Você está na página 1de 20

Street and Local Roads

Inspection and Acceptance of


Alternative Pavements

1.Inspections
Pre-Construction Meeting

Permits
Maintenance of Traffic
Lane closures/detours
Progress schedule
Required Transmittals
Pavement design
Source of Materials
Required inspections and
testing

2.Material used

STEEL REINFORCEMENT BARS


CEMENT
WATER
SOIL
CEMENT CONCRETE MATERIALS
PORPORATION
Chemical admixtures

3.Inspections and
Testing

(a)SUBGRADE
Proof roll subgrade
Undercut any unsuitable or
failing areas/stabilize
materials (if required)
Backfill of undercut area
with approved materials
Perform appropriate
moisture and density
testing
Verify approved typical
section.

(b)SUB-BASE
Proof roll
Remove/correct any
undulating areas
Perform appropriate
moisture and
density tests
Verify approved
typical section
Verify stone depths

(c)FORM WORK

(if required)
Ensure forms are clean
and oiled
Ensure flanges are not
bent
Ensure forms are
sufficiently braced
Check vertical and
horizontal alignment of all
forms
Perform depth checks

(d.)Continuously Reinforced
Concrete Pavement

(e.)Alternatives
Pre-cast Concrete Pavement

(F)Inspections
CONCRETE PLACEMENT
Prior to placement ensure
appropriate expansion joints
Testing for slump and air
Rate:
Make control/lab cylinders
Ensure concrete is cured
properly and in accordance with
approved method.
Verify temperatures, dispatch
times, cold joints

(G)Alternatives
Continuous Concrete Pavement

(H)Alternatives
Roller Compacted Concrete Pavement

(I)Curing
Curing requires adequate
Moisture
Temperature
Time
If any of these factors are
neglected, the desired
properties will not develop

(J)Inspections and Testing


FINAL INSPECTIONS
Ensure all forms are removed
Verify all laboratory cylinder
breaks are in compliance
Verify line and grade.
Straight edge joints for
compliance
Perform an overall visual
inspection of the pavement
surface condition, condition of
joint material etc

Any Queries??
Thank You

Precast Concrete Pavement


Precast concrete pavement eliminates the need
for on-site cure time by using prefabricated
concrete panels. The panels are made at a
specialized pre-casting facility ahead of time, then
hauled to the construction site and installed as
needed. The result is a pavement that can be
opened to traffic almost immediately after panel
installation, without compromising the durability
and long-term performance of the pavement
Precast concrete has long been a proven as
durable pavement, providing 30 years of service
life or longer with minimal maintenance.

Continuous Concrete Pavement


Benefits from using unreinforced concrete
slabs are lower construction cost with the
saving on mesh reinforcement and the
potential for continuous pouring.
The contraction joints of unreinforced
concrete slabs should be relatively
maintenance free.

Roller Compacted Concrete


Roller-compacted concrete, or RCC, takes its name from the
construction method used to build it. It's placed with conventional or
high-density asphalt paving equipment, then compacted with rollers.
RCC has the same basic ingredient as conventional concrete: cement,
water, and aggregates, such as gravel or crushed stone.

But unlike conventional concrete, it's a drier mixstiff enough to be


compacted by vibratory rollers. Typically, RCC is constructed without
joints. It needs neither forms nor finishing, nor does it contain dowels or
steel reinforcing.
Withstands extremely heavy loads, no rutting.
Will not deteriorate from spills of fuel or hydraulic leaks.
Will not soften when exposed to high temperatures.
Open to traffic quickly.
No special equipment needed.
These characteristics make RCC simple, fast, and economical.

Continuously Reinforced Concrete


Pavement
Type of Portland cement concrete pavement
reinforced with steel re-bars throughout its length
The use of continuous reinforcement generates
the random cracks in the pavement, while
obviating the need for transverse contraction joints
that appear prone to joint-related distresses and
failures. The cracks can be held tightly by the
reinforcement and should be of no concern so
long as they are uniformly spaced, maintaining the
structural integrity of the pavement.
The elimination of transverse contraction joints
can offer high riding quality

Você também pode gostar