SPILLWAYS

Aug 7, 2016

& NOF DAMS

NAC , HYDERABAD

Er.B.LAKSHMANA RAO, B.Tech., M.B.A.,


F.I.E.,C.Engr.,
Engineer-in-Chief(Rtd), Central Designs Org.,
Hyderabad
09440817277--- blakshmanarao@yahoo.co.in

Aug 7, 2016

NAC , HYDERABAD

PURPOSES OF THE
RESERVOIRS

IRRIGATION
HYDRO POWER GENERATION
FLOOD CONTROL AND RIVER
TRAINING
BALANCING RESERVOIRS
DRINKING WATER SUPPLY AND
SANITATION
FISH CULTURE
SOIL CONSERVATION
INLAND NAVIGATION
Aug 7, 2016

NAC , HYDERABAD

DATA REQUIRED FOR DESIGN OF SPILLWAYS

(a) Index Plan showing the location of Project, Towns and Cities nearby,
Railways and Road ways, Canal system and Command Area.
(b) General Layout of the Head works.
(c) Reservoir Standards
(d) Report on Hydrology of the Project containing the computation of
the Design Flood (PMF/SPF/1000 year/500 year Flood as the case
may be ) and the detailed calculations along with the Catchment
Area Plan.
(e) Tail water Rating Curve along with longitudinal and cross sections
of the river / Stream at closer intervals duly indicating the OMFLs
(f) Seismic Zone Standing committees Recommendations on
seismic coefficients
(g) Geological Report along with the Logging of bores, permeability
test results etc., from the Geological Survey of India.

