Escolar Documentos
Profissional Documentos
Cultura Documentos
Chapter 5
Accuracey
Data
Diagrams
Notes
Order of
Magnitude
BFD
Capacity +
inflation
Study (Major
equipment,
Factored)
PFD
Generalized
charts cost
Preliminary
Design (scope)
PFD
Group project
Definitive
+ 15%, - 7%
PFD +
P&ID
Detailed (firm or
contractor
+ 6%, - 4%
Complete engineering
Example 5.1
The estimated capital cost from a chemical plant using the study estimate method
(Class 4) was calculated to be $2 million. If the plant were to be built, over what range
would you expect the actual capital estimate to vary?
For a Class 4 estimate, from Table 5.2, the expected accuracy range is between 3 and
12 times that of a Class 1 estimate. A Class 1 estimate can be expected to vary from
+6% to -4%. We can evaluate the narrowest and broadest expected capital cost
ranges as:
Lowest Expected Cost Range
High value for actual plant cost ($2.0 x 106)[1 + (0.06)(3)] = $2.36 X 106
Low value for actual plant cost ($2.0 x 106)[1 - (0.04)(3)] = $1.76 x 106
Highest Expected Cost Range
High value for actual plant cost ($2.0 x 106)[1 + (0.06 )(12)] = $3.44 x 106
Low value for actual plant cost ($2.0 x 106)[1 - (0.04 )(12)] = $1.04 x 106
The actual expected range would depend on the level of project definition and effort. If
the effort and definition are at the high end, then the expected cost range would be
between $1.76 and $2.36 million. If the effort and definition are at the low end, then
the expected cost range would be between $1.04 and $3.44 million.
Example 5.2
Compare the costs for performing an order-of-magnitude estimate and a detailed
estimate for a plant that cost $5.0 x 106 to build.
Solution :
For the order-of-magnitude estimate, the cost of the estimate is in the range of
0.015% to 0.3% of the final cost of the plant:
Highest Expected Value: ($5.0 x 106)(0.003) = $15,000
Lowest Expected Value: ($5.0 x 106)(0.00015) = $750
For the detailed estimate, the cost of the estimate is in the range of 10 to 100
times that of the order-of-magnitude estimate
For the lowest expected cost range
Highest Expected Value: ($5.0 x 106 )(0.03) = $150,000
Lowest Expected Value: ($5.0 x 106)(0.0015) = $7500
For the highest expected cost range:
Highest Expected Value: ($5.0 x 106)(0.3) = $1,500,000
Lowest Expected Value: ($5.0 x 106)(0.015) = $75,000
Vendor quote
Most accurate
- based on specific information
- requires significant engineering
Use previous cost on similar equipment and scale for
time and size
Reasonably accurate
- beware of large extrapolation
- beware of foreign currency
Use cost estimating charts and scale for time
Less accurate
Convenient
Ca
Aa
Cb
Ab
(5.1)
Cost Exponent
Equipment Cost
Attribute - Size
Cost
Ca KAa
where
Cb
Abn
(5.2)
Ca K Aan
where
K Cb Abn
Economy of Scale
Example 5.3 :
Use the six-tenths-rule to estimate the % increase in purchased
cost when the capacity of a piece of equipment is doubled.
Using Equation 5.1 with n = 0.6:
Economy of Scale
Example 5.4
Compare the error for the scale-up of a heat exchanger by a
factor of 5 using the six-tenth- rule in place of the cost exponent
given in Table 5.3.
Using Equation 5.1:
Cost ratio using six-tenth-rule (i.e. n = 0.60) = 5.00.6 = 2.63
Cost ratio using (n =0.59) from Table 5.3 = 5.00.59 = 2.58
% Error = (2.63 -2.58)/2.58)(100) = 1.9 %
C K An
C
K An 1
A
I2
C2 C1
I1
C = Cost
I = Value of cost index
1,2 = Represents points in time at which
costs required or known and index values
known
Example 5.6
The purchased cost of a heat exchanger of 500 m2 area in 1990 was $25,000.
a. Estimate the cost of the same heat exchanger in 2001 using the two indices
introduced above.
b. Compare the results.
