Escolar Documentos
Profissional Documentos
Cultura Documentos
6
9/11/16
Nabil Dmaidi
University
Najah
CATEGORIES OF RESOURCES
Labor
Materials
Equipments.
9/11/16
Nabil Dmaidi
University
Najah
Labor
1. Salaried staff: like-project engineer,
secretary.
2. Hourly workers: like-carpenters.
9/11/16
Nabil Dmaidi
University
Najah
Resourc
e need
Resource Profiles
Actual, not
leveled
Leveled,
realistic
9/11/16
Nabil Dmaidi
University
Idea
l
Najah
Time
Sort
9/11/16
Nabil Dmaidi
University
Najah
9/11/16
Nabil Dmaidi
University
Najah
Activities Sort
Resource
unit
TF
ES
Duration
Activity
8H
9H
7H
5H
11
4H
8H
16
2H
11
4H
20
Nabil Dmaidi
University
Najah
Major Sort
Resource
unit
TF
ES
Duration
Activity
8H
9H
7H
4H
2H
11
5H
11
8H
16
4H
20
University
Najah
10
TF
ES
Duration
Activity
8H
9H
7H
4H
5H
11
2H
11
8H
16
4H
20
Nabil Dmaidi
University
Najah
11
Allocated resources
8H
A
9H 9H 9H 9H 9H 9H 9H 9H 9H
Activity
B
7H 7H 7H 7H 7H
C
4H 4H 4H 4H
E
5H 5H 5H 5H 5H
D
2H 2H 2H 2H 2H 2H
8H 8H 8H 8H
F
4H
H
9/11/16
Nabil
8 Dmaidi
10
University
Time
Najah
12
14
16
18
20
12
Time
10
12
14
16
18
20
8H
A
9H 9H 9H 9H 9H 9H 9H 9H 9H
B
7H 7H 7H 7H 7H
Activity
C
4H 4H 4H 4H
E
5H 5H 5H 5H 5H
D
G
2H 2H 2H 2H 2H 2H
8H 8H 8H 8H
F
4H
H
Total Labor
9/11/16
8 16 16 16 16 16 1313 13 13 7
7 7
7 10 8
Dmaidi
Najahaggregation
EarlyNabil
start
resources
University
8 8 4
13
Resource Aggregation
Resources aggregation: is a summation of
the resources that are used to carry out the
program on a time period basis. For example,
day to day , or week to week.
9/11/16
Nabil Dmaidi
University
Najah
14
Total Labor
8 16 16 16 16 16 1313 13 13 7
7 7
7 10 8
8 8 4
Labor
16
14
12
10
8
6
4
2
2
9/11/16
4
6
12
8
10
14
16
18
Nabil Dmaidi
Najah
Early start resources aggregation
diagram (Histogram)
University
20
Time
15 15
Late start
Another histogram can be obtained if
Late start considered. Shows different
resources demand.
And many histograms can be obtained
considering a different time in the
network.
Each histogram shows different
resources demand.
