ALTERNATIVE METHODS OF

PROCUREMENT PROCESS

(1) SHOPPING for ordinary


or regular supplies NOT
available in the
Procurement Service and
(2) SMALL VALUE
PROCUREMENT
End-user
Preparation of Purchase - at least 30 working days before PAPs
implementation except in cases of extreme
Request (PR) urgency
- Procurement must be based on APP (Sec. 7.2 of
Revised IRR RA 9184)
Submission of PR to Supervising Admin. End-user, SAO/PU, Budget Officer
Officer(SAO)/Procurement Unit (PU)for & Exec. Dir.
- at least 1-2 days from
verification of PR against Annual submission to AFD of PR for signing and
Procurement Plan (APP) notation of APP number

Procurement Unit
Preparation of Request for Quotation (RFQ) - within 1 day from submission of signed PR

Invitation of at least Procurement Unit


- if PhP50,000 or less: manual canvassing only;
three (3) suppliers or Posting of RFQ for 7 calendar 7-day posting is unnecessary
days in PhilGEPS, if more than PhP50,000.00 (maybe - If more than PhP50,000: PhilGEPS posting for
7 calendar days is mandatory; maybe extended
extended if no supplier submitted within 7 days) if none submitted within the 7-day

Determination & awarding of Lowest Calculated Bid Procurement Unit


that complies with specs (LCRB) and Approved - within 1 day from deadline of
posting/invitation
Budget of the Contract (ABC)
End-User, Procurement Unit, AFD Chief
Preparation and Signing of - at least 1-2 days from determination of
LCRB
Abstract Canvass

Preparation and Signing of Notice Procurement Unit, AFD Chief,


Exec. Dir., and Supplier
of Award (NOA) - at least 1-2 days from receipt of signed
Abstract of Canvass

Procurement Unit
Execution of Purchase Order (PO) - at least 1 day from receipt of NOA
- PO is equivalent to contract

Procurement Unit, AFD Chief,


Signing of PO Exec. Dir., and Supplier
- at least 2-3 days from receipt of signed NOA

Procurement Unit, AFD Chief


Issuance and signing of Notice to and Exec. Dir.
Proceed - Within 3 calendar days from approval & receipt of signed
PO (Sec. 37.4.1 Revised IRR RA 9184)

Implementation
NEGOTIATED
PROCUREMENT - HIGHLY
TECHNICAL CONSULTANT
(Individual)
End-user
Preparation of PR - at least 30 working days before PAPs implementation
NOTE: Pls. make sure that procurement must be
based on the APP (No APP, no procurement shall be
made Sec. 7.2 Revised IRR RA 9184)

Submission of PR to Supervising Admin. End-user, SAO/PU, Budget Officer &


Exec. Dir.
Officer(SAO)/Procurement Unit (PU)for - at least 1-2 days from
verification of PR against Annual submission to AFD of PR for signing and notation of
APP number
Procurement Plan (APP)

End-user with the assistance of


Invitation to prospective Procurement Unit
consultant/s - at least 5-7 days from receipt of signed PR

End-user
Selection and Negotiation of - 1 day from completion of invitation
Consultant - consideration for selection of consultant:
1. qualifications
2. eligibility
3. appropriate education
4. training & relevant experience to render
consultancy services
End-user
Submission to Procurement - within 3 days from completion of invitation
Unit of the required/necessary - documents to be submitted include invitation letter,
Terms of Reference (TOR), resume, conforme letter,
documents etc.

Procurement Unit, AFD Chief,


Preparation and Signing of Exec. Dir., and Supplier
Notice of Award (NOA) - at least 1-2 days from receipt of signed Abstract of
Canvass

Consultant
Posting of Performance Security - within 10 calendar days from receipt of NOA (Sec. 39 RA 9184)
- amount of performance security depends upon the
form of performance security either cash/cashier check,
bank draft, surety bond, etc.