Aug 7, 2016

NAC , HYDERABAD

NAGARJUNA SAGAR DAM

Aug 7, 2016

NAC , HYDERABAD

NAGARJUNA SAGAR DAM

Aug 7, 2016

NAC , HYDERABAD

NAGARJUNA SAGAR

Aug 7, 2016

NAC , HYDERABAD

BHAKRA DAM

Aug 7, 2016

NAC , HYDERABAD

TEHRI DAM

Aug 7, 2016

NAC , HYDERABAD

RANJIT SAGAR DAM

Aug 7, 2016

NAC , HYDERABAD

10

NATHPA JHAKRI DAM

Aug 7, 2016

NAC , HYDERABAD

11

INDIRA SAGAR DAM

Aug 7, 2016

NAC , HYDERABAD

12

BAGLIHAR DAM,
R.CHENAB - J&K

Aug 7, 2016

NAC , HYDERABAD

13

MULLAPERIYAR DAM KERALA

Aug 7, 2016

NAC , HYDERABAD

14

HIRAKUD DAM ORISSA

Aug 7, 2016

NAC , HYDERABAD

15

TUNGABHADRA DAM,
KARNATAKA

Aug 7, 2016

NAC , HYDERABAD

16

SARDAR SAROVAR DAM,


NARMADA

Aug 7, 2016

NAC , HYDERABAD

17

PONG DAM ON BEAS - HIMACHAL


PRADESH

Aug 7, 2016

NAC , HYDERABAD

18

RANA PRATAP SAGAR CHAMBAL RAJASTHAN

Aug 7, 2016

NAC , HYDERABAD

19

UKAI DAM, TAPI,


GUJARAT

Aug 7, 2016

NAC , HYDERABAD

20

UJJAASHTRANI DAM BHIMA, MAHARASHTRA

Aug 7, 2016

NAC , HYDERABAD

21

SALAULIM - GOA

Aug 7, 2016

NAC , HYDERABAD

22

KRISHNARAJA SAGAR DAM KARNATAKA

Aug 7, 2016

NAC , HYDERABAD

23

BHADRA DAM KARNATAKA

Aug 7, 2016

NAC , HYDERABAD

24

SATHANUR DAM PENNALIYAR TAMILNADU

Aug 7, 2016

NAC , HYDERABAD

25

METTUR DAM TAMILNADU

Aug 7, 2016

NAC , HYDERABAD

26

BHAVANI SAGAR TAMILNADU

Aug 7, 2016

NAC , HYDERABAD

27

SRISAILAM DAM

Aug 7, 2016

NAC , HYDERABAD

28

IDUKKI DAM KERALA

Aug 7, 2016

NAC , HYDERABAD

29

IDUKKI DAM KERALA

Aug 7, 2016

NAC , HYDERABAD

30

BANASURA SAGAR KALIPETTA


KERALA

Aug 7, 2016

NAC , HYDERABAD

31

PULICHINTALA PROJECT
A PANAROMIC VIEW

Aug 7, 2016

NAC , HYDERABAD

32

Aug 7, 2016

NAC , HYDERABAD

33

CHAGALLU RESERVOIR

Aug 7, 2016

NAC , HYDERABAD

34

SRISAILAM DAM

Aug 7, 2016

NAC , HYDERABAD

35

SRISAILAM DAM

Aug 7, 2016

NAC , HYDERABAD

36

NAGARJUNA SAGAR

Aug 7, 2016

NAC , HYDERABAD

37

JANJHAVATHI RUBBER DAM DRY


CONDITION

Aug 7, 2016

NAC , HYDERABAD

38

RUBBER DAM

Aug 7, 2016

NAC , HYDERABAD

39

FLOW OVER RUBBER DAM

Aug 7, 2016

NAC , HYDERABAD

40

YOGI VEMANA RESERVOIR


(MADDILERU) - SPILLWAY

Aug 7, 2016

NAC , HYDERABAD

41

TALIPERU PROJECT -SPILLWAY

Aug 7, 2016

NAC , HYDERABAD

42

SINGUR PROJECT
SPILLWAY

Aug 7, 2016

NAC , HYDERABAD

43

KOIL SAGAR DAM

Aug 7, 2016

NAC , HYDERABAD

44

BHAKRA NANGAL DAM

Aug 7, 2016

NAC , HYDERABAD

45

BHAKRA NANGAL DAM,PUNJAB

Aug 7, 2016

NAC , HYDERABAD

46

ARCH DAM , IDUKKI , KERALA

Aug 7, 2016

NAC , HYDERABAD

47

DAMODAR VALLEY DAM


INDIA

Aug 7, 2016

NAC , HYDERABAD

48

DAMODAR VALLEY DAM


INDIA

Aug 7, 2016

NAC , HYDERABAD

49

MORNING GLORY SPILLWAY AND ARCH DAM,


MONTICELLO

Aug 7, 2016

NAC , HYDERABAD

50

MORNING GLORY SPILLWAY (MONTI CELLO DAM, U.S.A.)

