Escolar Documentos
Profissional Documentos
Cultura Documentos
Engineering activities
SCADA & APPS System
Review of basic Process documents (Process Design Basis, P&IDs) as applicable for SCADA Conceptual design SCADA Design Basis Firming up of system configuration and specifications of SCADA & APPS Furnishing room sizes, layout, etc for control room, to Arch. Dept. Preparation of Material Requisition (MR) for systems Technical bid evaluation of bids Preparation of Purchase Requisition of system Review of vendors critical detailed engineering documents Participation in factory acceptance tests Site assistance as required Preparation of man-hour estimates, MR schedules, progress reports
2
OBJECTIVES
TO MONITOR & CONTROL THE PIPELINE FACILITIES VIZ. PUMP/ COMPRESSOR STATIONS, DESPATCH & RECEIVING TERMINALS, PIGGING/ SV/ CP STATIONS ETC. IN A TIMELY MANNER FROM A CENTRALIZED LOCATION wrt: Monitoring of Flow, Pressure, Temperature, Density, Electrical parameters etc. Pumps/ compressors status Status of all station & Intermediate valves Readiness to dispatch products and receipt of products Pumps/ compressors start/ stop, valves open/close commands Set point downloading to controllers CENTRALIZED ALARM & EVENT MANAGEMENT AND OPERATION & MANAGEMENT REPORTS FOR ALL THE DISTRIBUTED PIPELINE FACILITIES. PROVIDE REMOTE-EYE TO THE PIPELINE OPERATION
3
OBJECTIVES (Contd..)
Centralized checking of status of various pipeline facilities wrt
Readiness to despatch products Pumping status Readiness for receipt & distribution of products Status of valves
to ensure that the requested control action will not result in unsafe pipeline operation i.e. the above confirming tasks can be defined in SCADA system to ensure that operator cannot operate the pumps & valves in a manner that could jeopardize the safe operation of the pipeline To ensure proper pipeline shutdown by closing various pipeline facilities in orderly manner as per pre-defined sequence
OBJECTIVES (Contd.)
TO FACILITATE RUNNING OF APPLICATION SOFTWARE PACKAGES FOR RELIABLE & EFFICIENT OPERATION OF THE PIPELINES VIZ.
LIQUID PIPELINES LEAK DETECTION & LOCATION PIPELINE EFFICIENCY INVENTORY ANALYSIS BATCH TRACKING PUMP OPTIMISATION
GAS PIPELINES LEAK DETECTION & LOCATION PIPELINE EFFICIENCY INVENTORY ANALYSIS PREDICTIVE ANALYSIS CONTINGENCY ANALYSIS PLANNING FUNCTION COMPRESSOR FUEL OPTIMIZATION
5
MONITORING CONTROL ALARM & EVENT DETECTION MAN-MACHINE INTERFACE TRENDING REPORT GENERATION DATA ARCHIVING COMM. HANDLING & ERROR RECOVERY DATABASE CONFIGURATION & ENGINEERING FUNCTIONS SYSTEM MAINTENANCE & SECURITY INTEGRATION WITH APPLICATION SOFTWARE
Computer Workstations
Separate server & MMI machines with client server concept implemented at hardware & software level
Remote Workstations Communication Controller Units Remote Telemetry Units WAN Routers
Master Station
Projection System
Dual Local Area network Communication Controller Units Data channels as part of Telecom Network
To Second Master Station
RTU 1
IS for DT/ Pump Station/ Compressor station
RTU 2
IS for SV/ CP/ RP station
RTU 3
RTU n
FC
IS for IP station
FC
IS:Instrumentation System
10
11
12
13
14
15
Engineering activities
SCADA & APPS System
Review of basic Process documents (Process Design Basis, P&IDs) as applicable for SCADA Conceptual design SCADA Design Basis Firming up of system configuration and specifications of SCADA & APPS Furnishing room sizes, layout, etc for control room, to Arch. Dept. Preparation of Material Requisition (MR) for systems Technical bid evaluation of bids Preparation of Purchase Requisition of system Review of vendors critical detailed engineering documents Participation in factory acceptance tests Site assistance as required Preparation of man-hour estimates, MR schedules, progress reports
