PROJECT MANAGEMENT
CONCEPTS

Academic Computing Services 2009
Project, Defined
A project is an endeavor to accomplish a specific objective through
a unique set of interrelated tasks and the effective utilization of
resources.
It has a well-defined objective stated in terms of scope, schedule, and
costs.
Project s are born when a need is identified by the customer the
people or organization willing to provide funds to have the need
satisfied.
It is the people (project manager and project team), not the procedures
and techniques, that are critical to accomplishing the project objective.
Procedures and techniques are merely tools to help the people do their
jobs.
Academic Computing Services 2009
Examples of Projects
Planning a wedding
Designing and implementing a computer system
Hosting a holiday party
Designing and producing a brochure
Executing an environmental clean-up of a contaminated site
Holding a high school reunion
Performing a series of surgeries on an accident victim
Academic Computing Services 2009

Academic Computing Services 2009
Phases of the Project Life Cycle 1
The first phase involves the identification of a
need, problem, or opportunity.
The need and requirements are usually written by the customer into
a document called a request for proposal (RFP).
Academic Computing Services 2009
Phases of the Project Life Cycle 2
The second phase is the development of a
proposed solution to the need or problem.
This phase results in the submission of a proposal.
The customer and the winning contractor negotiate and sign
a contract (agreement).
Academic Computing Services 2009
Phases of the Project Life Cycle 3
The third phase is performing the project.
Different types of resources are utilized
Results in the accomplishment of the project objective
Academic Computing Services 2009
Phases of the Project Life Cycle 4
The final phase is terminating the project.
Perform close-out activities
Evaluate performance
Invite customer feedback
Academic Computing Services 2009
The Project Management Process
The project management process means planning the work and
then working the plan.
7 steps of planning
1. Clearly define the project objective.
2. Divide and subdivide the project scope into major pieces
3. Define the specific activities for each piece (work package)
4. Graphically portray the activities that need to be performed fro each work
package in order to accomplish the project objective in the form of
network diagram.
5. Make a time estimate for how long it will take to complete each activity
resources needed.
6. Make a cost estimate for each activity.
7. Calculate a project schedule and budget to determine whether the project
can be completed within the required time, with the allotted founds, and
with the available resources.


Academic Computing Services 2009
Project Control Process
Academic Computing Services 2009
Work Breakdown Structure (WBS)
The second step is to determine what
activities need to be performed.
A list of all the activities must be developed.
The WBS is a hierarchical tree of end items to
be accomplished.
A work item is one small piece of the project.
A work package is the lowest-level item.
Academic Computing Services 2009

Academic Computing Services 2009
Microsoft Project WBS

Academic Computing Services 2009
1. Start new project
Turn on the Project Guide
On the Tools menu, click Options, and then click the Interface
tab.
In the Project Guide settings section, select the Display
Project Guide check box.
Manually set up a new project
Academic Computing Services 2009
Project Project Information
or View Turn on project guide

http://office.microsoft.com/en-us/project/HA102639631033.aspx
Academic Computing Services 2009
Tools - Options

Academic Computing Services 2009

Academic Computing Services 2009
2. Tasks
There are four major types of tasks:
1. Summary tasks - contain subtasks and their
related properties
2. Subtasks - are smaller tasks that are a part of a
summary task
3. Recurring tasks - are tasks that occur at
regular intervals
4. Milestones - are tasks that are set to zero
duration and are like interim goals in the project

Academic Computing Services 2009
Add tasks

Academic Computing Services 2009
Insert new task

Academic Computing Services 2009
Outlining tasks

Academic Computing Services 2009
Tools Options - check Show project summary task
Academic Computing Services 2009
Academic Computing Services 2009
Predecessor
Academic Computing Services 2009
Tasks can be linked in four ways
Finish-Start FS Predecessor finishes and the other
starts
Start-Finish S-F Task begins at the same time as its
predecessor
Finish-Finish F-F Both tasks finish at the same time
Start-Start S-S Start of the predecessor determines
when the other starts


Academic Computing Services 2009
Constraints
Certain tasks need to be completed within a
certain date.
Intermediate deadlines may need to be
specified.
By assigning constraints to a task you can
account for scheduling problems.
There are about 8 types of constraints and
they come under the flexible or inflexible
category.
Academic Computing Services 2009

Academic Computing Services 2009
3. Managing task

Academic Computing Services 2009
Defining a Timeline
Find an optimistic value, D(o),
a pessimistic value, D(p) and
a realistic value, D(r) .

Then: Duration = ( D(o) + D(p) + 4 x D(r) ) / 6

Academic Computing Services 2009
The importance of tracking progress
Techniques to manage projects effectively:
Critical Path Management (CPM) and
Program Evaluation and Review Techniques (PERT).
They are similar and you will now often find the technique referred to as:
CPM/PERT.
The technique involves using network models to trace the links between
tasks and to identify the tasks which are critical to meeting the deadlines.
Once you've identified the critical path, any delay on any part of the critical
path will cause a delay in the whole project.
It is where managers must concentrate their efforts.
In MS Project, you use the Tracking Gantt diagram to show the critical
path in red and you can see the PERT diagram by looking at the Network
view.



