Escolar Documentos
Profissional Documentos
Cultura Documentos
February 5, 2013
Sessions
1. 2. 3. 4. 5. About the exam Integration & Scope Management Time & Cost Management Quality & HR Management Communication & Risk Management 6. Procurement Management
Milestone list
Significant point of event and its importance (mandatory/optional)
Discretionary dependencies
Also called / referred as Preferred Logic or Soft Logic Established based on best practices (although many sequences options are acceptable) Can create subjective total float values Is subject to review / modification / removal when fasttracking method is employed
EEF OPA
Resource leveling
Used AFTER critical path method Used when shared or critical resources are only available at certain times, in limited quantities, or to keep resource usage at constant level Used when resources are over-allocated Can cause change to original critical path
Fast tracking
Perform work in parallel (when default in sequential) May increase risk of rework Only work if overlapped activities can shorten duration
Schedule baseline Schedule data (resource requirements, alternative schedules, contingency reserves, etc) PD U
PD U
Basis of estimates
Documentation of basis of the estimate, assumptions, constraints, confidence level, etc
PD U
Reserve analysis Expert judgment Historical relationship (used in analogous and parametric estimation) Funding limit reconciliation
Performance reviews
Trend analysis (improving / deteriorating) Earned value performance (baseline vs. actual)
PD U
Cost estimates
Sample Questions
1. Which of the following is not an input item to the Define Activities process? A. The WBS B. The activity duration C. The project scope statement D. The WBS dictionary
Sample Questions
2. Why should you monitor the activities on the critical path more closely? A. Because each activity on the critical path has a zero float time and thereby poses a schedule risk. B. Because the activities on the critical path need to be performed before the activities on other paths. C. Because the activities on the critical path are critical to the organizations strategy. D. Because the activities on noncritical paths depend upon the activities on the critical path.
Sample Questions
3. You estimate the duration of an activity as five days because an expert told you that it took five days to complete a similar activity in a previous project. Which of the following methods have you used for your activity duration estimate? A. Parametric estimating B. Expert judgment C. Analogous estimating D. Delphi technique
Sample Questions
4. You have developed the schedule for your project, and youve called the kickoff meeting. A team member who is responsible for an activity comes to you and tells you that the activity cannot be performed within the allocated time because some pieces were left out during activity definition. The revised estimate will add two more days to the activity duration, but the activity is not on the critical path. Which of the following actions will you take? A. Go to the team members functional manager and find out whether the team members estimate is correct. B. Accept the new estimate but do not change the schedule. C. Accept the new estimate and update the schedule accordingly. D. Put the new estimate through the integrated change control process.
Sample Questions
5. The amount of time by which an activity can be delayed without changing the project finish date is called: A. Float time B. Lag time C. Grace time D. Activity gradient
Sample Questions
6. Which of the following is the most commonly used network diagramming method? A. Critical path method (CPM) B. Critical chain method (CCM) C. Precedence diagramming method (PDM) D. Arrow diagramming method (ADM)
Sample Questions
7. What is the crashing technique used for? A. Network diagramming B. Duration compression C. Cost reduction D. Activity sequencing
Sample Questions
8. Which of the following is a true statement about the critical path? A. Each activity on the critical path has zero float time. B. It controls the project finish date. C. It controls the project start date. D. It is the shortest sequence in the network diagram.
Sample Questions
9. In your research project on tourism, you must collect data before the tourist season ends because the project involves interviewing tourists. The datacollection activity has which of the following kinds of dependency? A. Mandatory B. External C. Internal D. Discretionary
Sample Questions
10. You know from a network diagram that Activity B cannot start until Activity A is finished. Which of the following are true? A. Activities A and B have a start-to-finish dependency. B. Activities A and B have a finish-to-start dependency. C. Activity B has a mandatory dependency on Activity A. D. Activities A and B are on a critical path.
Sample Questions
11. You are the project manager of a project that is running behind schedule. The project sponsor is very unhappy at the new finish date that you proposed, but he has accepted it. However, you also requested extra funds to support the extended time of work, and the sponsor has refused to supply more funds and is threatening to cancel the project if you cannot finish the project within the planned budget. What are your options? A. Crashing B. Fast tracking C. Asking the executive management for a new sponsor D. Speaking with the customer directly without involving the sponsor to see whether the customer can increase the budget
Sample Questions
12. Consider the following network diagram. Which of the following is the critical path?
Sample Questions
13. What is the float for Activity G? A. 3 B. 2 C. 1 D. 0
Sample Questions
14. What is the length of the critical path in the network diagram? A. 20 B. 21 C. 22 D. 31
Sample Questions
15. You use a three-point estimate for activity duration estimating. An activity has a duration of 9 days for an optimistic scenario, 18 days for a pessimistic scenario, and 12 days for the most likely scenario. Which of the following will you take as the duration estimate for this activity if you use the PERT analysis? A. 13 days B. 12.5 days C. 12 days D. 18 days
Sample Questions
16. Which of the following processes will you perform first? A. Plan Procurements B. Determine Budget C. Estimate Costs D. Develop Schedule
Sample Questions
17. Your supervisor has asked you to put some contingency reserve into your project plans. Which of the following is not true about contingency reserve? A. These are the funds and not the time. B. These are not included in the cost baseline. C. These are included in the budget. D. These are not used in earned value measurements.
Sample Questions
18. You are a project manager at a company that is a seller for another company. You are conducting a weekly and presenting that the project has CPI = 1.3 and SPI = 1.8 What does it mean for the project? A. Behind schedule and under cost B. Ahead of schedule and over budget C. Behind schedule and over budget D. Ahead of schedule and under budget
Sample Questions
19. Ron Collins is the project manager for a biotechnology company. He is outsourcing a part of the project to a foreign company for over 3 months when he is called for a steering committee meeting because of cost irregularities. Ron notices that many charges are made to the project budget without his approval. What should Ron calculate? A. CV B. SPI C. SV D. CPI
Sample Questions
20. Management has asked you to produce a chart that depicts the resource needs for all the activities in the project. Which of the following charts is management referring to? A. The project organizational chart B. The WBS C. The roles and responsibilities chart D. The responsibility assignment matrix
Sample Questions
21. Which of the following is not an output of the Determine Budget process? A. Cost performance baseline B. Project funding requirements C. Project schedule D. Project document updates
Sample Questions
22. Which of the following is a true statement about the estimate cost process? A. It is created by the human resources department. B. It is a tool for team development. C. It is created by the project manager with help from project team to produce output of the cost management planning efforts. D. It is provided by the project sponsor.
Sample Questions
23. You are in the process of developing the cost baseline for your project. What is the name of this process? A. Determine Budget B. Develop Cost Baseline C. Estimate Costs D. Develop Budget
Sample Questions
24. Your project is in the planning stage. You first want to make the cost estimates for the planned project activities, and then you want to aggregate those costs. Which process will you perform first? A. Determine Budget B. Develop Human Resource Plan C. Estimate Costs D. Develop Budget