16
17
18
19
REMOTE WORKSTATIONS
Remote workstation is normally envisaged at manned stations (other than Master Station location): Pump/ Compressor stations Terminals
to provide complete SCADA & APPS capability (graphics & reports) so that the operators at these locations are fully informed of:
All the monitoring variables in the pipeline Status of various pipeline equipments Alarms for the complete pipeline facilities
20
21
22
APPLICATION SOFTWARE
LEAK DETECTION MODULES
23
VOLUME BALANCE
BASED ON What goes in must come out! EMPLOYS ACCURATE FLOW MEASUREMENTS AT BOTH ENDS Flow In is RECONCILED WITH Flow Out CONSIDERING PIPELINE INVENTORY TO CALCULATE FLOW IMBALANCE V (Leak) = V (Inlet) - V (Outlet) - V (Change in Inventory) LEAK DETECTION IF FLOW IMBALANCE EXCEEDS PREDEFINED LIMIT
24
25
TRANSIENT MODELLING
EMPLOYS MATHEMATICAL MODEL OF THE PIPELINE (EQ. OF MASS, MOMENTUM, ENERGY, STATE) PIPELINE MODEL REQUIRES FLOW, PRESSURE, TEMPERATURE, DENSITY ( PROPERTY ) INPUTS PREDICTED VALUES ARE COMPARED WITH FIELD VALUES AND ALARM IS GENERATED IF WEIGHTED DEVIATION EXCEEDS PREDEFINED IMBALANCE LIMITS LEAK LOCATION IS DONE BY FINDING THE BEST LOCATION WHERE THE SIMULATED PIPELINE STATE MATCHES WITH CURRENT STATE
26
DETECT, LOCATE AND SIZE THE LEAK UNDER STEADY STATE AND EVEN UNDER TRANSIENT CONDITIONS GRADUALLY OCCURING LEAKS CAN BE DETECTED INSTRUMENT DRIFT ANALYSIS, DYNAMIC LINE PACK CALCULATIONS ARE PROVIDED
Note : Transient Modeling enveloping volume balance could additionally provide higher sensitivity for leak detection and would be better suited for pipelines with low pressure gradient
27
29
Generates current pipeline inventory information (accounting for the variations in line pack on the basis of pressure, temp. & density profiles) Comparison of inventory and packing rates against minimum & maximum allowable limits to generate alarms for limit violations, thereby facilitating the dispatcher in responding to changes in supply & demand
30
PIPELINE EFFICIENCY
PURPOSE
To detect whether pipeline friction losses in any section have exceeded defined limits
FUNCTION
Calculate actual friction factor based upon flow, pressure measurements at end points of pipeline section and product density profile as generated by product module Pipeline efficiency factor is compared to a predefined limit violation of limit results in an alarm This module gives requirements for carrying out pipeline pigging operation
31
32
Client
GAIL IPCL ADNOC (AbuDhabi ) PIL OIL India HPCL
Product
Natural Gas C2/ C3, C3, Lean Gas Natural gas
Length (km)
1700 160 150
Vendor
SSI/ Texas Instruments USA L&N Australia Serck Controls, UK Siemens ABB Norway ECIL/ Texas Instruments USA
33
80 1160 165
Sajjah-Layyah P/L
MMPL
SEWA (Sharjah)
BPCL
Natural Gas
Multi-Product
80
250
VVPL JLPL
HPCL GAIL
Multi-Product LPG
350 1200
Maqta-JebelAli P/L
CCKPL
ADNOC
Natural Gas
115
Serck Controls, UK
Neles Automation, Canada Foxboro, Italy
34
Petronet-CCK
Multi-product
290
Hazira-Dahej P/L
IPCL
100
35
FACILITIES PROVIDED
VOICE COMMUNICATION
Subscriber Dialing Facilities Direct dialing facilities between the various attended stations and between each unattended station to the nearest attended station. Conference Facilities To enable selective/all-call connection amongst the attended and unattended stations. Engineering Order Wire (EOW) One or two EOW circuits provided to facilitate maintenance of the system at all attended and all unattended stations. Facsimile communication Facsimile Communication is provided amongst all attended stations.
