Business Process Master List (BPML)

Management Guide

Version 1.0 December 2003

Document Information
About this Document
Abstract

The Business Process Master List (BPML) is a key tool for use in
implementations to capture the scope of the project, drive the
planning and managing of configuration and testing. This
document is an overview of what a BPML is and how to use and
manage it in an implementation. The following pages were provided
by a large COTS user and reflect their process for using the BPML.
See also the sample BPML included in the EI Toolkit.

File Name

bpml_mgmt_guise.ppt

Document Name

Business Process Master List (BPML) Management Guide

Version

1.0 December 2003

Date Last
Validated

September 2004

Document Change History


Version

Reason for Change

Date

0.0

Created for use by commercial industry customer #2

March 2001

1.0

Submitted for use in EI Toolkit

December 2003

Use Policy
This document was created to be used as a reference, sample or template. Contents of the EI Toolkit should
not be repurposed for publication in copyrighted material. This policy applies to all contents unless otherwise
specified in a particular document.

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Table of Contents
Overview
Objectives
Utilization
File Explanation
Organization,
Roles
Responsibilities
Updates Management

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

and

Overview
Business Process Master List (BPML) is An excel
worksheet containing Latin America Business
Processes configured in SAP R/3
The BPML was originally created in the ASAP tool
through the utilization of the Project Scooping
module, and adapted to Colgate business
practices by the Jaguar team
Since then, the BPML is the Back-Bone of Jaguar
Project as it is used in all project phases

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Overview
BPML
is
enriched
after
each
implementation with the new functionality
delivered to the subsidiary

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Objectives
Repository of Colgate Latin America
Business Processes, Practices and Variants
Repository
Functionality

of

Country

Specific

Configuration and Test Management


Support other Key Project Activities, such
as, Change Management and Security
Business Process Master List (BPML) Management
Guide
Version 1.0 December 2003

Utilization
The BPML is used through out the
implementation phases to support key
project activities, such as:

Implementation Team Training


Business Workshops
Business Variants Documentation
Configuration Management
GAP Analysis
Integration and Day in the Life Tests
Security
Roles & Responsibilities.

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Utilization

Implementati
on Team
Training

Implementation Team is trained to execute


all business processes supported by the
Latin America Application Framework
As well as the business logic behind each
piece of configuration
Therefore, the BPML is used as training
program
Business Process Master List (BPML) Management
Guide
Version 1.0 December 2003

Utilization

Business
Workshops

Implementation
team
presents
to
Subsidiary Management all the Business
Processes configured in the Latin America
Application Framework
The BPML is used to build up the BWAgendas and therefore a business cycle
sequence

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Utilization

Business
Variants

Implementation team has to identify and


document all the Business Variants that occurs in
their Subsidiary Processes
These Business Variants are documented in the
BPML and Used:
By the Core Team to track Configuration
By the Implementation team to duplicate Subsidiary
Business Process in SAP R/3

With this approach both Configuration and Testing


activities
are
efficiently
managed
and
implementation progress objectively measured

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Utilization

Business
Variants

All Business Variants are documented in the


MASTER LIST section of the BPML in RED
The Core Team MARKS the functionality and
business variants that will be available for a
giving configuration Cycle
Implementation team generates the test cycle
from MASTER LIST
Implementation team prints out the cycle n from
C n section
Implementation team assign testers in Cycle n

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Utilization

Business
Variants

Implementation
team
documents
results in Cycle n section

test

If Variant is successfully tested and approved by end


users, it is marked in Blue in both Master List & Cycle n
Sections

And the OK Word in TESTING DATE / Column ACTUAL

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Utilization

Business
Variants

Implementation
team
document
results in Cycle n section

test

If Variant or Business Process Procedure-BPP are not


successfully tested, error is documented in Integration
Test Tracking Sheet-ITTS and BPP or Variant will remain
in RED

And the ERROR ID in TESTING DATE / Column ACTUAL

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Utilization

Configuratio
n
Managemen
t

The Core Team delivers subsidiary configuration in a


specific dates along the implementation calendar, these
dates are identified as Configuration Cycles in the High
Level Plan
The MASTER LIST sheet has a FINAL CONFIGURATION
CYCLES section with Four C columns that represents
Configuration Cycles
Core Team Leaders marks with an X the configuration /
variants that will be delivered in each configuration cycle

