PRE-MONSOON CHECKLIST

INDEX

ROOF
TERRACE
AT VERTICAL FACES
STORM WATER DRAINS / PIPES
ROADS & DEVELOPMENT
MISC. POINTS
INTERIORS
UTILITY
EMERGENCY TOOLS
RAIN WATER HARVESTING

ROOF : Cleaning of Roof


Cleaning of Rain water
Gutter
Replacement of broken
Sheets
(FRP/polycarbonate/AC/Metal
etc)
Replacement of Broken
glasses for north light
structures
Sealing of dummy Holes ,
loose screws etc
Appropriate treatments with
elastomeric compounds
(Kemper/ Isothene) for Metal
to FRP / polycarbonate &
Metal to RCC structures
Verification of flashings at
Junction between Roof &
cladding

TERRACE : Cleaning of Terrace


Cleaning the mouth of Down
take pipe
Fixing of Screen at the mouth
of Down take to arrest the solid
particles
Rectification of damaged
waterproofing
Rectification of Cracks,
potholes with appropriate
chemical coatings( Dr.
Fixit,Fosroc,tapecrete etc.)
Closing of Cutouts lefts for
Cable, pipe entry, etc
Fixing of Vent Cowls over
Pipes
Closing of open ducts, light
courts, lift shafts according to
site condition, If applicable
Slope at the top of parapet
wall

AT VERTICAL FACES:Sealing of cracks in


wall/plaster
Clamping of Down take pipes
Junction of gutter downspout
to pipe
Sealing of junctions around
window, doors, rolling
shutters, glazing etc.
Replacement of Broken
glasses of window, glazing etc
Lowering the flap of louvered
windows
Outward slope at window sill
level
Sealing of Joints around
cutouts, holes made for
Utilities (pipes, ducts etc)
Rectification of vertical
flashings of sheets against
leakages

STORM WATER DRAINS/PIPES: Cleaning of


Drains,pipes,chambers etc
Proper Slope to drains
Cleaning the Area below
gratings
Verification of Down take
pipe connection in Storm
water drain
Finishing of Chambers
inside & outside
Replacement of broken
chamber covers, pipes
Physical Testing of line to
observe the flow, stagnancy ,
blockage of water etc
Opening the valves In dyke
walls of oil yard etc
Alt. arrangement near rain
water harvesting pit against
over flow

ROADS & DEVELOPMENT: Cleaning of Roads & soccer


drains
Removal of obstructions to
surface run-off.
Identification & rectification of
water stagnancy areas.
Feeling of Exposed grove
with Bitumen
Rectification of cracks &
potholes with epoxy mortar
Cleaning of weep holes
Mouth cleaning outside
compound at discharge point
Esurience of water discharge
at nearest water stream
Identification & demarcation
of landslide areas
Back filling around critical
structure elements such as
Foundation, raft etc

MISC. POINTS: Provision of Sump & Sump


pit in the underground
structures such as basement,
pump room etc
Negative Waterproofing for
the under ground structures if
applicable/required
Checking & fixing covers for
water tanks, & septic tanks
,utility/service trenches etc.
Check the locations near
retaining walls for any voids
on the rear sides of the wall
for any voids , trenches and fill
them up above the level of
the adjoining ground so as to
reduce pressure on the wall
by avoiding the storm water to
flow abutting the wall.
Security gate track cleaning
& covering the motor

BUILDING INTERIORS:Clean carpets and rugs


regularly to reduce musty
smell & water and insect
infestation respectively
Protect wooden cupboards,
desk drawers from moisture
with appropriate majors
Protect wooden flooring from
moisture by properly waxed
(polished) to protect them
from moisture
Destroy termite infestation
which is a major problem
where water leakage or high
humidity exists.
Install ventilators to remove
dampness in humid areas
Provide the door mats.

UTILITIES:

Check Transformer Oil Insulation resistance, filtration of Transformer oil to


be done.
Check Transformer safety relays operation B relay, Oil Temp., winding
temp., Oil Surge relay.
Check Transformer Cable end Boxes for ingress protection level if found
in bad condition then make proper sealing of all joints to avoid ingress of
moisture.
Check HT Panel relays for satisfactory operations.
Provide Space heaters in HT Cable compartments.
Check LT Panels for ingress protection if found not up to mark, then
replace gaskets, tighten the panel covers.
Check insulation resistance of LT Panel.
Check space heaters operations in LT Panels.
Check whether HT & LT Panel rooms are well protected from Rains &
provide enough lighting & if necessary space heating in case of high
moisture area.

UTILITIES:

Check bus duct for ingress protection failure, space heaters operation.
Check whether LT Panel is not under area where leakage can happen in
rainy season.
Check Earthing Values, if found not OK then do necessary compound filling
work.
Check tightness of all earthing joints.
Check Lightening Arrestor connectivity to earth pits.
Check earthing connections to all machines & equipments, every equipment
must have two distinct earth connections.

EMERGENCY TOOLS:1.
2.
3.
4.
5.
6.

Sump pump
HDPE Pipe 50 Rmt
Polythene paper 200 Sqm
Silicon Sealant
Waterproofing chemical compounds
Drill Machine

ARTIFICIAL RECHARGE :
RECHARGE WELL
RECHARGE PIT /SHAFT
DUG WELL
FLOODING
PERCOLATION TANK
STREAM AUGMENTATION
DITCH & FURROW SYSTEM

THANK YOU !!

S.N.Pingle Consultants
66,Bhosale Nagar,
Pune-411008
Tel: 020-25561598
Fax:020-25560950
Cell:9822199719
Email : snpingle@gmail.com
Website : www.snpc.in

Você também pode gostar