36
DATA COMMUNICATION
Dedicated low speed data channels (19.2 Kbps) are configured at all TELECOM stations to enable remote operation, monitoring and shutdown of the pipeline through SCADA System. High Speed (2 Mbps) data channels between SCADA SMCS and SCADA Sub-Master/ Remote workstations High-speed data channel for NMC-NMC Communication Certain identified stations/offices are interlinked with video conferencing/CCTV facility.
Depending on the volume of voice and data transmission, the optimal communication system is selected from amongst a number of cable and wireless systems e.g.
Cable System :- Paired Telephone Cable or Optical Fibre Cable Wireless System: - VHF/UFH/Microwave Communication system/ Satellite Communication system [The system chosen depends on the particular requirements of a project like terrain, number of stations, telecom requirements etc.
37
Small overall diameter of the cable leads to efficient space utilization Light weight and flexibility of the cable makes cable-laying easy and comparatively cheap. The dielectric medium of fibre is immune to electromagnetic interference and thus enjoys noise immunity. Silica fibres offer low loss and as such very long repeater spacing can be envisaged leading to lower overall system cost. Very high communication bandwidth. Addition of a new station in existing communication system can be done easily.
38
39
Multiple sources Extra control activities for operator to optimise generation Operator controls are complex
Distribution Side
Multiple load centres at multiple locations Requires complete network status in real time to be available to operator to allow safe and reliable operation Requires centralised control of distribution switchgear with the help of network overview.
40
Tripping of captive electric generator Tripping of utility grid connection Tripping of steam generator Reactive power imbalance Load control and Tie line control Voltage & reactive power control Electric load shedding Steam load shedding It is necessary to assign shedding priority to all electric loads and process steam consumers in ascending level of severity to plant process
41
Substation-wise On line status of feeders in SLD pictorials Typical displayed parameters: Voltage, active and reactive power, power factor and frequency in selected cases Typically, data acquired and updated every 2-3 sec. Hourly and shift logs ( or as desired by client) in client specified formats Typical logged parameters: Voltage, power(s), energy consumption, peak power, power factor etc. Log reports can be unit-wise, substation-wise or switchboard-wise as feasible Alarms generated due to abnormalities in field Alarms generated due to abnormalities in any ECS subsystem
42
Allocates reactive power share of various sources such as utility grid, captive generators, shunt capacitors and synchronous motors. Generate set points (or raise / lower)for excitation of Generators and synchronous motors
43
Raise / lower grid transformer OLTC Advise on switching ON / OFF of shunt capacitor banks subject to the constraints to be met to the extent feasible: All machines within capability limits Voltage profile in the network within prescribed limits Grid power factor close to unity Infrequent change of grid transformer OLTC Identify all possible island conditions in distribution network Monitor the network in real time to detect if any of the island conditions have occurred. Estimate the power shortfall in the island. Disconnect some loads connected from this island starting from lowest priority such that power shortfall is eliminated. Matching of power shortfall with quantum of load shed. Accurate. Secondary (slow) load shedding based on under frequency sensing Slow load shedding on grid transformer overload and crossing contract demand limit Steam shedding not implemented in ECS
44
APPLICATION SOFTWARE
LEAK DETECTION MODULES
SUPPLEMENTARY MODULES
VOLUME BALANCE
BASED ON What goes in must come out! EMPLOYS ACCURATE FLOW MEASUREMENTS AT BOTH ENDS Flow In is RECONCILED WITH Flow Out CONSIDERING PIPELINE INVENTORY TO CALCULATE FLOW IMBALANCE V (Leak) = V (Inlet) - V (Outlet) - V (Change in Inventory) LEAK DETECTION IF FLOW IMBALANCE EXCEEDS PREDEFINED LIMIT
46
TRANSIENT MODELLING
EMPLOYS MATHEMATICAL MODEL OF THE PIPELINE (EQ.