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Utilization

GAP
Analysis

Once the Configuration available for each cycle


is
identified
the
implementation
team
documents the corresponding business variants
During GAP Analysis implementation team
develops the necessaries business conditions to
replicate their business processes in SAP R/3,
AND
Evaluate the FIT of the Latin America Application
Framework in their business

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Utilization

Integration
Tests

After GAP Analysis, there will be several


integration test, each of them with specific
objectives
IT-Agendas will be based in functionality /
business variants available for a giving cycle
BPML will be used to keep teams focus to
achieve test objectives

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Utilization
Security

In the Area of Security the BPML is used to


document all the transactions that are
used for a specific profile.
The BPML assures no T-Code is missing for
a specific role

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Utilizatio
n

Roles &
Responsibilitie
s

End user procedures and business


procedures defined and linked
Job roles assigned
May be linked to Security profiles

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Sample BPML

Area:
This column is used
to identify the Functional
Area of the Business
Processes
Example: Finance

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Sample BPML

Scenario:
This column is used to
identify the Scenario in which
The Business Processes are
Involved.
Example: Contract
Manufacturing

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Sample BPML

Group:
This column is a sublevel
Of the scenario, used to
Classify several process with the
Same objective.

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Sample BPML

Process:
This column is a sublevel
Of the Group, used to identify
Business processes.

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Sample BPML
Business Process Procedure:
This column, used to identify
the specific tasks within a process
That have a particular T-Code on
The System.
All business variants have to be
documented in the Master List
Section of the BPML that are
involved in the Process.
Initial variants in color RED
Variants tested and approved in
color BLUE in the Master List
Section
Business Process Master List (BPML) Management
Guide
Version 1.0 December 2003

Sample BPML

Code:
This column, used to document
the T-Codes of SAP for their own
BPP
These are not to be modified

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Sample BPML

Consultant:
This column, used to assign a
Consultant that is responsible
For the specific Business process
These column is to be updated
By the core team.

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Sample BPML

Owner:
This column, used to assign a
CP Person that is responsible
For the specific Business process
These column is to be updated
By the implementation team.

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Sample BPML

C1:
This column, used by the core
teamto mark which business
processes are in scope to be
tested on the specific cycle
Cn.
This will be used to generate the
Cycle n Worksheet.

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Sample BPML
C1 worksheet:
After identifying the scope of
The testing cycle and you
Generate the worksheet, here
Is were you find the worksheet

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Sample BPML
C1 Worksheet:
This is how the testing scope
Worksheet looks like, you have
the same process structure
(area, scenario group, process,
BPP & T-Codes this are to be
generated Automatically.
The Testing Dates column
should be updated after
each process or variant is
tested and signed off.

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Sample BPML
C1 Worksheet:
The Tester column is the
Person responsible to test
the specific Process
This is updated by the
Implementation team
Business Variants tested OK
Will be Marked OKin
TESTING DATES /
Column ACTUAL
in Section C1 of the BPML
Variants with error will
remain in RED in both
Master List and C1
Business Process Master List (BPML) Management
Guide
Version 1.0 December 2003

Organisation, Roles and Responsibilities

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Functional
Teams

Technical &
Security Team

Core
Team

Change Team

Core Team
Leader

Organisation
BPML
Coordinator
Subsidiary
Team Leaders

Subsidiary
Team

Functional
Teams

Technical &
Security

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Change Team

Organisation : Roles and Responsibilities


BPML
Coordinator

Receive changes from all teams


Ensure BPML structure integrity
Ensure teams complete only their area of
responsibility
Publish & ensure all teams work with the
latest version of the BPML

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Organisation : Roles and Responsibilities


Core Team
Leaders

Responsible
to
document
system
configuration in a Business Process format
in the BPML document
Maintain up-to-date the BPML with all new
developments and configuration status
Report new configuration / documentation
to BPML coordinator

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Organisation : Roles and Responsibilities


Subsidiary
Team Leaders

Ensure team members :


Maintain Business Variants
Update business variants after Integration or
Day in the Life Tests
Maintain file structure
Work with the latest version

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Organisation : Roles and Responsibilities


Functional
Team

Document Business Variant


Update Business Variants Test Status after
Integration and Day in the Life Test
Report BPML changes to functional team
leader

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Maintenance Process
Since the BPML is used & updated by different people a
central coordination is mandatory to ensure file integrity,
AND
Set of rules to maintain its utilization synchronization
Event
Responsible

