Você está na página 1de 19

Chapter 8: Strategy and Analysis

Using NPV

Where are the sources of positive NPV


Introduction to real options and decisions trees

8-1

Introduction to Real Options

Traditional NPV analysis (Chapters 4, 6, and 7)


usually does not address the decisions that managers
have after a project has been accepted.

In reality, capital budgeting and project management is


typically dynamic, rather than static in nature.

Real options exist when managers can influence the


size and riskiness of a projects cash flows by taking
different actions during the projects life.
Real option analysis incorporates typical NPV
budgeting analysis and also incorporates opportunities
resulting from managers decisions.
8-2

Real options and decision trees,


an example

A new proposed project would cost $500 now (t=0) in order to


explore the projects feasibility.
Next year, it will cost an additional $1500 at t=1 upon final
acceptance, and is expected to produce cash flows in years 2
through 6 (from t=2 to t=6).
Our current (t=0) forecast for cash flows CF2 through CF6 is:

70% probability of $1000 per year


30% probability of $400 per year

Next year (t=1), we will know cash flows CF2 through CF6 with
certainty; they will be either $1000 or $400 per year.

8-3

Traditional or static NPV

Calculate the expected cash flows CF2 through CF6

E(CF) = (0.70)(1000) + (0.30)(400) = $820 per year

A time line of expected cash flows is shown below.


t=0

t=1

t=2

t=3

t=4

t=5

t=6

CF0 = -500

CF1 = -1500

CF2 = 820

CF3 = 820

CF4 = 820

CF5 = 820

CF5 = 820

8-4

Traditional or static NPV

Now calculate the NPV of the projects timeline.


This projects NPV consists of the following items:

$500 spent today


$1500 spent at t=1
Five expected cash flows of $820 each from t=2 to t=6 (a
n=5 year annuity). The PV annuity formula produces a value
for t=1, which must be discounted by n=1 years from t=1 to
t=0.

1
820

5
0.15

0.15
1

0.15
1500

NPV0 - 500
1 0.15
1 0.15
NPV0 585.884
8-5

Traditional or static NPV

This estimated NPV of $585.884 is incomplete. It


assumes the continuation of the project from t=0 to
termination at t=6 if the project is accepted today.
All we have is the NPV of expected future cash flows,
ignoring the option to abandon the project.
In reality, if $500 is spent today, then next year at t=1,
the firm has the option to either spend $1500 to
continue, or abandon the project.

The decision at t=1 to continue or abandon depends on


whether CF2 to CF6 are then known to be $1000 or $400 per
year. If the project is believed to be negative NPV at t=1,
then it will be cancelled at that time.
8-6

NPV including the option to


abandon

When the $1500 expenditure is made at t=1, we know


if CF2 through CF6 is either $1000 or $400 per year.
We first calculate the projects NPV1, for CF1 through
CF6 being $1000 per year. We deem this as the
success NPV.

From todays (t=1) perspective, this success NPV has a


p=70% chance of occurring.

1
NPV1 - 1500 1000

5
0
.
15
0.151 0.15

NPV1 - 1500 (1000)(3.352155) $1852.155


8-7

NPV including the option to


abandon

Next we calculate the projects NPV1, for CF1


through CF6 being $400 per year. We deem this
as the failure NPV.

From todays (t=1) perspective, this failure NPV


has a p=30% chance of occurring.

1
NPV1 - 1500 400

5
0
.
15
0.151 0.15

NPV1 - 1500 (400)(3.352155) - $159.138


8-8

NPV including the option to


abandon

What is todays (t=0) decision, based on this new


scenario analysis of next years likelihood of p=70%
success and p=30% failure?

NPV0 = -500 + (0.7)[success NPV1/(1+r)] + (0.3)[failure


NPV1/(1+r)]

We will not go forward next year with negative NPV1,


therefore the failure NPV1 is ZERO, as the project will
just be cancelled at t=1 if CF2 through CF6 are then
known to be $400 per year.

