Escolar Documentos
Profissional Documentos
Cultura Documentos
: : : :
ELECTRICITY ACTS
Indian Electricity Act, 1910, The Electricity (Supply) Act, 1948 The Electricity Regulatory Commissions Act,
1998 CERC AND STATE ERCs
discriminatory open access , Power Trading , Tariff Regulations of ERCs and Tariff Policy and National Electricity Policy of GOI etc.,
GENERATION
TRANSMISSION
DISTRIBUTION
TRANSMISSION OF ELECTRICITY
TRANSMISSION :
Transmission of electricity is defined as the bulk transfer of power at high voltage (132KV and above) over long distances. A power transmission system is referred to as GRID
transmission companies
Central Transmission Utility (CTU) State Transmission Utilities (STU)
transmission between states and between regions STUs are responsible for transmission within states. Private Transmission Licensees
October 1991 - Eastern and the Northeastern regional grids were synchronized March 2002 West synchronized with the above mentioned regional grids through
AC lines (Central Grid).
In August 2006 North synchronized with the Central grid, to form the NEW grid. There are five regional grids and two freq In 2014, the whole of India will operate as a single grid with the SR grid
synchronised with the NEW grid.
PRICING PROCESS
Pricing nechanism involves two
distinct processes:
Determination of Transmission Charges (Servicing the investments) Sharing of Transmission charges among the beneficiaries (many use)
HISTORICAL BACKGROUND
METHODS OF TRANSMISSION
PRICING
MW- MILE METHOD POSTAGE STAMP METHOD (ZONAL, INCREMENTAL , NATIONAL, REGIONAL)
mechanism of sharing transmission charges was based on regional postage stamp system / method All States in the Region were sharing the transmission charges on a Regional pooled basis, in the ratio of the quantum of power drawn through the Inter-State transmission system.
transmission service charges were done prorata on energy drawal basis. Post ABT the apportioning to different beneficiaries was on the basis of capacity allocation (MW) out of the total capacity handled by the transmission system in the region. The quantum of power allocation is calculated as the sum of entitlements (firm share plus share from unallocated quota of power in the Central Generating Stations) from Central Generating Stations
MERITS
This is the simplest form of transmission pricing. Even with the introduction of open access in transmission this mechanism has served the needs of the system well.
DEMERITS
However, with the integration of the regional grids, and the objective of the policy and regulatory framework to provide access to sellers and buyers, an appropriate change in the pricing mechanism which is sensitive to quantum of flow, distance and direction of flow is required. One of the problems in postage stamp method is that of pan caking of charges-Term used to describe stacking up of charges in a transmission system due to repeated application of charges for different regions. This can be understood with the following example cited below:
willing to supply power in Maharashtra (WR). According to postage system, the total charges and total transmission losses of the system for each region is pooled and is spread over the users of the system on per MW basis. A Ltd. will have to bear the transmission charges for three regions involved namely NER-ER-WR (there is no direct link in NER-WR), While a local generator of WR may use own dedicated line or may pay only one region charges for supply within the region. Thus, a generator in other region becomes grossly uncompetitive in the sellers region. If a State Transmission Utility (STU) network is also used, then charges and losses of such STU would further be loaded, which may vary widely among states.
against the underlying theory of assuming full displacement from injection to delivery point, due to many generators and consumers connected in between the two. The system worked well in pre-reforms era where there was only government owned agencies in both generation and demand and there were identifiable lines. system, post 2012, would be a deeply meshed network, making it almost impossible and impractical to trace the destination to source and underlying routes.
With the reforms and private sector players coming in, the
power plant developers and customers to decide the optimal location of the power plant by comparing the costs of fuel transportation and the cost of electricity
REVISED FRAMEWORK
The beginning of the revised framework for
sharing of transmission charges and losses lies in the National Electricity Policy (NEP) notified by the Central Government under Section 3 of the Act vide Resolution No.23/40/2004-R&R(Vol.II) dated 12.1.2005 provides as under:
To facilitate cost effective transmission of power across the region, a national transmission tariff framework needs to be implemented by CERC. The tariff mechanism would be sensitive to distance, direction and related to quantum of flow.
MARGINAL PARTICIPATION
It analyses how flow in the grid is
modified when minor changes are introduced in the production or consumption of one unit of power(1 MW) Marginal Participation sensitivities are obtained UK , Norway, Brazil, Columbia have implemented.
AVERAGE PARTICIPATION
POWER TRACING: For every individual generator a number of
physical paths are constructed from the point of injection to reach the various loads. Similar calculations are performed for demands tracing upstream to reach the generators. Wide range for PoC charges, little international exp.
HYBRID APPROACH
In the Hybrid method, distributed slack buses
(responding nodes) are selected using AP method and the MP method is used to capture network utilisation, by injection/withdrawal at each node.
geographically and electrically proximate demand first and then the demands which are geographically and electrically distant.