9/11/16
Nabil Dmaidi
University
Najah
16
TF
LS
Duration
Activity
8H
9H
7H
4H
10
5H
11
2H
14
8H
16
4H
20
Nabil Dmaidi
University
Najah
17
Time
2
12
10
14
16
18
20
8H
A
9H 9H 9H 9H 9H 9H 9H 9H 9H
B
7H 7H 7H 7H 7H
Activity
4H 4H 4H 4H
E
5H 5H 5H 5H 5H
2H 2H 2H 2H 2H 2H
8H 8H 8H 8H
4H
Total Labor
9/11/16
8 9 9
9 16 16 1616 16 13 9
Late
9 7
Nabil Dmaidi
Najah
University
start resources aggregation
7 10 10 10 10 4
18
Total Labor
8 9 9
9 16 16 1616 16 13 9
9 7
7 10 10 10 10 4
Labor
16
14
12
10
8
6
4
2
2
9/11/16
10
Nabil Dmaidi
12
Najah
14
16
18
20
19
Time
Total Labor
8 9 9
9 16 16 1616 16 13 9
9 7
7 10 10 10 10 4
Labor
16
14
12
10
8
6
4
2
2
10
12
14
16
18
20
Time
Nabil Dmaidi
Najah
9/11/16
20
Early start vs Late start resources
University
aggregation diagram (Histogram)20
Total Labor
8 9 9
9 16 16 1616 16 13 9
9 7
7 10 10 10 10 4
Labor
16
14
12
10
8
6
4
2
2
10
12
14
16
18
20
Nabil Dmaidi
Najah
9/11/16
21
21Time
Early start vs Late start resources
University
aggregation diagram (Histogram)
Example
10
6 0 0
F
13
10 0 6 16
13 0 6 19
16
12
11 0 0 11
11
I
17
A
1
16
16 6 6 22
B
6
11
Dur. LS
EF9/11/16
FF TF LF
6 6 22
22
11
14 0 0 14
22
24 0 0 24
J
12
14
8 0 6 14
ES
19
D
6
14
22 0 0 22
H
16
6
Nabil8 Dmaidi
University
14 8 8 22
Najah
22
Activities Sort
Activity
9/11/16
Resource
unit
TF
ES
Duration
Activity
8H
2H
4H
9H
5H
5H
10
2H
11
8H
11
5H
13
2H
14
6H
22
Dmaidi
Najah
sort with ES time asNabil
Major
sort & TF
and duration as Minor Sorts23
University
2
A
Time
8
10
12
14
16
20
22
24
8H 8H 8H 8H 8H
2H 2H 2H 2H 2H
4H 4H
9H 9H
9H
9H 9H 9H
9H
5H 5H 5H
5H 5H 5H
5H 5H 5H
5H 5H 5H
2H 2H 2H
8H 8H
5H 5H 5H
2H 2H 2H 2H 2H 2H 2H 2H
6H 6H
Total
Labor
18
8 8
9/11/16
8 8
8 15 1516 16 12 20 20 17 12 12 2 2
Nabil Dmaidi
University
Najah
2 2 2 2 6
6
24
Total
Labor
8 8
8 8
8 15 1516 16 12 20 20 17 12 12 2 2
2 2 2 2 6
25
20
18
Labor
16
14
12
10
8
6
4
2
2
9/11/16
10
12
Nabil Dmaidi
University
Time
14
16
Najah
18
20
22
24
Activities Sort
Resource
unit
TF
LS
Duration
Activity
8H
2H
4H
12
9H
12
5H
16
5H
16
2H
11
8H
17
5H
19
2H
14
0
22
2
6H
K
Activity sort with LS time as Major sort & TF and duration as Minor Sorts
9/11/16
Nabil Dmaidi
University
Najah
26
2
A
Time
8
10
12
14
16
18
20
22
8H 8H 8H 8H 8H
2H 2H 2H 2H 2H
4H 4H
9H 9H 9H 9H
5H 5H 5H 5H 5H 5H
5H 5H 5H 5H 5H 5H
2H 2H 2H
8H 8H
5H 5H 5H
2H 2H 2H 2H 2H 2H 2H 2H
6H 6H
Total
Labor
24
8 8
9/11/16
8 8
2 2 2
Late
2 15 15 11 11 12 20 2017 17 17 6
Nabil Dmaidi
Najah
University
start resources aggregation
6
27
Total
Labor
8 8
8 8
2 2 2
2 15 15 11 11 12 20 20 17 17 17 6 6
20
18
Labor
16
14
12
10
8
6
4
2
9/11/16
10
12
Nabil Dmaidi
University
Time
14
Najah
16
18
20
22
24
28
Late start resources aggregation diagram
Early start
Labor
20
18
16
14
12
10
8
6
4
2
Late start
Labor
20
18
16
14
12
10
8
6
4
2
9/11/16
Nabil Dmaidi
University
Najah
29
Smoothing/Leveling
Let us program activity F to start by its late
start day which is day 17.
And activity I to start by day 14.
