Radio Operation Clean Up
Principles of Knowledge
Flagman
A road gang of labourers were carrying out flagmans duties, directing traffic, at roadworks on a highway near a bridge. There was one car already stopped at the stop sign when a semi-trailer travelling behind this car failed to see the stop sign and veered to the incorrect side of the road. The semi-trailer then side-swiped a vehicle travelling in the opposite direction, and then continued on to hit three other stationary vehicles (two being table top trucks). The semi-trailer then collided with the rear of the car that was stopped at the flagmans stop sign and also hit the flagman.
Legal Foundations
OH&S laws are State laws
OH&S laws are criminal in nature OH&S laws apply to employers and employees (including volunteers) Cannot insure against a fine / imprisonment
Civil Contractors Federation, Version 1, 3 October 2006
Legal Foundations
OH&S laws have 3 layers: Acts (example: OH&S Act 2004) Regulations Codes
10
The Code
Gazetted on 22 December 2004
11
Application
Clause 4.1 This Code applies to any person conducting, or proposing to conduct any works on a highway (being a road or road related area). Areas on side of roads (footpaths, verges etc) are covered if the risk of a road accident exists.
Civil Contractors Federation, Version 1, 3 October 2006
12
Application
Does the Code apply to firefighters performing burning off duties along a highway? Does it apply to firefighters fighting a fire on a gravel road?
13
Definitions
long term describes works where the traffic management plan is required to operate both day and night and may be left unattended.
14
Definitions
mobile works are works which entail vehicles moving along the roadway continually at a speed significantly lower than other traffic and obstructing or partially obstructing traffic lanes.
15
Definitions
short term are works where the traffic management plan is required only while work personnel are in attendance and generally limited to the duration of a single shift or lesser period where road conditions are returned to normal when the shift or lesser period ends.
16
Definitions
very short term are works that take no longer than five minutes to complete. worksite is an area which includes the work area(s) and any additional length of road required for advance signing, tapers, side-tracks, or other areas needed for associated purposes.
17
Contractor Responsibilities
Clause 10 (4) a) manage traffic at the worksite through the preparation and operation of a traffic management plan. b) carry out risk assessments of each worksite or each generic worksite. c) obtain any necessary approvals for the works and/or the use of certain traffic control devices (eg. speed limit signs, portable traffic signals).
Civil Contractors Federation, Version 1, 3 October 2006
18
Contractor Responsibilities
Clause 10 (4) cont. d) Contractor to manage traffic engineers, road safety auditors and subcontractors. e) Carry out, where appropriate, compliance audits, road safety audits and surveillance on itself or its subcontractors. f) ensure traffic control signs and devices are used for their intended purposes.
19
Contractor Responsibilities
Clause 10 (4) cont. g) Ensure the minimisation of health and safety risks to others and/or himself/herself. h) Comply with any relevant contractual requirements.
20
Main Duty
Clause 11 (2) any person responsible for conducting works on a road that is open to traffic has a duty of care under common law to take all reasonable measures to prevent accident or injury to persons carrying out the works and also to members of the public using the road.
21
22
23
24
Risk Assessment
Clause 17 A systematic approach is necessary to identify areas of risk, to prioritise the critical risks from the lesser risks, and to identify effective ways of eliminating or significantly reducing risks that may have an undesired or unexpected outcome.
25
26
27
Controls
1st 2nd 3rd 4th 5th Eliminate Substitute Engineering Administration Personal Protection (PPE)
28
Major Risk
Clause 18 (4) A major risk at any worksite (whether located on the roadway or roadside) is where an errant vehicle runs out of control and collides with workers or roadworks plan or equipment at the worksite, or another vehicle or person passing through the worksite.
Every effort should be made to eliminate or reduce the risk of such an occurrence.
29
Emergency Works
Clause 44 When traffic speeds are low, whether due to the inherent nature of the road or the effects of the emergency, the initial traffic control may be achieved by using a work vehicle with suitable warning signs or devices mounted on it. After the worksite is protected, other signs and warning devices should be deployed in accordance with the requirements of this Code as determined by the expected duration of the works.