Aug 7, 2016

NAC , HYDERABAD

51

THE HOLE DURING DRY


SEASON

Aug 7, 2016

NAC , HYDERABAD

52

MORROW POINT DAM


COLARADO USA

Aug 7, 2016

NAC , HYDERABAD

53

DAM ON LONG RIVER CHINA

Aug 7, 2016

NAC , HYDERABAD

54

THREE GORGES DAM,


CHINA

Aug 7, 2016

NAC , HYDERABAD

55

DREISCHLUCHTEN POWER
DAM CHINA

Aug 7, 2016

NAC , HYDERABAD

56

HOOVER DAM, USA

Aug 7, 2016

NAC , HYDERABAD

57

HOOVER DAM - VEGAS

Aug 7, 2016

NAC , HYDERABAD

58

HOOVER DAM - USA

Aug 7, 2016

NAC , HYDERABAD

59

HOOVER DAM

Aug 7, 2016

NAC , HYDERABAD

60

GRAND COULEE SPILLWAY ON COLUMBIA RIVER


WASHINGTON STATE USA

Aug 7, 2016

NAC , HYDERABAD

61

GRAND COULEE DAM

Aug 7, 2016

NAC , HYDERABAD

62

GRAND COULEE DAM

Aug 7, 2016

NAC , HYDERABAD

63

DWORSHAK DAM IDAHO


USA

Aug 7, 2016

NAC , HYDERABAD

64

STEPPED SPILLWAY

Aug 7, 2016

NAC , HYDERABAD

65

Aug 7, 2016

NAC , HYDERABAD

66

Aug 7, 2016

NAC , HYDERABAD

67

Aug 7, 2016

NAC , HYDERABAD

68

NORIS DAM EAST


TENNESSEE USA

Aug 7, 2016

NAC , HYDERABAD

69

NIAGARA SPILLWAY, USA

Aug 7, 2016

NAC , HYDERABAD

70

ROOSEVELT DAM USA

Aug 7, 2016

NAC , HYDERABAD

71

JOHNY DAM COLUMBIA USA

Aug 7, 2016

NAC , HYDERABAD

72

MELTON DAM-STEPPED SPILLWAY

Aug 7, 2016

NAC , HYDERABAD

73

HYDRO POWER DAM ALQUEVA


EUROPE

Aug 7, 2016

NAC , HYDERABAD

74

CRESTA DAM,NORTH CALIFORNIA, U.S.A.


TILTING GATES

Aug 7, 2016

NAC , HYDERABAD

75

BUTTRESS DAM

Aug 7, 2016

NAC , HYDERABAD

76

BONNEVILLE DAM
COLUMBIA

Aug 7, 2016

NAC , HYDERABAD

77

CHUTE SPILLWAY ALCEVA


PORTUGAL

Aug 7, 2016

NAC , HYDERABAD

78

WARRAGAMBA DAM- AUSTRALIA

Aug 7, 2016

NAC , HYDERABAD

79

TARBELA DAM - PAKISTAN

Aug 7, 2016

NAC , HYDERABAD

80

RED RIDGE STEEL DAM, USA

Aug 7, 2016

NAC , HYDERABAD

81

RUBBER DAM, USA

Aug 7, 2016

NAC , HYDERABAD

82

RED RIDGE WOODEN


DAM, USA

Aug 7, 2016

NAC , HYDERABAD

83

R.C.C. DAM
GROUT ENRICHED VIBRATED
ROLLER
COMPACTED CONCRETE

Aug 7, 2016

NAC , HYDERABAD

84

Aug 7, 2016

NAC , HYDERABAD

85

Aug 7, 2016

NAC , HYDERABAD

86

Aug 7, 2016

NAC , HYDERABAD

87

Aug 7, 2016

NAC , HYDERABAD

88

Aug 7, 2016

NAC , HYDERABAD

89

Aug 7, 2016

NAC , HYDERABAD

90

Aug 7, 2016

NAC , HYDERABAD

91

Aug 7, 2016

NAC , HYDERABAD

92

Aug 7, 2016

NAC , HYDERABAD

93

Aug 7, 2016

NAC , HYDERABAD

94

Aug 7, 2016

NAC , HYDERABAD

95

CLASSFICATION OF RESERVOIRS
Classification
Storage
Small
mcum

0.5-10

Intermediate
mcum

10-60

Large
mcum

Aug 7, 2016

Hyd. Head
flood

Design

7.5 - 12 m
flood

100 year

12 - 30 m

>60

NAC , HYDERABAD

> 30 m

S.P.F.
P.M.F.

96

DESIGN STAGES

Aug 7, 2016

HYDRAULIC DESIGN
STRUCTURAL DESIGN
FOUNDATION TREATMENT
MODEL STUDIES
INSTRUMENTATION

NAC , HYDERABAD

97

HYDRAULIC DESIGN

DESIGN FLOOD DISCHARGE


TAIL WATER RATING CURVES
FREE BOARD COMPUTATIONS
CREST LEVEL , F.R.L., T.B.L
VENTWAY, No. OF VENTS, Size of
Vents

Aug 7, 2016

NAC , HYDERABAD

98

STRUCTURAL DESIGN
STABILITY ANALYSIS OF BODY WALL
INCLUDING SEISMIC ANALYSIS
FACTORS OF SAFETY AGAINST
SLIDING
DESIGN OF COMPONENTS VIZ. PIERS,
GALLERIES,SUMPWELLS, ADITS, STAIR
WELLS, SPILLWAY BRIDGE, WALKWAY
BRIDGE Etc.,
ENERGY DISSIPATION ARRANGEMENTS
Aug 7, 2016