Table 5.5: The Basis for the Chemical Engineering Plant Cost Index
Components of Index
Fabricated Equipment
Process Machinery
Pipe, Valves, and Fittings
Process Instruments and Controls
Pumps and Compressors
Electrical Equipment and Materials
Structural Supports, Insulation, and
Paint
37
14
20
7
7
5
10
100
22
10
Total
100
61% of total
Example 5.7
The capital cost of a 30,000 metric ton/year isopropanol plant in
1986 was estimated to be $7 million. Estimate the capital cost of a
new plant with a production rate of 50,000 metric tons/year in 2001.
Cost in 2001 = (Cost in 1986)(Capacity Correction) (Inflation
Correction)
= ($7,000,000)(50,000/30,000).6(397/318)
=($7,000,000)(1.359)(1.248) = $11,870,000
Symbol
Comments
Equipment Cp
f.o.b. cost
Materials
CM
Labor
CL
Symbol
Comments
Freight,
insurance,
and taxes
CFIT
Construction
overhead
CO
Contractor
engineering
expenses
CE
Symbol
Comments
Contingency
CCont
Contractor
fee
CFee
4. Auxiliary facilities
Factor
Symbol
Comments
Site
development
CSite
Auxiliary
buildings
CAux
Off-sites and
utilities
COff
Lang Factor
n
CTM FLang C pi
i 1
4.74
3.63
3.10
Lang Factor
Example 5.8:
Determine the capital cost for a major expansion to a fluid processing
plant that has a total purchased equipment cost of $6,800,000.
Capital Costs = ($6,800,000)(4.74) = $32,232,000
Lang Factor
1.
1.
2.
Advantage
Easy to apply.
Drawbacks
Special MOC.
High operating pressure.
Table 5.8
o
CBM C p FBM
Bare Module
Cost
FBM = B1 + B2FpFM
o
FBM
B1 B2
C p Cop Fp FM
Example 5.9
The purchased cost for a carbon steel heat exchanger operating
at ambient pressure is $10,000. For a heat exchanger module
given the following cost information:
Item
% of Purchased Equipment Cost
Equipment
100.0
Materials
71.4
Labor
63.0
Freight
8.0
Overhead
63.4
Engineering
23.3
Using the information given above, determine the equivalent cost
multipliers given in Table 5.8 and the following:
0
a. Bare module cost factor, FBM
0
b. Bare module cost, C BM
Item
Equipment
100.0
1.0
Materials
71.4
0.714
Labor
63.0
0.63/(1+0.714)=
0.368
Freight
8.0
FIT
0.08/(1+0.714)=
0.047
Overhead
63.4
Engineering
23.3
0.634/0.368/
(1+0.714)= 1.005
0.233/(1+0.714) =
0.136
o
CBM C p FBM
Bare Module
Cost
FBM = B1 + B2FpFM
o
FBM
B1 B2
C p Cop Fp FM
Material Factor, FM, for these equipment are obtained from Figure A.8
along with Table A.3.
Values of B1 and B2 are given in Table A.4
FP ,vessel
( P 1) D
0.0315
2 850 0.6( P 1)
0.0063
Material Factor
Material Factor, FM , for other equipment are given in table A.6
along with Figure A.9
Illustrative Example
Cp
o
C BM
MOC
1 bar
CS
25 K
1 bar
SS
25 K
100 bar
CS
25 K
100 bar
SS
25 K
94.4 K 82.3 K
25 K
CBM
82.3 K 82.3 K
197.4
K
CTM 1.18
all equip
CBM
Grass-Roots Costs
o
CBM
CTM
all equip
Materials of Construction
Very important
Table 5.9 rough guide
Perrys good source
Capcost
Calculates costs based on input
CEPCI use current value of 401 or
latest from Chemical Engineering
Program automatically assigns
equipment numbers