PoC REGIME
CERC Consultation Paper Apr. 2009 Tr. Sharing Regulations June 2010 Stake holders consultations
/workshops Implementation / Validation Committees / 50% RPS+50% PoC /SLAB RATES Made Effective from July 2011 2011-2012 SR/NEW 2012-13(H Y) 5 Regions
standard deviation Reasons: Reduce Heart burn Easy to comprehend and implement
SLAB RATES
YEAR 2011-12
NEW GRID /MW/Month(P/unit) /MW/Month(P/unit) 70000 (10) 85000 (12) 100000 (14) SR GRID
ISTS licensees
(NLDC)
WebNetUse Software
POC RATES
POWERGRID APPROVED YTC FOR 2013-14(SR): TANGEDCO ENTITLEMENT OF CGS POWER : TOTAL POWER HANDLED BY SR GRID : TN SHARE : ANNUAL TR CHARGES TO TN ACCOUNT : MONTHLY TR CHARGES PAYABLE :
Basic Network data pertaining to the network elements and the generation and load at the various network nodes. electricity system, electrical plant or line below 132 kV except where generators are connected to the grid at 110 kV.
AC load flows using the Basic Network, nodal generation and nodal demand. Basic Network along with the converged load flow results for various grid conditions shall be validated by the validation committee. Approved Basic Network, nodal generation and nodal demand data shall form the base for computation of Marginal Participation factors and loss allocation factors.
nodes shall be computed based on the Yearly Transmission Charge (YTC) apportioned to each of the lines of the ISTS Licensees. aggregate the charges for geographically and electrically contiguous nodes on the ISTS to create zones, in order to arrive at uniform zonal charge in Rs / MW / month.
zones for generation and demand. Such zoning shall be governed by the following considerations:
(i) Zones shall contain relevant nodes whose costs (as determined from the output from the Hybrid method) are within the same range. (ii) The nodes within zones shall be combined in a manner such that they are geographically and electrically proximate. The demand zones shall normally be the state control areas except in the case of North Eastern States, which are considered as a single demand zone. Generation zones are formed by combining the generators connected to the ISTS.
BILLING
BILLING
The billing for ISTS charges for all Designated
ISTS Customers shall be on the basis of Rs./MW/Month, and shall be raised by the CTU in four parts. use of the transmission assets of the ISTS Licensees based on the Point of Connection methodology. This part of the bill shall be computed as: Approved Injection X PoC for injection
For Generators:
BILLING
The second part of the bill shall recover
charges for Additional Approved Medium Term Open Access similar to above formula. The second part of the bill shall be raised on the Designated ISTS Customers along with the first part of the bill.
BILLING
The third part of the bill shall be used to
adjust any variations in interest rates, FERV, rescheduling of commissioning of transmission assets, etc. as allowed by the Commission for any ISTS Transmission Licensee. This part of the bill shall be raised on first working day of September and first working day of March for the previous six months. Deviations shall be billed separately by the CTU as fourth part, bill based on the RTA issued by the RPCs. (25% extra for deviations from approved injection/withdrawal)
DEFINITIONS
ISTS: INTER STATE TRANSMISSION
SYSTEM
Any system for the conveyance of electricity by means of a transmission line from the territory of one state to another state. The conveyance of electricity across the territory of an intervening state as well as conveyance within the state which is incidental to such interstate transmission of energy The transmission of electricity within the territory of state on a system built ,owned, operated, maintained or controlled by CTU
Users of any element of the ISTS and includes Generators STU SEB or load serving entities directly connected to ISTS and Bulk consumer Transmission system which has the regulatory approval of the Commission as being used for interstate transmission of power
DEEMED ISTS:
Transmission assets of non-ISTS licensees ,which have been certified by RPCs as being used for inter state transmission.
BASIC NETWORK
The power system of the country at voltage levels 765 KV,400 Kv,220Kv and 132KV and HVDC Transmission network and all generator and loads connected to it. A substation or a switchyard of a generator Annual Transmission Charges approved by the Commission for all the transmission projects of a transmission licensee, Provisional/ Determined as per CERC T&C Benchmarked Adopted
NODE
LOSS ALLOCATION FACTOR Loss allocation Factor of a bus measures the losses attributed to that node . PARTICIPATION FACTOR Participation Factor of a node in any transmission line means the percentage of usage of that line by a node, whether a generator node or a demand node. PoC CHARGING METHOD It is the methodology of computation of sharing ISTS charges and losses amongst DICs , which depends on the location of the node in the grid . PoC TRANSMISSION CHARGES Nodal/Zonal charges determined using the PoC charging method. UNIFORM CHARGE
The charge determined by dividing the YTC of the ISTS licensee by the sum of the approved injection and approved withdrawal from the grid alternatively defined as POSTAGE STAMP Charge.
UNIFORM LOSS This means the energy loss and is accounted for by providing a differential
AVERAGE PARTICIPATION