Escolar Documentos
Profissional Documentos
Cultura Documentos
Madhav Madhira
Permeability scale
Radial flow
Excavation in sandy soils: a. Sandy Soils & b. Deep wall to increase Head loss
Excavation in rock like conditions: a. Pumping only & b. Pumping + Grout Cut-off
India-Teesta dam
Dewatering
Construction below GWT Removal of Water Safe & Stable Open Excavation Long Term Integrity of Structure Major Component of Modern Construction below GL K > 10-4 cm/s
Dewatering
Typically considered contractors responsibility He chooses the method Ensures it operated correctly Specifications therefore:
Typically brief
Emphasis is on assignment of responsibility
Design Alternatives
Shallow Excavations
Perimeter trenches Sumps Well point systems Mechanical shields such as sheet piling
Perimeter Trenches
Effective if water migrates laterally If trench can be dug to sufficient depth to drain site Pumping of trenches then may be required
Well Points
Well Points
Ground water is extracted Wells rarely more than 20 feet deep If deeper than 20 feet:
May be placed on series of benches or steps Due to problems trying to lift water from depths
Two Step Well Point System Separate Pump Provided for Each Step
Cased Borehole Using well drilling rig Drilled to lower than required dewatering depth Use of submersible pump
Jet System:
Has two pipes in well One is in-flow pipe at considerable pressure A venturi system at bottom of well creates a vacuum As water from in-flow pipe passes thru out-flow pipe This vacuum pulls any water in bottom of well into
Only one pipe extended into well Pump creates a vacuum in manifold and Water is sucked up pipe into manifold Then discharged a distance from excavation Will operate at 20 foot depth or less
Vacuum Dewatering
Electro-Osmosis
Relief Wells
Foundation Drains
Blanket Drains
Examples of Drains
Interceptor Drains
Filters
Cut-Off Methods
Cut-Off Methods 2
Cut-Off Methods 3
Sheet Piling
Sheet Piling
Mechanical Shields
Types of Caissons
Watertight Structure:
In which work is performed underwater Area is dewatered
Drilled Caisson:
Deep foundation constructed in place by drilling &
placing concrete
Used for:
Small structures (few feet in diameter)
Un-watering Caisson
Cofferdams
Structures built in place Exclude water & earth from excavation Single walled cofferdam:
Excavation small enough to Permit internal bracing
Steel sheet piling enclosure constructed Tremie concrete seal poured Cofferdam un-watered as internal bracing installed Pier construction completed in dry
Cofferdam
Cellular Cofferdam
Excavation size precludes cross bracing Typically circular cells at perimeter May be un-watered as soon as enclosure complete
Slurry Trench
Digging narrow deep trench Filling trench with stiff clay slurry May need to dig thru the slurry in soil prone to caving in. In some cases concrete is pumped to bottom of trench then concrete displaces slurry as it rises Other cases slurry is thickened then allowed to dry The clay filled trench forms almost an impenetrable barrier to moisture migration Excavation must be kept back distance from trench
Used only in rare instances due to high costs Involves: Drilling closely spaced holes:
Around perimeter of area to be excavated
Inserting piping Pumping a Super-cooled refrigerant solution thru pipes Two pipes required in each hole
To provide circulation of refrigerant
If there is a flow of water through the ground to be frozen the freezing time will be increased by reason of the continuing supply of heat energy and, if the flow is large and the water temperature high, freezing may be completely inhibited.
Once the freezing process has begun, monitoring is required to ensure formation of the barrier wall and also to verify when freezing is complete. During the drilling process, temperaturemonitoring pipes are installed to measure the ground temperature. Below are the techniques for temporary support of a tunnel heading by freezing:
Secant Piles
View of Excavation
DSM Pattern
DSM Wall