Escolar Documentos
Profissional Documentos
Cultura Documentos
Project Planning
A plan must be stated as a
Set of targets
The achievement or non achievement can be measured Target start and completion date for each activity Visibility of start and completion of activities
Achieved by producing something tangible such as a product or deliverable
Objectives of planning
Feasibility assessment
Resource allocation
Detailed costing Motivation Co-ordination
Feasibility assessment
Is the project possible:
within required timescales Resource constraints
Project plans allow us to forecast a completion date with any reasonable knowledge of its achievability. If a project is estimated for 2 work years effort, could it be done with eight people in three months?
Resource allocation
What is the most effective ways of allocating resources to the project and when should they be available? The Project plan allows us to investigate the relationship between timescales and resource availability
Detailed costing
How much will the project cost and when is the expenditure likely to take place? Detailed estimates of costs and timelines can be achieved after producing: activity plan resource schedule
Motivation
Providing targets and
being seen to monitor achievement against targets is an effective way of motivating staff particularly when they have been involved in setting those targets in the first place.
Co-ordination
Project plans provide effective communication and co-ordination among teams Particularly where staff may need to be transferred between project teams or different departments
When to plan
Feasibility study
Estimate timescales Risk
Not achieving target completion dates Not keeping within budget
Monitoring and replanning must continue to correct any drift that might prevent meeting time or cost targets
10
Project Schedules
Construct an ideal activity plan
Plan activities where resources are not a constraint
Risk Analysis
Identify potential problems Might suggest alterations to the ideal plan
Resource allocation
May place constraints on when activities can be carried out
Schedule production
Indicates planned start and completion dates, resources requirements for each activity
11
Identifying activities
Activity based approach:
12
Analyse
Design
Build
Data Design
Process Design
Physical Design
13
1.4 Management 1.4.1 Project Management 1.4.2 Administrative Support 1.4.3 Management Tools 1.4.4 Management Reviews 1.4.5 Management Training
1.5 Product Assurance 1.5.1 Configuration Management 1.5.2 Library Operations 1.5.3 Interface Control 1.5.4 Data Management 1.5.5 Quality Assurance 1.5.6 Quality Control 1.6 Operations and Support
Etc ...
14
Techniques
Milestones Gantt charts PERT
15
Milestones
Project estimation is the business of establishing project milestones. An essential aspect of project milestones is that they are specific measurable events. We estimate Checkpoints or milestones to allow progress to be periodically reviewed.
16
Milestones
TEAM PROJECT - Recommended Milestone Management Plan Task/Deliverable Prep Cover, Executive Summary, Contents, etc. Assigned Plan Date Actual Date Status
17
Gantt Charts
These are a graphical project management technique.
A Gantt chart is a bar chart, with each bar representing a project task. The horizontal axis represents time & should include dates to signify the start & end of the particular tasks that we list along the vertical axis.
18
2.
Reverse scheduling
Establish a project deadline & then schedule backward from that date. This means the tasks, their duration, & resources must be chosen to ensure that we can complete the project by the deadline. We use the reverse scheduling strategy in most information system projects.
19
20
2. A nice feature of Gantt charts is the ability to factor a top-level chart into one or more lower levels of chart.
22
A Gantt chart is a horizontal bar chart, with each bar representing a project task.
The horizontal axis represents time and should include dates to signify the start and end of the particular tasks that we list along the vertical axis. On a Gantt chart, the horizontal axis is a calendar timeline. After we have identified the project team, we can also establish personal calendars to block out individual commitments. Unlike PERT charts, which we will look at next, they do not show the dependency of one task on another.
23
For example, we can enter the number of staff required to do a task into the bar on the diagram.
Resources complete the tasks that you have included in a Gantt Chart. Resources are people, material, and tools that you assign to the completion of a task. We can assign costs to resources to assist in budgeting for the project. If we record actual time spent on tasks, we can compare budgets to actual expenses.
24
25