The resulting resources aggregation
histogram will be as follows:
9/11/16
Nabil Dmaidi
University
Najah
30
2
A
Time
8
10
12
14
16
18
20
22
8H 8H 8H 8H 8H
2H 2H 2H 2H 2H
4H 4H
9H 9H
9H
9H 9H 9H
9H
5H 5H 5H
5H 5H 5H
5H 5H 5H 5H 5H 5H
2H 2H 2H
8H 8H
5H 5H 5H
2H 2H 2H 2H 2H 2H 2H 2H
6H 6H
Total
Labor
24
8 8
9/11/16
8 8
8 15 1516 16 12 12 12 12 12 12 7 10 10 2 2 2 6 6
Nabil Dmaidi
Najah
31
Early start resources
aggregation
University
Total
Labor
8 8
8 8
8 15 15 16 16 12 12 12 12 12 12 7 10 10 2 2 2 6
20
18
Labor
16
14
12
10
8
6
4
2
2
9/11/16
Nabil
12
10 Dmaidi
University
Time
Najah
14
16
18
20
22
24
32
Smoothing/Leveling
9/11/16
Nabil Dmaidi
University
Najah
33
2
A
Time
8
10
12
14
16
18
20
22
24
8H 8H 8H 8H 8H
2H 2H 2H 2H 2H
4H 4H
9H 9H
9H
9H 9H 9H
9H
5H 5H 5H
5H 5H 5H
5H 5H 5H
2H 2H 2H
8H 8H
5H 5H 5H
2H 2H 2H 2H 2H 2H 2H 2H
6H 6H
K
Total
9/11/16
8 8
Labor
5H 5H 5H
8 8
8 15 1516 Nabil
16 Dmaidi
7 University
15 15 Najah
12 7 7
7 7
7 7 7 7 634 6
Total
Labor
8 8
8 8
8 15 15 16 16 7 15 15 12 7
7 7
7 7 7 7 6
20
18
Labor
16
14
12
10
8
6
4
2
9/11/16
2
Nabil Dmaidi
12
10 University
Time
Najah
14
16
18
20
22
35
24
Smoothing/Leveling
In case activity D is split able activity. It
could be interrupted to be carried out in tow
parts.
Let us program activity B to start by 7th day .
And activity H to starts by its Late start date.
And activity E to start by day 14.
The resulting resource aggregation and
histogram will be as follows:
9/11/16
Nabil Dmaidi
University
Najah
36
2
A
Time
8
10
12
14
16
18
20
22
24
8H 8H 8H 8H 8H
2H 2H 2H 2H 2H
4H
4H
9H 9H 9H 9H
5H 5H 5H
5H 5H 5H
5H 5H 5H 5H 5H 5H
2H 2H 2H
8H 8H
5H 5H 5H
2H 2H 2H 2H 2H 2H 2H 2H
6H 6H
Total
8 8
Labor 9/11/16
8 8
8 6
11 11 Nabil
11 11
10 10 Najah
11 12 12 12 12 12 12 7 7
Dmaidi
University
Early start resources
aggregation
37
Total
Labor
8 8
8 8
8 6
11 11 11 11 10 10 11 12 12 12 12 12 12 7 7
20
18
Labor
16
14
12
10
8
6
4
2
9/11/16
2
Nabil Dmaidi
12
10 University
Time
Najah
14
16
18
20
22
38
24
Najah
WHY ?!
Nabil Dmaidi
University
39
Nabil Dmaidi
University
Najah
40
9/11/16
Nabil Dmaidi
University
Najah
41
University
42
Example
A
1
2
1
0
B
1
11 0
8H
Activity desc.
