Escolar Documentos
Profissional Documentos
Cultura Documentos
Terminology
Activity/task - Smallest unit of work
definite duration logic relationships with other activities in the project resource consumption an associated cost
Terminology (contd.)
Work package
Inputs
Predecessors Preconditions Resources Requirements/specifications
Task
Statement of work Time Cost Responsibility Quality assurance Risk
Outcomes
Deliverables results
Terminology (contd.)
Responsibility matrix
Matrix with task/activity, person, type of responsibility
Schedule
Project schedule used by management to plan and review the project Task schedule specific activities necessary to complete
Network Diagrams
Describes projects in terms of sequences of activities and events AON or Precedence Diagramming Method (CPM) AOA (PERT)
Predecessor-Successor Relationships
Mandatory cannot be reversed Discretionary External an activity must follow some event/activity not in the network
4
3 8 1 3 1
D
E F G H I
C
D E F G H
2
1 4 3 8 1
A
B,C D E F G
2
6 7 11 14 22
4
7 11 14 22 23
I
J
3
1
H
I
23
26
26
27
Rel. J
Finish
Slack
Total slack the amount of time an activity can be delayed without delaying the project Difference between late start and early start or late finish and early finish schedules Critical activities: those with 0 slack Free slack the amount of time an activity can be delayed without delaying the early start of a successor activity Free slack = ES EF -1 There can be more than one CP for a project
Slack Calculation
Activity Early Start Early Finish Late Start Late Finish Slack Critical?
A
B C D E F G H I j
0
2 2 6 7 11 14 22 23 26
2
6 4 7 11 14 22 23 26 27
0
2 4 6 7 11 14 22 23 26
2
6 6 7 11 14 22 23 26 27
0
0 2 0 0 0 0 0 0 0
Yes
Yes No Yes Yes Yes Yes Yes Yes Yes
Critical path
Longest path from the project start node to end node
Other notations
Box type notation EF = ES +duration - 1 LS = LF duration + 1
Buffers
A means to ensure that critical activities are completed on time It is the time included in the schedule to protect against unanticipated delays and to allow early starts Buffer is different from slack Types of buffers
Project buffers Feeding buffers placed at each point where a non-critical activity is related to a critical activity Resource buffers Strategic resource buffers
Resource Leveling
Involves extending schedules so that particular resources are not over-scheduled CP assumes that unlimited resources are available Quality of project management is measured by the proportion of waste time encountered but Crashing Resource smoothing
Precedence Relationships
Finish-to-start (FS): Start only when the predecessor finished Lags are indicated as FS=n Start-to-start (SS): Start only when the predecessor started Finish-to-finish (FF): Finish only when the predecessor finished Start-to-finish (SF): Finish only when the predecessor started
Resource Constraints
Resource Allocation Resource Workload Resource Loading
Resource Levelling
Time-Cost Relationship
Cost slope = (Cc-Cn)/(Tc-Tn) Reduce Project Duration
Select the activity with smallest cost slope
PERT
A technique to estimate the likelihood of project completion te=(a+4m+b)/6 V= 2 =((b-a)/6)^2 Expected duration of the project is the sum of expected activity durations along the critical path Variance in project duration is the sum of the variances of the activity durations along the CP, that is Vp= V
cp
Issues in PERT
Ignores human behavior Activity durations are independent The three estimates are guesses unless supported by historical data