Consultant
Submission of Official Receipt - within 1 day from posting of performance security
(OR) to Procurement Unit
Procurement Unit, AFD Chief, Exec. Dir., &
Contract Award and Consultant
Execution of Contract - within 5 days from receipt of official receipt, contract shall be
executed
- Within 10 calendar days from receipt of NOA, NYC and
consultant shall enter into a contract (Sec. 37.2.2 Revised IRR RA
9184)

Legal Affairs Unit


Contract Review - within 2 days from receipt of contract. Documents that form
part of the contract include contract agreement, bidding docs, bidders
bid, performance security, notice of award, & other contract docs.
(Sec. 37.2.3 Revised IRR of RA 9184)

Chairperson/Exec. Dir., Accountant, Witnesses, and


Contract Approval and Consultant
Signing - Within a maximum of 15 calendar days from receipt thereof, HOPE
shall approve the contract (Sec. 37.3 Revised IRR RA 9184)

Procurement Unit, AFD Chief & Exec. Dir.


Issuance and signing of - within 3 calendar days from approval of contract/PO and
Notice to Proceed receipt thereof (Sec. 37.4.1 Revised IRR RA 9184)

Contract Implementation
Negotiated Procurement
thru Lease of Real
Property and Venue
End-user
Preparation of PR - at least 30 working days before PAPs implementation
NOTE: Pls. make sure that procurement must be
based on the APP (No APP, no procurement shall be
made Sec. 7.2 Revised IRR RA 9184)

Submission of PR to Supervising End-user, SAO/PU, Budget Officer & Exec.


Dir.
Admin. Officer(SAO)/Procurement - at least 1-2 days from submission to AFD of PR for
Unit (PU)for verification of PR against signing and notation of APP number

Annual Procurement Plan (APP)

Conduct of Cost Benefit Analysis End-user


- at least 1 day from receipt of PR

Recommendation of end-user to lease End-user & Procurement Unit


- recommendation to be submitted to PU within 1
privately-owned real estate or venue day from conduct of cost benefit analysis

Invitation of at least three (3) Procurement Unit


- at least 5-7 days from receipt of PR
prospective lessors OR
Preparation of Rating Factor vis-a-vis End-user
- at least 1-2 days from invitation
Technical Specifications

Determination of Lowest Calculated and Procurement Unit


- within 1 day from deadline of invitation
Responsive Bid (LCRB)

Preparation and Signing of Procurement Unit, AFD Chief, Exec. Dir., and
Supplier
Notice of Award (NOA) - at least 1-2 days from determination of LCRB

Procurement Unit
Execution of Purchase Order (PO) - at least 1 day from receipt of NOA
- PO is equivalent to contract

Signing of PO Procurement Unit, AFD Chief, Exec. Dir., & Lessor


- at least 2-3 days from receipt of signed NOA

Issuance and signing of Notice to Procurement Unit, AFD Chief & Exec. Dir.
- within 3 calendar days from approval of contract/PO and
Proceed receipt thereof (Sec. 37.4.1 Revised IRR RA 9184)

Implementation
Negotiated
Procurement thru
Agency-to-Agency
End-user
- at least 30 working days before PAPs implementation
Preparation of PR - Procurement must be based on APP (Sec. 7.2 of
Revised IRR RA 9184)

End-user, Procurement Unit/SAO, Budget Officer & Exec. Dir.


Submission to SAO/PU for verification - at least 1-2 days from submission to AFD of PR for signing and
of PR against APP notation of APP number

End-user
Conduct of Cost-Benefit Analysis - at least 1 day from receipt of PR

Assessment and recommendation of end-user to End-user


- at least 1 day from receipt of cost-benefit analysis
use agency-to-agency

End-user & Procurement Unit


Securing of Certificate from Servicing Agency - within 3-5 days from receipt of PU of cost-
that it has the mandate to deliver benefit analysis
goods/consultancy required to be procured, etc.

BAC and HOPE


Issuance of BAC Resolution recommending - at least 7 days from receipt of certificate from
the use of A-to-A to Head of Procuring servicing agency, BAC shall issue BAC reso
Entity (HOPE)
Servicing agency, Accountant, Exec. Dir/
Execution of Memorandum of Agreement Chairperson, & HOPE
(MOA) after approval of BAC Resolution - at least 10 days from approval of BAC reso

Posting to PhilGEPS Procurement Unit


- posting for 7 calendar days of the general
Information of procurement activity