2
0 11
11
16 0
F
16
11
0 16
20 0
5H
8H
5
0
5
3 10
7H
7
11 0
11
10
3 14
H
16
0 20
9H
2
7
17 3
20
21 0
20
0 21
4H
14
3 20
2H
4H
ES Dur. LS
EF FF TF LF
Resources
9/11/16
Nabil Dmaidi
University
Najah
43
Resource
unit
TF
ES
Duration
Activity
8H
9H
7H
4H
5H
11
2H
11
8H
16
4H
20
Nabil Dmaidi
University
Najah
44
9/11/16
Nabil Dmaidi
University
Najah
45
Total Labor
8 16 16 16 16 16 1313 13 13 7
7 7
7 10 8
8 8 4
Labor
16
14
12
10
8
6
4
2
9/11/16
2
4
6
12
8
10
14
16
18
Nabil Dmaidi
Najah
Early start resources aggregation
diagram (Histogram)
University
20
Time
46 46
Activity
2
A
B
C
E
D
G
F
H
Total Labor
Time
10 12 14 16 18 20 22
8H
9H 9H 9H 9H 9H 9H 9H 9H 9H
7H 7H 7H 7H
4H 4H 4H 4H
5H 5H 5H 5H 5H
2H 2H 2H 2H 2H 2H
8H 8H 8H
4H
8 9 9 9 9 9 9 9 9 9 7 7 7 7 9 9 9 9 7 10 10 10 2 2 4
12
Labor
Limit
10
Labor
24 26
8
6
4
2
9/11/16
NabilTime
Dmaidi
University
Najah
47
9/11/16
Nabil Dmaidi
University
Najah
48
Hint
: Construction costs includes
.Materials costs( 1
.labor costs( 2
plant and equipment costs( 3
. overhead costs and profit( 4
9/11/16
Nabil Dmaidi
University
Najah
49
Example
10
6 0 0
F
13
10 0 6 16
13 0 6 19
16
12
11 0 0 11
11
I
17
A
1
16
16 6 6 22
B
6
11
Dur. LS
EF9/11/16
FF TF LF
6 6 22
22
11
14 0 0 14
22
24 0 0 24
J
12
14
8 0 6 14
ES
19
D
6
14
22 0 0 22
H
16
6
Nabil8 Dmaidi
University
14 8 8 22
Najah
50
9/11/16
)$Cost)
TF
ES
Duration
Activity
650
1300
400
1450
500
1100
10
600
11
350
11
1000
13
1300
14
200
22
Nabil Dmaidi
University
Najah
51
2
A
C
Time
12
10
100250
9H
9H 300
9H 100
9H
150 100
22
24
20
18
16
14
200 100100
100 100 150 200 100100 150 100
100 100
Total
Dmaidi
Najah
200 100 200 100 50 350 550550 Nabil
400 500
750 450 600
300 350 150 200 100100 150 100 100
52100
cost 9/11/16
University
Total
cost
200 100 200 100 50 350 550550 400 500 750 450 600 300 350 150 200 100100 150 100 100 100
800
700
600
500
400
300
200
100
9/11/16 2
Nabil Dmaidi
12
10University
Time
Najah
14
16
18
20
2253 24
Cash Flow
It is quite significant to the contractor to
know the amount of money that would be
spent in each stage of the project.
( Expenditures)
And compare it to the amount of money that
would be received. (income)
Overtrading
Nabil Dmaidi
University
Najah
54
Total
cost
Com.
cost
200 100 200 100 50 350 550550 400 500 750 450 600 300 350 150 200 100100 150 100 100 100
200 300 500 600 650 1000 1550 2100 2500 30003750 4200 4800 51005450 5600 580059006000 6150 625063506450
$
6400
6000
5600
5200
4800
4400
4000
3600
3200
2800
2400
2000
1600
1200
800
400
9/11/16 2
4
Com. cost = Cumulative Cost
Nabil Dmaidi
12
10University
Time
Najah
14
16
2255 24
18
20
Cash Flow Diagram
Retainage Release
Expenditures
Revenues
Cumulative
Expenditure
s
& Revenues
9/11/16
Amount of
Negative
Cash Flow
Nabil Dmaidi
Najah
Time (Months)
University
56
$$$
$$
early
planned
late
Time
9/11/16
Nabil Dmaidi
University
Najah
57
Profi
t
Spending
Reimburseme
nt
Time
9/11/16
Nabil Dmaidi
University
Najah
58
9/11/16
Nabil Dmaidi
University
Najah
59
Nabil Dmaidi
University
Najah
60
Nabil Dmaidi
University
Najah
61
Materials Management
Is defined as the planning and controlling of all
necessary efforts to ensure that the correct
quality and quantity of materials and
equipment are appropriately specified in a
timely manner, are obtained at a reasonable
cost, and are available when needed.
9/11/16
Nabil Dmaidi
University
Najah
62
9/11/16
Nabil Dmaidi
University
Najah
63
Objectives of materials
management
Ensure that materials meet the
specifications and are on hand when and
where required.
Obtain the best value for purchased
materials.
Provide efficient, low-cost transport,
security, and storage of materials at
construction sites.
Reduce any surplus to the lowest level
Nabil Dmaidi
Najah
9/11/16
possible.
University
64