Escolar Documentos
Profissional Documentos
Cultura Documentos
An Overview
Islanding
Deliberate act of Isolation of a running Unit/s with compatible loads to save the Unit/s from tripping when Grid is having unstable condition.
Islanding Scheme
At CPP-II
Single Unit followed by Double Unit Islanding
FCX Relay connected to 132kV Islanding Bus CVT
Sensing Under frequency during islanded condition
Islanding Conditions
Directional O/C ( E/F) combined with Under Voltage
Over Current
Directional Forward ( towards line) IEC E Inv, 300A ( Each Feeder), TMS-0.125
150A, 0.125 for One Generator / One Feeder condition
Under Voltage
Definite Time 52.66 kV ( 70%) Phase- Neutral Time Delay- 0 s
Islanding Conditions
Reverse Power combined with U/F
Reverse Power
Directional Forward ( towards line) 28.8MW ( Each Feeder) for 5 Sec
Under Frequency
48 Hz for 1.0 Sec
Islanding Conditions
Under Voltage (pure)
60 kV ( 80%) ( Phase to Neutral) Definite Time ; Time delay 1.5 sec
Over Voltage
91.2 kV ( 120%) ( Phase to Neutral)
Definite Time ; Time delay 2.0 sec
Sequence Logic
HSL FDR-1 OFF HSL FDR-2 OFF
AND
RM-2
d5
1A
1B
d4 DU
OR
CPP-1
CPP-2
d1
b1 SU
2A
2B
d2/d3 MSDS-2
Sequence Logic
SU d9 SU MSDS-3
SU
TRIP SEC-2 B/C
RM-1
DU
d8 CPP-1
DU
Sequence Logic
AND
C22
DU
U1 U2
DU DU
U1 AND AND
FCX
RH29
MSDS-2
U2
G1
U1 AND
G2
SU SU
U2 U1 AND
OR
U2
U1
U2
OR
SU
AND AND
C21
CPP-1
CPP-2
Synchronisation
Evolution
Inception 1980 MSDS-3 1987 1989-90
RM-1 Grid
CPP-2
MSDS-3
MSDS-2 MSDS-2
RM-2
1997
CPP-1-GRID
33 KV GRID
1987
CPP-2 units commissioned No Islanding scheme was available for CPP-2 units.
1989
Single Unit Islanding scheme commissioned
U/F, -dF/dt & U/V isolation provided
Scheme suggested by Consultant (TCE) Although Double Unit Islanding scheme was provided by consultant, it was not taken into service.
2000
DOC Islanding put into service
Current feedback to grid combined with Under Voltage initiated isolation Isolation of HSL Fdr- 1&2 at MSDS-II IEC SI curve for DOC
2005
DOC /DEF combined with U/V implemented for Single Unit Islanding also.
2006
Islanding scheme as in service now implemented.
Directional O/C & E/F relays introduced in grid side of HSL fdr.
To prevent tripping in case of grid fault.
Dynamic relay setting for single Unit/ single Feeder configuration. Dedicated Islanding Panel commissioned in MSDS-2
Constraints.
Post islanding stability of CPP-2 units is not satisfactory.
No of failure of Units after successful isolation is very high
Problems attributed to Governing & Excitation system
Constraints.
Constraints of Islanding Load
Fluctuating Loads have to be shed during islanded condition
Constraints
Difficult synchronization process
Synchronization facility not available in Common Coupling point ( MSD-2) Multiple operations required for synchronization. Multiple asynchronous points
Actions
Dedicated control cables between islanding locations
Status of Grid side CB of HSL feeders and CPP-2 unit CB shall be available No. of interposing relays shall be reduced- Islanding commands shall be transmitted radially.
Cable Laying job under progress- completion expected by Mar07