PROCUREMENT PROCESS
Procurement Unit
Preparation of Request for Quotation (RFQ) - within 1 day from submission of signed PR
Procurement Unit
Execution of Purchase Order (PO) - at least 1 day from receipt of NOA
- PO is equivalent to contract
Implementation
NEGOTIATED
PROCUREMENT - HIGHLY
TECHNICAL CONSULTANT
(Individual)
End-user
Preparation of PR - at least 30 working days before PAPs implementation
NOTE: Pls. make sure that procurement must be
based on the APP (No APP, no procurement shall be
made Sec. 7.2 Revised IRR RA 9184)
End-user
Selection and Negotiation of - 1 day from completion of invitation
Consultant - consideration for selection of consultant:
1. qualifications
2. eligibility
3. appropriate education
4. training & relevant experience to render
consultancy services
End-user
Submission to Procurement - within 3 days from completion of invitation
Unit of the required/necessary - documents to be submitted include invitation letter,
Terms of Reference (TOR), resume, conforme letter,
documents etc.
Consultant
Posting of Performance Security - within 10 calendar days from receipt of NOA (Sec. 39 RA 9184)
- amount of performance security depends upon the
form of performance security either cash/cashier check,
bank draft, surety bond, etc.
Consultant
Submission of Official Receipt - within 1 day from posting of performance security
(OR) to Procurement Unit
Procurement Unit, AFD Chief, Exec. Dir., &
Contract Award and Consultant
Execution of Contract - within 5 days from receipt of official receipt, contract shall be
executed
- Within 10 calendar days from receipt of NOA, NYC and
consultant shall enter into a contract (Sec. 37.2.2 Revised IRR RA
9184)
Contract Implementation
Negotiated Procurement
thru Lease of Real
Property and Venue
End-user
Preparation of PR - at least 30 working days before PAPs implementation
NOTE: Pls. make sure that procurement must be
based on the APP (No APP, no procurement shall be
made Sec. 7.2 Revised IRR RA 9184)
Preparation and Signing of Procurement Unit, AFD Chief, Exec. Dir., and
Supplier
Notice of Award (NOA) - at least 1-2 days from determination of LCRB
Procurement Unit
Execution of Purchase Order (PO) - at least 1 day from receipt of NOA
- PO is equivalent to contract
Issuance and signing of Notice to Procurement Unit, AFD Chief & Exec. Dir.
- within 3 calendar days from approval of contract/PO and
Proceed receipt thereof (Sec. 37.4.1 Revised IRR RA 9184)
Implementation
Negotiated
Procurement thru
Agency-to-Agency
End-user
- at least 30 working days before PAPs implementation
Preparation of PR - Procurement must be based on APP (Sec. 7.2 of
Revised IRR RA 9184)
End-user
Conduct of Cost-Benefit Analysis - at least 1 day from receipt of PR