Engro Sindh Coal Power Project

Project Overview by MISL

Company Structure Overview


Engro Powergen was incorporated in 2008, as a

fully owned subsidiary of Engro, to develop power projects in Pakistan.


The Sindh Engro Coal Mining Company Limited

(SECMC) is a JV between the Government of Sindh and Engro Powergen, to mine coal from Thar Block II.

MISL Confidential

Sindh Engro Coal Mining Company


SECMCL Ownership Stake

40 60 Government of Sindh (GoS)

Engro PowerGen Limited (EPL)

MISL Confidential

Feasibility Studies
Study Detailed Feasibility Study Hydrological Study Drilling Fieldwork Environmental & Social Impact Assessment Ground Water Modeling & Mitigating Strategy for ESIA Company Sinocoal, China Northeast Coal Bureau, China Deep Rock Drilling, Pakistan Hagler Bailly Pakistan/ SRK, UK RWE, Germany

Financial Model and Economic Viability Assessment

RWE, Germany
4 MISL Confidential

Thar Coal Reserves


Thar Desert contains the worlds 7th largest

coal reserves, totaling an estimated 175 billion tons of Lignite grade coal.
This is equivalent to 50 billion ton of crude

oil, more than Iran & Saudi Arabias combined oil reserves.
Phased development can lead to 400 600

mt /year coal mining in 20 years


5 MISL Confidential

Coal Quality
The coal beds of variable thickness ranging from 0.20

22.81 meters are developed. The maximum number of coal seams found in some of the drill holes is 20. The cumulative thickness of the coal beds range from 0.2 to 36 meters. Claystone invariably forms the roof and the floor rock of the coal beds.
The coal is brownish black, black and grayish black in

colour. It is poorly to well cleared and compact. The quality of coal is better where percentage of clay is nominal.
6 MISL Confidential

Project Scope
Mine & Power plant to be developed in parallel :
The production capacity of Coal mine will be 22.5

Mt/a to support 4000 MW of power generation capacity for 70 years in parallel with 1200 MW Power Plant

Phase 1 will be development of a 6.5 Mt/a Coal mine


In subsequent phases, chemical and fertilizer plants

would be set-up as part of a Mega Petro-Chemical Complex which would be supported by additional coal mining
7 MISL Confidential

Project Scope (continued)


Power transmission line of 500 KV will be

planned and constructed for 1000 mw power dispersal to power grid network.
Coal Gasification System with a 36-42 Hi-

Pressure Gas Transmission Pipeline will be planned and constructed to connect to the SSGC Network at Hyderabad / Jamshoro.

MISL Confidential

Project Timeline
Detailed Feasibility Study completed by

September 2010
Financial Close is expected by December

2012
Coal Mining and Power Generation

Project will start operation by December 2016


9 MISL Confidential