OF MASS, MOMENTUM, ENERGY, STATE)
PIPELINE MODEL REQUIRES FLOW, PRESSURE, TEMPERATURE, DENSITY ( PROPERTY ) INPUTS PREDICTED VALUES ARE COMPARED WITH FIELD VALUES AND LEAK ALERT IS GENERATED IF WEIGHTED DEVIATION REMAINS ABOVE THE PREDEFINED IMBALANCE LIMITS FOR DURATION OF TIME. MULTIPLE LEAK ALERTS ARE INTEGRATED FOR GENERATION OF CONFIRMED LEAK ALARM (PREVENTING FALSE LEAK ALARMS). LEAK LOCATION IS DONE BY FINDING THE BEST LOCATION WHERE THE SIMULATED PIPELINE PRESSURE PROFILE MATCHES WITH TELEMETERED PRESSURE PROFILE
48
RETROSPECTIVE DETECT, LOCATE AND SIZE THE LEAK UNDER STEADY STATE AND EVEN UNDER TRANSIENT CONDITIONS CAN AUTOMATICALLY ADJUST THE THRESHOLDS/ IMBALANCE LIMITS FOR VARIOUS TRANSIENT CONDITIONS (PUMPS START/ STOP, VALVES OPEN/ CLOSE, PIG TRACKING etc.) TO PREVENT FALSE LEAK ALARMS GRADUALLY OCCURRING LEAKS CAN BE DETECTED INSTRUMENT DRIFT ANALYSIS, DYNAMIC LINE PACK CALCULATIONS ARE PROVIDED
49
Dispatch a batch to the pipeline (density variation/ manifold valves openings and together with batch schedule) Determine the batch volume (based on actual flow measurement and by density change) Monitors the extent of mixing as a function of time along the length of the pipeline Update the position of batch fronts (based on velocity profile generated by the Transient model) Monitors whether the actual batch transportation is taking place in accordance with the batch schedule
50
Batch is approaching destination Batch has reached destination Batch size exceeds the schedule batch size New batch launched not being identified on the schedule or not in proposed sequence identified by schedule Discrepancy between actual time of batch arrival and expected time of arrival exceeding the limits
51
OPTIMIZATION MODULES
The economic & efficient operation of the pipeline can be carried out by utilizing optimization modules viz. Pump station optimization module ( e.g. for variable speed drives of pumps) & Compressor fuel optimization module (for natural gas pipelines) Pump station Optimization Module Utilizes the pipeline hydraulics & pump performance module to determine the pump stations operation that will achieve the desired delivery flow rate requirements with the objective function of lowest electrical energy consumption The real time monitoring & control in SCADA can also take care of contingencies arising out of closure of the receipt terminals & tripping of pumps with consequent adjustment of speed set points (pump stations) & flow set points (receipt terminals) to permit continuation of pipeline operation.
52
53
SUPPLEMENTRY MODULES
Predictive Module Predicts the future operating conditions of the pipeline based on the current state of the pipeline Warn the operator of impending short term constraint violations and future consequences of continuation of current operating conditions Planning Module Helps the operator to maintain the new operating plans covering the operational aspects of reduction or increase of gas supply & gas delivery requirements, deviation of current state with the forecast state etc. by analyzing different strategies & presenting the feasible ones to the operator
54
55
PIPELINE EFFICIENCY
PURPOSE To detect whether pipeline friction losses in any section have exceeded defined limits FUNCTION Calculate actual friction factor based upon flow, pressure measurements at end points of pipeline section and product density profile as generated by product module Pipeline efficiency factor is compared to a predefined limit violation of limit results in an alarm This module gives requirements/ guidelines for carrying out pipeline pigging operation
56