PV0 = -500 + (0.7)[1852/(1+0.15)] + (0.3)[0] = $627.399


8-9

NPV including the option to


abandon

Note that this dynamic NPV=$627.399 is greater than


the earlier static NPV=$585.884. The $41.52
difference is the value of the option to abandon.
A decision tree of the project is shown below.
success,
p=70%

ACCEPT,
NPV1=$1852

conduct
$500 study
failure,
p=30%

REJECT,
NPV1=$0

do nothing

8-10

Second example of incorporating


the option to abandon

A project has a k=10% cost of capital. If accepted, the project


costs $1100 today at t=0.
Next year, at t=1, we will know whether or not the project is
actually a success or failure. Today at t=0, all we know are the
probabilities of future success or failure.

Success: probability=50%, and the project will generate cash flows of


$180 per year forever (perpetuity) if a success.
Failure: probability=50%, and the project will generate cash flows of
$30 per year forever (perpetuity) if a failure.
Project X can be abandoned at t=1 for $500 salvage value.

CFs here are perpetuities. The PV of a perpetuity is always


PV=CF/r
8-11

Second example, NPV while


ignoring the option to abandon

Expected annual CF = (p success)(180) + (p


failure)(30) = (0.5)(180) + (0.5)(30) = $105

The expected cash flow is $105 per year forever.

NPV0 = -1100 + 105/0.1 = -1100 + 1050 = -$50

If treated as a project that is allowed to continue


forever after t=0 acceptance, the expected NPV is
negative.
Under this type of analysis (ignoring the
abandonment option), the project should be rejected.
8-12

Second example

A tree diagram of the project is shown below. There


are really two NPVs for this project; one for success
and one for failure, each with a probability of 50%.
Success,
p=50%

CF = $180/year, forever,
PV0 = 180/0.1 = $1800

Investment costs
$1100 today
Failure,
p=50%

CF = $30/year, forever,
PV0 = 30/0.1 = $300
Or abandon at t=1 for $500
8-13

Second example

The first timeline shows the project, if successful and, of course, never
abandoned.
The second timeline shows the project, if an eventual failure and not
abandoned.
The third timeline shows the project, if known to be a failure at t=1 and
abandoned at t=1 for $500 (the projects t=1 cash flow will be earned).
t=0
CF0 = -1100

t=0
CF0 = -1100

t=0
CF0 = -1100

t=1

t=2

CF1 = 180

CF2 = 180

t=1

t=2

CF1 = 30

CF2 = 30

t=1
CF1 = 30
+ 500 salvage

8-14

Second example

NPV0 (if success) = -1100 + 180/0.1 = -1100 + 1800 =


$700
NPV0 (if failure): this issue must be further addressed
in detail. Either the project can be continued at t=1 or
it can be abandoned and the assets sold for $500
salvage value.
First, calculate the NPV0 if as though the project is
continued in operation as a failure with the $30 annual
cash flows:

Failure NPV0 = -1100 + 30/0.1 = -1100 + 300 = -$800


8-15

Second example

Now investigate abandoning the project at t=1


if we realize it is a failure. At t=1 one cash flow
(the only project cash flow since the project is
then cancelled) of $30 is received and then the
assets are sold for $500. This abandon upon
failure NPV0 is thus:

NPV0 = -1100 + 30/(1+0.1) + 500/(1+0.1) = -1100


+ 481.18 = -$618.18 if abandoned at t=1.

If a failure at t=1, the abandonment NPV is


higher than the NPV if allowed to continue.
8-16

Second example

If accepted today, at t=0, there is a 50% chance that the


project will be allowed to operate forever, and a 50%
chance that it will be abandoned for a $500 salvage
value.
Dynamic NPV0 = (0.5)[success NPV0] + (0.5)[failure
NPV0]
Dynamic NPV0 = (0.5)[700] + (0.5)[-618.18] = $40.91.
The project should now be accepted since the NPV
becomes positive when we allow for project
abandonment.
8-17

Second example

The NPV0 = $50 if the project is treated as


continuing forever after acceptance.
The NPV0 = $40.91 when we include the
decision to abandon at t=1 when the project
becomes a failure.
The difference between these two NPVs is
called the value of the option to abandon.

Value of option = 40.91 (50) = $90.91


8-18

Types of Real Options

Investment timing options

Abandonment/shutdown options

Two example were previously shown

Growth/expansion options

Often, the option to delay investment is valuable if market or


technology conditions are expected to improve.

May be valuable if the demand turns out to be greater than


expected

Flexibility options

Projects may be more valuable if an allowance is made for


greater future modifications.
8-19

Você também pode gostar