Escolar Documentos
Profissional Documentos
Cultura Documentos
on
Network Analysis - II
By
Dr. D. B. Naik (Ph.D.- Mech. Engg.)
Professor, Training & Placement
Sardar Vallabhbhai National Institute
of Technology, Surat
PERT
CPM & PERT Comparison
Statistical aspects - Calculation
Three Time Estimate in PERT
Variance & Standard Deviation
Calculation of Probability
Case Study
PERT
Deterministic
Probabilistic
No statistics applicable
Statistics Applicable
Activity Oriented
Event Oriented
Known Project
New Project
Accuracy - 100 %
Accuracy - Probability
PERT Activity :
i
to - tm - tp
to = a = Optimistic time
tm = m = Most likely time
tp = b = Pessimistic time
B distribution
to
tm
tp
to
te
tm
tp
ij
to - tm - tp
Vij = Variance
=
ij
project
V project
project
( i j ) critical on C . P .
( i j ) critical on C . P .
A
0
Z 0.00 0.01
0.0
0.1
0.2
..
1.0
..
3.0 0.4986
+Z
0.02 . . . . . . . 0.09
0.0359
0.0870
0.3621
0.4990
project
Case Study :
A project has the following time
estimate in weeks for each of its activities.
to
tm
tp
Activity
1-2
1-3
2-3
2-4
3-4
3-5
4-6
5-6
3
7
3
3
2
3
5
4
6
8
6
5
5
9
8
6
21
27
09
13
08
21
35
08
to
tm
tp
te
1-2
1-3
2-3
2-4
3-4
3-5
4-6
5-6
3
7
3
3
2
3
5
4
6
8
6
5
5
9
8
6
21
27
09
13
08
21
35
08
8
11
6
6
5
10
12
6
3
3.33
1
3.33
1
3
5
0.66
3-5-13
3-6-9
1
7-8-27
5-8-35
2-5-8
3
3-9-21
4-6-8
8
1
11
5
3
12
10
6
TE=31
8 2
6
=3
=1 4
12
1
6
6
=5
5 =1
TE=31
11
6
3
5
10
V project
V ( i j ) critical on C . P .
=
=
=
project
( i j ) critical on C . P .
2
( i j ) critical on C . P .
8 2
6
=3
=1 4
12
1
6
5 =1 =5
11
6
3
5
10
project
=
=
( i j ) critical on C . P .
3 1 1 5
= 6
6
TE=31
this duration ?
8
1
11
12
10
The expected time of completion
of project is 31 weeks
6
TE=31
for
project
TS = TE
Z= 0
Hence Probability = 0.5 = 50%
Z = -1
Z = (25-31)/6 = -1
For Z=1
Z= 1
A= 0.3413
Hence for Z= -1
Z = (43-31)/6 = 2
Z=2
Z= 2
For Z=2
A= 0.4772
Hence for Z= 2
Z = -1
Z=2
0.3413 0.4772
Z = -1
Z=2
For TS Beyond 43
0.4772
Z= 2
Probability = 0.5 - 0.4772
= 0.0228
= 2.28%
0.25
Z = -0.675
-0.675 = (TS - 31)/6
Hence TS = 27 weeks
RECAPITULATION
CPM & PERT Comparison
Statistical aspects - Calculation
Three Time Estimate in PERT
Variance & Standard Deviation
Calculation of Probability
Case Study
GATE PROBLEM
10
(d) 97.7 %
5
6
1 68.26%
99.72%
2 95.44%
Variance = 4
Z = (TS TE) /
= (24 20) / 2
= 2
Probability =
Z=2
= 50 + (95.44/2)
= 97.7 %
GATE PROBLEM
In PERT network activity a = 9 days b = 21 days
and m = 15 days. The approx. probability of
completion of this activity in 13 days is :
(a) 16%
(b) 34%
(c) 50%
(d) 84%
= (21 9) / 6 = 2
Z = (TS TE) /
= (13 15) / 2
=1
Probability =
Z = -1
= 50 (68.26/2)
= 15.87 %
(b) 2
(c) 3
(d) 6
GATE QUESTION
In PERT, the distribution of activity times is
assumed to be :
(a) Normal
(b) Gamma
(c) Beta
(d) Exponential
180
220
23
12
14
150
220
36
1 2, 2 3
12
180
240
14
240
300
45
14
12
80
11
200
200
400
5 6 indirect
1 4,cost
4 5Rs. 40 6per day.
Consider
(i)
( ii )
( iii )
[2]
Activity
Duration
Normal
Crash
12
60
23
85
24
11
65
25
34
90
45
70
56
240
[3]
Activity
12
13
24
14
25
15
36
46
57
67
14
12
23
35
10
16
Typical
Questions
C D E F G
A B B D E
H
C
I
F,G
tm (days)
9 11 4 11 5 13
tp (days)
8 14 27 29 7 17 14 31
( i )
Draw the network and find expected completion
duration of project.
12
Normal Duration (days)
9
13
8
14
15
24
5
34
10
45
2
12
200
180
300
100
300
120
260
255
390
120
360
160
Cost slope
(Rs./day)
20
25
30
10
15
40
(i)
12
1
1
7
13
1
4
7
14
2
2
8
25
1
1
1
35
2
5
14
46
2
5
8
56
3
6
15
Find expected time of project completion.
Thank you
For any Query or suggestion :
Contact :
Dr. D. B. Naik
dbnaik@gmail.com
dbnaik@svnit.ac.in
dbnaik_svr@yahoo.com