NAC , HYDERABAD

99

FORCES TO BE CONSIDERED
VERTICAL FORCES:
1.SELF WEIGHT OF BODY WALL
2.INTERMEDIATE PIER
3.RADIAL GATE / VERTICAL GATE
4.HOIST PLATFORM & EQUIPMENT
5.WEIGHT OF WATER
6.SPILLWAY BRIDGE
7.SEISMIC FORCE
8.UPLIFT FORCE

HORIZONTAL FORCES:
1.WATER PRESSURE FORCE
2.EARTH PRESSURE FORCE
3.SILT PRESSURE FORCE
4.HYDRODYNAMIC FORCE
5.SEISMIC FORCE
Aug 7, 2016

NAC , HYDERABAD

100

STABILITY OF THE SPILLWAY BODY WALL


The stability of the Spillway body wall is to be checked for
the following Load combinations as per the I.S.6512-1984
A: DAM COMPLETED- NO WATER IN RESERVOIR- NO TAIL WATER
B: F.R.L. IN RESERVOIR- NORMAL TAIL WATER LEVELNORMAL UPLIFT

( No tensile stresses are allowed in Load combination B)


C: MAXIMUM WATER LEVEL- ALL GATES OPENWATER LEVEL- NORMAL UPLIFT
D:
COMBINATION A +
E:
COMBINATION B +
F:
COMBINATION C +
INOPERATIVE )
G:
COMBINATION E +
INOPERATIVE )

Aug 7, 2016

MAXIMUM TAIL

EARTH QUAKE
EARTH QUAKE
EXTREME UPLIFT ( DRAINS ARE
EXTREME UPLIFT ( DRAINS ARE

NAC , HYDERABAD

101

Energy Dissipation Arrangements


To minimize erosion of strata on the
downstream
of the spillway, energy dissipation shall be done
using the following methods.

Types of energy dissipators:


Bucket type
Roller bucket Solid and
Slotted
Trajectory bucket
Stilling basin type
Horizontal apron
Sloping apron
Aug 7, 2016

NAC , HYDERABAD

102

KADDAM PROJECT
ENERGY DISSIPATION

Aug 7, 2016

NAC , HYDERABAD

103

FOUNDATION
TREATMENT
CURTAIN GROUTING
CONSOLIDATION
GROUTING

Aug 7, 2016

NAC , HYDERABAD

104

GALLERY IN
CHAGALLU BARRAGE

Aug 7, 2016

NAC , HYDERABAD

105

MODEL STUDIES
To study
Co-efficient of discharge
Adequacy of vent way provided
Negative pressures on Crest and
Glacis
Energy Dissipators efficiency

Aug 7, 2016

NAC , HYDERABAD

106

PULICHINTALA PROJECT
MODEL STUDIES

Aug 7, 2016

NAC , HYDERABAD

107

Aug 7, 2016

NAC , HYDERABAD

108

3D MODEL STUDIES

Aug 7, 2016

NAC , HYDERABAD

109

Aug 7, 2016

NAC , HYDERABAD

110

GROYNE IN GODAVARI

Aug 7, 2016

NAC , HYDERABAD

111

INSTRUMENTATION

Aug 7, 2016

NAC , HYDERABAD

112

SPILLWAY

Aug 7, 2016

BRIDGES

NAC , HYDERABAD

113

JURALA
PROJECT
SPILLWAY BRIDGE

Aug 7, 2016

NAC , HYDERABAD

114

SWARNAMUKHI
BARRAGE

Aug 7, 2016

NAC , HYDERABAD

115

GUNDLAKAMMA PROJECT

Aug 7, 2016

NAC , HYDERABAD

116

SPILLWAY BRIDGES
Spillway bridges are to be provided
over the spillway piers to have access
between the left flank and right flank
of reservoir.
Spillway Bridges may be provided on
u/s side or d/s side of Radial gates
Spillway bridges are also utilised for
movement of Gantry Crane for lifting
of Stop Log Elements
Aug 7, 2016

