Escolar Documentos
Profissional Documentos
Cultura Documentos
Session 1
Introduction
Coverage Session 1
What is a project?
Project Management:1. Project Planning.
2. Project Scheduling.
3. Project Controlling.
Basic Tools:1. Bar chart.
2. Milestones chart.
Management Applications of Network Analysis
Definition of Project
1. Project Planning.
2. Project Schedule.
3. Project Control.
1. Project Planning
Objectives.
Team Organization.
Performance Criteria: Time, Cost.
Requirement of Resources.
Developing of Network.
2. Project Schedule
Availability of Resources (Human, Material,
Financial).
Duration estimates of activities.
Selection of Managerial Technique.
Networks (PERT, CPM).
3. Project Control
Monitoring.
Revision & Updating.
Rescheduling Measures.
Reallocation of Resources.
Activity
Duration
1.
4 weeks
Preparing a mould
2 weeks
1 weeks
Heat Treatment of A
2 weeks
Installing machine M
7 weeks
Machining part B
5 weeks
3 weeks
4 weeks
2 weeks
10
1 weeks
GANTT CHART
Activity
Prepare Pattern
Prepare Mould
Cast & Clean A
Heat Treatment A
Install Machine M
Machine Part B
Assemble Parts A & B
Prepare Test Rig
Test Assembly
Pack & Dispatch
111 1 1 111 1
1 2 3 456 7 8 9012 3 4 567 8
GANTT CHART
Activity
Prepare Pattern
Prepare Mould
Cast & Clean A
Heat Treatment A
Install Machine M
Machine Part B
Assemble Parts A & B
Prepare Test Rig
Test Assembly
Pack & Dispatch
1 1 1 1 1 1 1 1 1
1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8
Milestone Charts
For dynamic programming, knowledge of
amount of work in progress or jobs completed
is necessary.
Suppose 10th weeks have elapsed, what
progress is made?
Lagging
MILESTONE
GANTT CHART
Activity
Prepare Pattern
Prepare Mould
Cast & Clean A
Heat Treatment A
Install Machine M
Machine Part B
Assemble Parts A & B
Prepare Test Rig
Test Assembly
Pack & Dispatch
At the end of 10th week
1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
Duration in days
Design Questionnaire
Answer Questionnaire
Exercise 1
Activity
Design Questionnaire
Print question paper
Distribute to various centers
Answer questionnaire
Collect answer books at main office
1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
Exercise 2 - Data
Activity
Duration in Days
Activity 1
Activity 2
Activity 3
Activity 4
Activity 5
Activity 6
Activity 7
Activity 8
Exercise 2
June, 2010
Activity
Activity 1
Activity 2
Activity 3
Activity 4
Activity 5
Activity 6
Activity 7
Activity 8
1 1 1 1 1 1
7 8 9 0 1 2 3 4 5
1
6
1
7
1
8
1
9
2
0
2
1
2
2
2
3
2
4
2
5
2
6
2
7
2
8
2
9
3
0
Exercise 2
June, 2010
Activity
1
2
3
4
5
6
7
8
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Exercise 2 - Monitoring
Answer the following:1. On what calendar date the project was
completed?
2. On 23rd June, what was the progress of the
project?
Exercise 2 - Monitoring
Answer 1:- The project completed on 30 th
June.
Answer 2:(i) Activities 1,2,3,4,5,6 had completed.
(ii) Activity 7 was under progress for 2 days,
4 more days required for its completion.
(iii) Activity 8 was under progress for 4 days,
2 more days required for its completion.
Thanks