Civil Contractors Federation, Version 1, 3 October 2006
30
31
32
Clearances
Safety barrier in place Local Traffic Road Collector Road or Rural Arterial C Road No No Yes 1.2m to 3.0m Secondary Road or Rural Arterial A and B Road Arterial Road (urban area) or Rural M Road Freeway (urban) No Yes No Yes No Yes 60 60 Speed limit 40 80 40 80 40 80 Worksite Speed Limit (km/h)
33
Clearances
Clearance to Traffic (metres) Within 1.2m Road Type Safety Barrier in place Worksite Speed Limit (km/h) 40
All
No
34
Barriers
A barrier must resist vehicle impact. The proper and most common barrier is the concrete barrier. Table 7 specifies NO GO zones for different barrier types (next slide).
Civil Contractors Federation, Version 1, 3 October 2006
35
Safety Barrier type Precast Concrete Barrier (6 metre Units) with Units not connected Precast Concrete Barrier with Units connected by steel pin or equivalent and a 30 metre minimum length Plastic Water Filled Barrier with TL3 compliance
100 80 60
100 80 60
36
37
38
worksite 2D
39
2D
1.5 to 2D
2D
40
30 metres
41
42
43
Speed Limits
See Clause 73 (4) for speed variations and buffer zone speed reductions Generally speed should be reduced at 20 km/h intervals
44
Speed Limits
Clause 77 if there are traffic controllers, the max speed is 60 kmh. VicRoads / Council must be contacted before speed restrictions are set.
45
Signs
Clause 79 (4) by 1 July 2005 all roadworks signs should be at least Class 1 retroreflective material.
46
Signs
See table D1 on p. 79 onwards for sign sizes and requirements Example:
47
Traffic Controllers
48
Traffic Controllers
Rules for Traffic Controllers (Refer Trainees to Participants Course Notes)
49
Traffic Controllers
50
Traffic Controllers
1. Must be highly visible; high visibility vests must be worn. For night work, light coloured clothing is required with reflective bands on arms and legs as well as around the waist (please be mindful that reflective bands only reflect light, therefore are of no use is there is no light at all, in such cases the area should be illuminated). 2. Must face the on-coming traffic so that he/she is aware of traffic and can react to situations as they arise.
Civil Contractors Federation, Version 1, 3 October 2006
51
Traffic Controllers
3. Must give clear instructions to traffic. He/she must never assume that the motorists will see him/her or that they will obey signals without a clear instruction. 4. Must never leave the position unless relief is given, even if there appears that there is no traffic at that moment. 5. The STOP-SLOW sign should never be displayed without the controller holding it.
52
Traffic Controllers
6. Only give the SLOW sign after being confident that the workers or other motorists from other direction have understood they must stop. 7. Must have an escape route to get out of the way of traffic. 8. Must be able to see on-coming traffic at least at a distance equal to one and a half times the traffic speed (km/h). 9. Always face on-coming traffic.
53
Traffic Controllers
Motorists must obey a STOP sign held by Traffic Controller but can only be fined by police (Road Safety Rule 101).
54
101. Hand-held stop signs 1) A driver approaching a hand-held stop sign must stop before reaching the sign. Penalty: 3 penalty units. 2) The driver must not proceed until the holder of the sign a) no longer displays the sign towards the driver; or b) otherwise indicates that the driver may proceed Penalty: 3 penalty units 3) This rule does not apply to a driver approaching or at a handheld stop sign at a children crossing. Note: Rule 80 defines childrens crossing, and deals with hand-held stop sign at childrens crossings. Hand-held stop signs.
55
Correct Sign
56
57
58
59
60
2D
.5D
61
62
63
64
65
66
67
68
69
Monitoring
Check before you start your duties. What to check. Record Inspections.
70
Removal
Removal occurs in the reverse order of erection Start from the work area out toward the approaches.
71
72
Questions?
73
Practical Assessment
Hand in your
Assessment Workbook first Enrolment form Course Evaluation
Assemble as directed
Civil Contractors Federation, Version 1, 3 October 2006
74
The End
Thank you
Presenter: Nino Capogreco 0402 481 389 nino@contractorss.com
75