Advanced Supply Chain Planner

(ASCP)

Agenda
1) Advantages
2) Prerequisites
3) Hardware Configuration
4) Bill of Material
5) Input of Demand and its Supply
6) Supply calculation
7) Collection Plan

Prerequisites
Modules Required
1) Order Management
2) Inventory
3) Purchasing
4) Bill of Material
5) Work in Progress

Advantages

Holistic Planning

1) All Manufacturing Methods (Discrete,Process,Flow,Repetitive and Project)


2) One Plan from Customers to Supplier.

Constraints

1) Enforcing Due Dates


2) Enforcing Capacity Constraints

Optimization

1) Maximize Plan Profit


2) Maximize On-Time Delivery
3) Maximize Inventory Turns

Hardware Configuration

Centralized Setup

Decentralized Setup

BOM

Demand/Supply

Demand

Sales Order : 2 EA (Ship Date : 18th May)


Forecast set : 3 EA (Ship Date : 25th May)

Supply

For Make item : Discrete Job Order


For Buy Item : Purchase Requisition
Note : Consider zero on hand quantity for all the item. No open discrete job for
Make item and no open PO,PR for buy items. Holidays on Sunday alone.

Supply Calculation

Make Item
For 18th May Shipment
Required Qty : 2 Pcs
Total Time Required : 16 hrs ( 8hrs/Pcs )
Discrete Job Start date

: 17th May 08:00

For 25th May Shipment


Required Qty

: 3 Pcs

Total Time Required

: 24 hrs ( 8hrs/Pcs )

Discrete Job Start date

: 24th May 00:00

Supply Calculation
17th May Production

24th May Production

Buy 1

Qty Required : 2 pcs


Lead Time : 5 days
Sugg. Need by date:16th May

Qty Required : 3 pcs


Lead Time : 5 days
Sugg. Need By date:23rd May

Buy2

Qty Required : 2 pcs


Lead Time : 6 days
Sugg. Need by date:16th May

Qty Required : 3 pcs


Lead Time : 6 days
Sugg. Need by date:23rd May

Collection Plan

View the Recording Now

Q&A

Thank You