NAC , HYDERABAD

117

As per the requirement the width of


carriage way may be 4.25m or 7.5m
The Bridge may have
Foot path on one side
Foot paths on both sides
Without footpaths
Aug 7, 2016

NAC , HYDERABAD

118

Components of Spillway Bridge


Deck Slab
Longitudinal Girders
Cross Girders
Neoprene Bearings
Pedestals

Aug 7, 2016

NAC , HYDERABAD

119

Instruments used in
Spillways

Aug 7, 2016

Stress meters
Strain meters
Thermo meters
Vertical plumb bob
Inverted plumb line
Joint meters
Pore pressure cells
Uplift measuring cells
Seismometers
NAC , HYDERABAD

120

HYDRO MECHANICAL
COMPONENTS

Aug 7, 2016

NAC , HYDERABAD

121

GATES
Radial Gates
For High Heads; H > 6m

Vertical Gates
For low heads;

Aug 7, 2016

NAC , HYDERABAD

H < 6m

122

RADIAL GATE

Aug 7, 2016

NAC , HYDERABAD

123

GUNDLAKAMMA PROJECT

Aug 7, 2016

NAC , HYDERABAD

124

RADIAL GATE DESIGN


Radius of gate - H to 1.25 H
( H= vertical distance between top of gate and the
horizontal through sill)

Trunnion Location:
1.5 m clear of water profile

Location of Sill:
Slightly downstream of crest and to be located as far as
possible a vertical plane tangent to the u/s face of the
skin plate will intersect the spillway at or d/s from the
crest

Aug 7, 2016

NAC , HYDERABAD

125

KOVVADA KALVA PROJECT

Aug 7, 2016

NAC , HYDERABAD

126

Aug 7, 2016

NAC , HYDERABAD

127

Aug 7, 2016

NAC , HYDERABAD

128

Radial Gates -

DATA REQUIRED

U/S and D/S equations of Ogee crest of


Spillway
Sill level of Radial and Stop log gates
Top of the gate.
Radius of the gate.
Trunnion level.
Hoist level and its location.
Road bridge level and all other important
details
Aug 7, 2016

NAC , HYDERABAD

129

STOP LOG GATES

Aug 7, 2016

NAC , HYDERABAD

130

Aug 7, 2016

NAC , HYDERABAD

131

YELERU PROJE

Aug 7, 2016

NAC , HYDERABAD

132

LIST OF B.I.SCODES FOR DESIGN OF SPILLWAYS


Sl.No

Aug 7, 2016

COMPONENT

I.S.CODE No.

Reservoir capacity-Maximum flood discharge


SPF/PMF/5OO/1OOO/year flood and fixing of
spillway capacity and considering gate inoperative
condition.

5477-1971
11223-1985

Site Selection

6966-1989

3.

Permeability in rock below Gravity Dams

11216-1985

4.

In-situ Permeability test

5529-1985

Selection of Spill ways and dissipators

10137-1982

Foundation treatment Consolidation GroutingPressure grouting

6066-1994

Design Criteria of solid Gravity Dams


stability analysis, Load combinations, Loads
Factors of safety against sliding
Fetch and free board computations

6512-1984

Hydraulic design of High Ogee Overflow Spillways


Ogee Profile, U/S and D/S Quadrants, computation
of Coefficient of discharge, provision of Breast
wall etc.,

6934-1998

Hydraulic Design of Bucket type Energy dissipator


(a) Solid Roller (b) Slotted Roller
(c) Trajectory Bucket

7365-1985

10

Hydraulic jump type stilling basins

4997-1968

NAC , HYDERABAD

133

Aug 7, 2016

11

Structural arrangement of energy dissipator for


spillways

11527-1985

12

Drainage arrangements of Energy Dissipators,Spacing


of contraction joints, size and spacing of half round
pipes-details of no fine concrete blocks.