Academic Computing Services 2009
Gantt Chart View critical path
A Gantt chart is a type of bar chart that illustrates a
project schedule.
Critical path: View More views - Detail Gant
Academic Computing Services 2009
PERT diagram - Network view

Academic Computing Services 2009
Views
Views allow you to examine your project from
different angles based on what information you want
displayed at any given time.
You can use a combination of views in the same
window at the same time.
Project Views are categorized into two types:
Task Views (5 types)
Resource Views (3 types)

Academic Computing Services 2009
Saving a baseline
Baseline plan: The original project plans used to
track progress on a project.
The baseline plan is a snapshot of your schedule at
the time that you save the baseline and includes
information about tasks, resources, and assignments.
You can set a baseline for your project, enabling you
to compare your progress with the original plan and
any additional baselines you set at milestones
throughout your project.
Academic Computing Services 2009
Saving a Baseline

Tools Tracking Save Baseline
http://office.microsoft.com/home/video.aspx?assetid=ES102776241033&width=1024&height=768&startindex=0&CTT=11
&Origin=HA102751251033&app=WINPROJ&ver=12
Academic Computing Services 2009 Academic Computing Services 2009
RESOURCES
Academic Computing Services 2009
Manage the project resources:
Resources are of three types:
work resources, material resources and cost resources.
Work resources complete tasks by expending time on them. They are usually people and
equipment that have been assigned to work on the project (you track their participation by the
amount of time they spend).
Material resources are supplies and stocks that are needed to complete a project. You assign
material resources by the quantity that you need: two tons of gravel or 300 gallons of diesel
fuel, for instance. Because materials aren't measured by time, quantities usually affect only the
cost of your project. Materials affect dates or duration only when you have to wait for those
materials to become available.
Cost. Cost resources are the new kid on the Project 2007 block, and they're strictly cost; no
time, no quantitiesjust dollars. Expenses, such as travel or fees, increase the project price
tag, but they aren't associated with work or material resources.

You must start by identifying the resources available along with their
costs.
Resource costs will be multiplied by duration to calculate project costs.
You have to open the Resource sheet to specify the project resources
and costs.
people
equipment
supplies
Academic Computing Services 2009
Academic Computing Services 2009
Fields in the Resource Sheet may be blank or contain different types of information
depending on the type of resource. For example, a work resource doesn't have a Material
label, and costs are calculated initially as dollars per hour. Material resources have a cost
per unitper pound, gallon, or pieceand the Material label field defines the units. Cost
resources receive a value only when you assign them to tasks.
Academic Computing Services 2009
Academic Computing Services 2009
Academic Computing Services 2009
Use the Detail Gantt view to find
slack (float)
On the View menu, click More Views.
In the Views list, click Detail Gantt, and then
click Apply.
On the View menu, point to Table, and then
click Schedule. In the chart portion of the
view, slack appears as thin bars to the right of
tasks, with slack values adjoining the regular
Gantt bars.

Academic Computing Services 2009

Academic Computing Services 2009
To shorten a project schedule
Reduce duration of activities on critical path
More resources
Change their scope
Academic Computing Services 2009
Technically Constrained Activity Sequence
Academic Computing Services 2009
Resource-Constrained Planning
Academic Computing Services 2009
Painting Project Showing Needed Resources
Academic Computing Services 2009
Create a budget for your project
Step 1: Create budget resources for your
project
Step 2: Assign the budget resources to the
project summary task
Step 3: Enter values for the budget resources
Step 4: Categorize resource costs according
to their budget type
Step 5: Group resources to view how they
compare against the budget

Academic Computing Services 2009
Step 1: Create budget resources for
your project
Create Budget-Travel and Budget-Labor on your resource
sheet
View Resource Sheet
Academic Computing Services 2009

Check
the check
box for
Budget
Academic Computing Services 2009
Step 2: Assign the budget resources
to the project summary task
Gent chart view Tools Options View Tab Show
project summary task (check box)
Task is added to the top of the project list. Select this task.
Click on Button Assign Resources
Select the two budget resources you created earlier and
click Assign
Academic Computing Services 2009
Step 3: Enter values for the budget
resources
View Resource Usage view
Add Budget Cost and Budget Work fields (columns):
Insert Column Budget Cost and Budget Work
Add values for travel and Labor cost
Academic Computing Services 2009

Add: 15,000 for Budget-Travel and 30,000
for Budget-Labor (Budget Work column)
Academic Computing Services 2009
Step 4: Categorize resource costs
according to their budget type
Create custom filed (column)
Open Resource Sheet view
Tools Customize Fields
Choose Resource text filed and rename: Budget Type
Academic Computing Services 2009

Select Option Button: Roll down unless
manually entered
Add field to the resource sheet view: Insert column choose
Budget Type column ( you can now identify your resources as labor
or travel
Academic Computing Services 2009

Academic Computing Services 2009
Step 5: Group resources to view how
they compare against the budget
Resource Usage view
Project Group by: No Group Customize Group By -
Select the Budget Type field
Academic Computing Services 2009

Academic Computing Services 2009
Viewing Project Cost Information
Right click the Select All button and click Cost
Or
View Table: Entry Cost

Academic Computing Services 2009
Reports
Cost Report: Reports - Reports Costs Cash Flow:
Edit Column list
Project Summary report: Reports Overview Project
Summary
Academic Computing Services 2009
Resource Usage Report
Academic Computing Services 2009
Current Activity Reports