Escolar Documentos
Profissional Documentos
Cultura Documentos
S.K.Rao
Construction contract-mutual
obligations
A construction contract is between two partiesEmployer and Contractor.
The work is executed based on Contract
provisions and the rights and obligations of the
parties are governed by these documents
Both parties have to fulfill their respective
obligations under the contract.
Non fulfillment of any obligation by one party
affects the interests of the other party
Long duration of contract-various issues arise
during construction
Views of one party may not be acceptable to the
other resulting in disagreement
2
Sources of disputes
Sources of disputes could be:
Interpretation of contracts in
case of discrepancies
The following aspects are to be considered while
interpreting contract documents
a) Contract to be read as a whole
c) Local custom or usage
d) Reasonable meaning
e) Order of precedence among various
documents forming part of contract
f) Words versus figures
g) Written words versus printed words
h) General versus special provisions
5
Inconsistencies in different
parts of Contract
In order to resolve apparent inconsistencies or
contradictions, in cases where the subject
matter is covered several times in different
parts of the Contract, the order of precedence
to be considered is laid down in the General
Conditions of Contract adopted by various
organisations
There is a sub-clause in FIDIC contract form
also (Federation Internationale des IngenieursConseils) laying down the order of precedence
for interpretation
6
The
The
The
The
The
The
The
The
contract agreement
letter of acceptance
letter of tender
Particular Conditions
General Conditions
Specification
Drawings
schedule or any other documents
7
Engineers clarification
If an ambiguity or discrepancy is found in
the documents, the Engineer shall issue
necessary clarification or instruction
The work will be executed as per the
instruction of Engineer
Disagreement on any issue may result in
claim/dispute which will have to be
resolved by various procedures of dispute
resolution
8
Dispute Resolution-ADR
Disagreement between the Employer and the
Contractor results in dispute
Going to Court for resolving disputes involves
lengthy litigation which is tedious and time
taking
Various alternative methods of dispute
resolution are, therefore, devised for
settlement of disputes-ADR
Arbitration and conciliation are governed by
The Arbitration and Conciliation Act,1996
11
Mutual discussion
Decision of Accepting officer
Conciliation- provision in the
Arbitration and Conciliation Act, 1996
Arbitration as per the Arbitration and
Conciliation Act, 1996
Intervention by Court
13
DRB proceedings-commencement
DRB proceedings are commenced from the date
the chairman accepts his appointment
DRB chairman calls for Claims statement from
both parties with details within a specified date
He shall endorse copy to the other members
The parties are asked to endorse copies to
opposite party as well as other members
On receipt, the chairman calls for Defence
statement from the opposite parties by a
specific date
Copies to be endorsed to the parties as well as
other members
Parties may request for extension of time for
submission which may be considered by the DRB
17
DRB proceedings-hearing
On receipt of all the documents from both
parties, each member studies the case in detail
The chairman fixes the date for site visit and
hearing of the case in consultation with all
concerned
The procedure for conducting the proceedings
will be decided by DRB in consultation with the
parties
On the appointed date, DRB visits site along with
parties
The hearing of the case is conducted at a
convenient location
Full opportunity is given to both parties to
present their cases during site visit as well as
during the hearing
18
DRB proceedingsrecommendations
DRB Members make their own notes during site
visit and the hearing
They may ask for any clarifications from the
parties
The hearing will be closed after both parties are
satisfied that they are given full opportunity to
present their case
There after, the DRB will have their internal
meeting, deliberate the issues among them and
make their Recommendations
This will be signed by the members and chairman
The copies will be sent to both parties and the
members
If this is not acceptable to either party, the matter
may be referred to Arbitration
19
Resolution of disputes-ADR
Mutual discussion
Decision of Engineer/ Accepting
officer
Dispute review board- provision in
FIDIC contract form
Conciliation- provision in the
Arbitration and Conciliation Act, 1996
Arbitration as per the Arbitration and
Conciliation Act, 1996
21
26
Part I Arbitration