ANALYSIS OF PRICE

BUILT UP RATES FOR BRICKWORKS


TABLE 1: LABOUR CONSTANT PER M2 (COMMON BRICKS)

DESCRIPTION

UNIT

SKILLED

WORKER
(HR)

UNSKILLED
(HR)

HALF BRICKWALL BELOW DPC

m2

0.90

0.45

ONE BRICKWALL DITTO

m2

1.80

0.90

ONE AND HALF BRICKWALL DITTO

m2

2.50

1.25

HALF BRICKWALL ABOVE DPC

m2

1.00

0.50

ONE BRICKWALL DITTO

m2

2.00

1.00

ONE AND HALF BRICKWALL DITTO

m2

2.70

1.35

EXTRA FOR FAIR FACE IN STRETCHER


BOND

m2

+0.30

+0.15

DITTO IN FLEMISH BOND

m2

+0.35

+0.175

DITTO IN ENGLISH BOND

m2

+0.40

+0.20

ANALYSIS OF PRICE
BUILT UP RATES FOR BRICKWORKS
BRICKS FACEWORK: the following is the no. of facing
bricks required per m2 of brickwork to all which is faced on
one side only. *allow - 5% wastage
TYPE OF BOND

NO. OF BRICK

STRETCHER BOND

59

HEADER BOND

118

ENGLISH BOND

89

FLEMISH BOND

79

ENGLISH GARDEN WALL

74

FLEMISH GARDEN WALL

67

ANALYSIS OF PRICE
BUILT UP RATES FOR BRICKWORKS

NO. OF COMMON
BRICKS PER M2

MORTAR
Labour mixing 2.05hr/m3

One brickwall 118 pcs


Mortar used per m2
Half brickwall 59 pcs
One brickwall 0.052 m3
Half brickwall 0.032 m3

ANALYSIS OF PRICE
BUILT UP RATES FOR BRICKWORKS
Analyse unit rates of one brickwall in common bricks in
cement and sand mortar (1:3) laid in English bond.
BASIC MAT. PRICES
Cement

RM10.50/bag

Bricks

RM0.21/pc

Sands

RM11/m3

Exmet

RM0.65/m

Damp proof course

RM1.00/m

LABOUR WAGES PER DAY


Bricklayer

RM60

Unskilled

RM30

ANALYSIS OF PRICE
BUILT UP RATES FOR BRICKWORKS
Analyse unit rates of one brickwall in common bricks in cement and
sand mortar (1:3) laid in English bond.
MATERIALS MORTAR (1:3), COMMON BRICKS
LABOUR BRICK LAYER, LABOURER

MORTAR
1 mc cement 28.4 bag @ 10.50
3 mc sand 3 @ 11.00

298.20
33.00
331.20

Add consolidating & wastage


33%
Therefore Cost of 1 MC
440.50
4
Add labour for mixing mortar per m3
2.05hr @ 30.00
8
Therefore 1 MC mortar (1:3) would cost

109.30
440.50

110.13

7.69
RM117.82

ANALYSIS OF PRICE
BUILT UP RATES FOR BRICKWORKS
COMMON BRICKS
MATERIALS
Bricks for 1 m2 of 1B wall
118pcs @ 0.21/pc
Mortar for 1 m2 of 1B wall
0.052 m3 @ 117.82

24.78
6.13
30.91

LABOUR ( refer labour constant)


Brick layer
2.0 hrs @ 60.00
8
Labourer
1.0 hr @ 30.00
8

15.00

3.75

Add Overhead & Profit 15%


TOTAL

18.75
49.66
7.45
RM57.11

ANALYSIS OF PRICE
BUILT UP RATES FOR BRICKWORKS
Analyse the unit rates of half brickwall in common bricks in cement & sand (1:3) laid in
Stretcher bond with and including exmet at every fourth course.
MATERIALS MORTAR (1:3) COMMON BRICKS, EXMET
LABOUR BRICK LAYER, LABOURER
MATERIALS
Bricks for 1m2 of B wall
59pcs @ 0.21/pc
12.39
Mortar for 1m2 of B wall
0.032m3 @ 117.82
3.77
Exmet (3 layers)
3 @ 0.66/m
1.95
18.11
LABOUR
Brick layer -1hr @ 60.00/8
Labourer-0.5hr @ 30.00/8
9.38
27.49
Add Overhead & Profit 15%
TOTAL:

7.50
1.88

4.12

RM31.61

ANALYSIS OF PRICE
BUILT UP RATES FOR DOOR & WINDOW
FRAME
Door and window frame should be price per
linear meter.
material to add 5% waste
SIZE OF FRAME

JOINER HOURS

37mm X 150mm

0.25

50mm X 150mm

0.30

50mm X 175mm

0.40

ANALYSIS OF PRICE
BUILT UP RATES FOR DOOR & WINDOW
FRAME
Analyse price per linear meter for 50mm X 150mm door frame in Grade A
timber.
Data : 50mm X 150mm Frame RM12/m
Material
1m
Add 5% waste
Labour
0.30 @ 30.00
8
Add 15% overhead & profit

12.00
0.60
12.60

1.10
13.70
2.06
RM15.76/m

ANALYSIS OF PRICE
BUILT UP RATES FOR DOOR & WINDOW
Method of estimating

Find cost of material skeleton frame, plywood cover, etc.


Add 5% waste

Labour for fixing for m2 of timber

15% overhead & profit

LABOUR FOR FIXING & HANGING PER M2

JOINER HRS

40mm skeleton framed flush door

1.00

40mm solid cored framed flush door

1.25

50 mm ditto

1.40

25mm framed, hedged & braced door

0.80

50 mm ditto

1.40

54mm fired door

1.50

ANALYSIS OF PRICE
BUILT UP RATES FOR DOOR & WINDOW
Analyse price for 40mm skeleton framed flush door covered both side with
5mm plywood size 850mm X 2050mm and hanging on butt hinges (m/s).
Data 850mm X 2050mm X 40mm thick flush door RM85/no.
Material
1 no. door
add 5% waste

Labour
1hr @ 30.00 @ 0.85 @ 2.05
8
Add 15% overhead & profit
Therefore cost 40mm flush door/no

85.00
4.25
89.25

6.53
95.78
14.37
RM110.15