New BPP in BPML File


Core Functional Team
Configuration in Cycle n
Core Team Leader
Documentation of Business Variants
Implementation Team
Testing Activities and Status
Implementation Team
Users Profiles
Security Team
Training Classes/Roles
Change Team
Communication of updated BPML BPML Coordinator

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Management : Updating Approach


BPML update conditions and responsibilities :

Core Configuration Team

Translate new functionality into BPML Business Processes


Update configuration status
Communicate updates to Core Team Leaders

Core Team Leaders

It is controlled centrally by the BPML Manager :

The Core Team might update the BPML in this events

Include a new process


New Transaction
Identify process to be tested in specific cycles

The subsidiary might update the BPML in this events:

Include new Business Variants


Assign Owner of the Process
Update the Tested Variants
Business Process Master List (BPML) Management
Guide
Version 1.0 December 2003

Maintenance Flow - Core Team

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Manage Control
Core Team: Configure or Modifies a Process
Project
Managers
Core Team

Core Team
Leader

BPML
Coordinator

1.- CT Configure or
Modifies a process

4.- CT Leader
Authorize update

6.- Updates BPML


According to form

2.- CT fills up an
Update form

5.- CT Leader 7.- Emails notification


of New BPML
Emails form to
version on DB
BPML coordinator

3.- CT sends form


to Team Leader
for authorization

Core
Team
Leaders

Subsidiar
y
Teams

Consulta
nts
Business Process Master List (BPML) Management
Guide
Version 1.0 December 2003

Manage Control
Core Team: Identifies or Modifies a T-Code
Core Team
Leader
Core Team

Project
Managers

BPML
Coordinator

1.- CT Identifies or
Modifies a T-Code
2.- CT fills up an
Update form
3.- CT sends form
to BPML coordinator
with copy to
CT Leader

6.- Updates BPML


According to form
7.- Emails notification
of New BPML
version on DB

Core
Team
Leaders

Subsidiar
y
Teams

Consulta
nts
Business Process Master List (BPML) Management
Guide
Version 1.0 December 2003

Manage Control
Core Team: Identifies Cycle N for IT.
Project
Managers
Core Team

1.- CT Identifies
processes for
cycle n in BPML
2.- CT sends BPML
to Team Leader
for Review

Core Team
Leader

3.- CT Leader
Reviews BPML

BPML
Coordinator

6.- Updates Official


BPML

5.- CT Leader 7.- Emails notification


of updated BPML
Emails form to
version on DB
BPML manager

Core
Team
Leaders

Subsidiar
y
Teams

Consulta
nts
Business Process Master List (BPML) Management
Guide
Version 1.0 December 2003

Maintenance Flow - Implementation Team

Business Process Master List (BPML) Management


Guide
Version 1.0 December 2003

Manage Control
Subsidiary Team: Identifies Business Variant.
Project
Managers
Subsidiary

1.- Sub Identifies a


Business Variant
for a process
2.- Subsidiary fills
up an Update form

Subsidiary
Team Leader

BPML
Coordinator

4.- Sub Leader


6.- Updates BPML
Authorize update According to form
5.- Sub Leader 7.- Emails notification
Emails form to
of updated BPML
BPML manager
version on DB

3.- Sub sends form


to Sub Team Leader
for authorization

Core
Team
Leaders

Subsidiar
y
Teams

Consulta
nts
Business Process Master List (BPML) Management
Guide
Version 1.0 December 2003

Manage Control
Subsidiary: Identifies an Owner of a Process
Subsidiary
Leader
Subsidiary

Project
Managers

BPML
Coordinator

1.- Subsidiary
Identifies or
Modifies a T-Code
2.- Subsidiary fills up a
BPML
3.- Subsidiary sends
File to BPML
manager with copy
to Sub Leader

4.- Updates
Official
BPML
5.- Emails notification
of updated BPML
version on DB

Core
Team
Leaders

Subsidiar
y
Teams

Consulta
nts
Business Process Master List (BPML) Management
Guide
Version 1.0 December 2003

Manage Control
Subsidiary Team: Indicate Tested B. Variants
IT
Coordinator
Subsidiary

1.- After IT, results of


BVariants test will be
in the BPML colored
accordingly.
2.- Subsidiary sends
file, to BPML
Manager with copy to
IT coordinator

Project
Managers

BPML
Coordinator

4.- Updates
Official
BPML
5.- Emails notification
of updated BPML
version on DB

Core
Team
Leaders

Subsidiar
y
Teams

Consulta
nts
Business Process Master List (BPML) Management
Guide
Version 1.0 December 2003