Line Balancing is the process of assigning tasks to workstations in such a way that the workstations have approximately equal time requirements. Design of Product Layout: Line Balancing Cycle time is the maximum time allowed at each workstation to complete its set of tasks on a unit. Cycle Time Output capacity = OT CT OT operating time per day D = Desired output rate CT = cycle time = OT D
Determine Maximum Output
N = (D)( t) OT t = sum of task times
Determine the Minimum Number
of Workstations Required Precedence diagram: Tool used in line balancing to display elemental tasks and sequence requirements A Simple Precedence Diagram a b c d e 0.1 min. 0.7 min. 1.0 min. 0.5 min. 0.2 min. Precedence Diagram Arrange tasks shown in Figure 1 into three workstations. Use a cycle time of 1.0 minute Assign tasks in order of the most number of followers Example 1: Assembly Line Balancing
Workstation
Time Remaining
Eligible
Assign Task Revised Time Remaining
Station Idle Time 1 1.0 0.9 0.2 a, c c none a c - 0.9 0.2
0.2 2 1.0 b b 0.0 0.0 3 1.0 0.5 0.3 d e - d e - 0.5 0.3
0.3 0.5 Example 1 Solution Percent idle time = Idle time per cycle (N)(CT) Efficiency = 1 Percent idle time Calculate Percent Idle Time Assign tasks in order of most following tasks. Count the number of tasks that follow Assign tasks in order of greatest positional weight. Positional weight is the sum of each tasks time and the times of all following tasks. Some Heuristic (intuitive) Rules: Line Balancing Rules c d a b e f g h 0.2 0.2 0.3 0.8 0.6 1.0 0.4 0.3 Example 2 Station 1 Station 2 Station 3 Station 4 a b e f d g h c Solution to Example 2 Design of Process Layouts Alternatives Qualitative Method Links some criteria to the closeness required between a pair of resources Computer packages such as ALDEP and CORELAP are available Quantitative Method Uses some quantitative performance measures for assessing the impact of a layout design Seeks to arrive at the best layout design by optimising on this performance measure One of the popular method used in CRAFT Performance evaluation models using computer simulation techniques Design of process layouts Qualitative method Department 1 Department 2 Department 3 Department 4 Department 5 Department 6 O U A U O A O U O I X O E U A Value Closeness A Absolutely necessary E Especially Important I Important O Ordinary closeness OK U Unimportant X Undesirable
Design of Process Layout Quantitative Method C ij = Cost per unit of transporting a unit distance from department i to department j F ij = Inter-departmental flow between department i and department j D ij = Distance between department i and department j n = Number of departments to be laid out The total cost of the plan is given by:
One can model the above as a mathematical programming problem with the objective function of minimizing the total cost of the plan