11772-1986

13

Water stops at transverse contraction joints in


Spillways,NOF dams and at junctions of galleries

12200-2001

14

Construction of Spill ways-preparation of foundations


and anchorage, maximum size of aggregates for
different components, blocks lengths etc.,

11155-1994

15

Galleries and other openings in dams drainage gallery,


inspection gallery, instrumentation gallery ,adits ,sump
well and pump chambers ,stair wells, lift etc.,
general and structural design

12966-1990&1992
parts 1&2

16

Curtain Grouting from galleries spacing ,depth of


grouting ,size and inclination of grout holes-pressure of
grouts etc.,

11293-1993
Part-2

17

Shear parameters at interface of foundations of Dam


with Rock.In-situ shear test on rocks

7746-1991

18

General construction of plain and R.C.C.for dams

457-1957

19

Aggregates ,Fine and Coarse for concrete

383-1997
(reaffirmed)

20

HYSD bars and wires for concrete Reinforcement

1786-1990
(Reaffirmed)

NAC , HYDERABAD

134

21

Drainage system for gravity dams, their foundations


and abutments
(a)spacing ,size and depth of drainage holes
(b)size of porous concrete and formed drains

10135-1985

22

Earth Quake resistant design of structures seismic


zone, and computations, hydrodynamic forces and
values at different elevations

1893 -1984

23

Dewatering during construction

9759-1981
(Reaffirmed-1998)

24

Extreme weather concreting


(1)Hot weather
(2) Cold weather

7861-1975
(Reaffirmed-2002)

25

Temperature control of mass concrete for dams

14591-1999

26

Computation of seepage provision of sump well and


pump chamber-size of sump etc.,

4721-2000

27

Radial gates radius, trunion level etc.,

4623-2000

28

Instrumentation

7436(part-ii)-1997

part-1-2000

Location of measuring instruments in concrete & masonry


dams.

Selection ,splicing, Installation and providing


protection to the open ends of cables used for
connecting type measuring devices in concrete and
masonry dams.

Aug 7, 2016

NAC , HYDERABAD

10334-1982

135

B.I.S CODES
.
S. No.

IS CODE AND YEAR

DESCRIPTION

(latest)

IS:800-1994

General construction in steel code of practice

IS:807-1976

Code of practice for Design, manufacture,erection


and testing structural portion of cranes and hoists

IS:3177-1999

Code of practice for Electric overhead traveling cranes


and Gantry cranes other than steel work cranes

IS:4622-1992

Recommendations for fixed wheel gates structural design

IS:4623-2000

Recommendations for structural design of Radial gates

IS:5620-1985

Recommendations for structural design criteria for low


head slide gates

Aug 7, 2016

IS:13591-1992

Criteria for design of Lifting Beams

NAC , HYDERABAD

136

B.I.S CODES
8

IS:6938-1989

Code of practice for design of Rope drum and chain Hoists


for Hydraulic Gates

Is:9349-1986

Recommendations for structural design of medium and


high head slide gates

10

IS:10210-1993

Criteria for design of hydraulic hoists for gates

11

IS:11228-1985

Recommendations for design of screw hoist for hydraulic gates

12

IS:11388-1985

Recommendations for design of Trash racks for intakes

13

IS:11855-1986

General requirements for rubber seals for hydraulic gates

14

IS:14177-1994

Guide lines for painting system for hydraulic gates and hoists

Aug 7, 2016

NAC , HYDERABAD

137

Aug 7, 2016

NAC , HYDERABAD

138