Escolar Documentos
Profissional Documentos
Cultura Documentos
CONTRACTS
CONTRACT LAW II
Actual Anticipato
Breach ry breach
Minor Material
Breach Breach
1. ACTUAL BREACH
Court held
that the defendant breached the sale agreement
dated 12th February 2013 and is accordingly entitled
to a refund of the entire consideration as agreed.
2. ANTICIPATORY BREACH
Court Held
Therefore, the court held that, it could as there was an anticipatory breach,
where the innocent party may either sue immediately.
3. MINOR BREACH
Facts of case
SCC (NZ) Ltd (SCC) provided call centre services to Samsung Electronics
New Zealand Ltd (Samsung). There was one system for recording
telephone inquiries and another system for recording email inquiries.
Under the call centre agreement (the agreement), Samsung paid
piecemeal rates for inquiries to the telephone system and a fixed annual
rate for inquiries to the email system.
Following an investigation, Samsung discovered SSC had recorded some
email inquiries as both email and telephone inquiries enabling SSC to
wrongfully claim payment for a fictitious telephone inquiry. The
investigation also uncovered other fictitious telephone with SSC admitted
to creating.
Samsung claimed that, by deliberately issuing false
invoices, SSC failed to act in good faith and had
committed a material breach of the agreement entitling
Samsung to terminate the contract.
SSC applied for an interim injunction arguing that there
was a serious question to be tried over whether Samsung
was entitled to terminate the agreement.
Court Held
Application by SSC was refused. Therefore, Samsung was
entitled to terminate the agreement for breach of good
faith.
STROUTH V. POOLS BY
MURPHY & SONS 79 CONN.
Facts of the case APP. 55 (2003)
the Strouths (plaintiffs) sought to have Pools by Murphy and Sons, Inc. (Pools by
Murphy) (defendant) install a swimming pool in their yard.
The Strouths selected a peanut-shaped pool with a circular spa from a brochure
and informed Pools by Murphy of its decision. The parties entered a contract
specifying that Pools by Murphy would construct a custom shaped pool for the
Strouths.
Construction commenced and Pools by Murphy excavated the yard and built a
steel frame.
However, the frame was in the shape of a kidney with an almond-shaped spa.
The Strouths ordered Pools by Murphy to discontinue construction. Pools by
Murphy eventually offered to complete construction of the kidney-shaped pool
with a circular spa.
The Strouths refused and brought suit against Pools by Murphy for breach of
contract.
Court held
The pools by Murphy substantially deviated
from the requirements of the contract
because construction of the kidney-shaped
pool was a material breach of the contract
and awarded the Strouths $10,618.63.
8.2 EFFECTS OF BREACH OF
CONTRACT
a) Breach of contract always entitled the
innocent party to claim damages.
Appellant took possession of the property prematurely. He then contended that the
Respondent failed to make the arrangements. The Appellant failed to make payments,
and also made a number of other small breaches of the agreement, which the
Respondent demanded remedy for. None was supplied by the Appellant. The
Respondent sued in order to regain possession, obtain damages and outstanding rent
Appellant took possession of the property prematurely. He
then contended that the Respondent failed to make the
arrangements.The Appellant failed to make payments,
and also made a number of other small breaches of the
agreement, which the Respondent demanded remedy for.
None was supplied by the Appellant.The Respondent sued
in order to regain possession, obtain damages and
outstanding rent.
COURT HELD
The contract contained a provision that limited the contractor's
liability for accidents and damage to 2,300 pounds. The Court of
Appeal held that, because of the fundamental breach, the
contractors were not entitled to rely on the liability-limiting
provision. The contractors were held liable for the cost of
reinstating the factory, an amount determined at trial to be in
excess of 170,000 pounds.
MCDONALD V DENNYS
LASCELLES LTD (1933) 48
CLR 457
FACTS OF THE CASE
The Plaintiff was assigned rights under a contract for a sale of
land. He became the vendor to a future purchase by Rye Grazing
Co. Rye Grazing needed more time to pay an instalment, and the
Plaintiff agreed so long as the Defendant served as a guarantor.
However, that sum was never paid by Rye Grazing or the
Defendant. The contract was later repudiated, and brought to an
end. The Plaintiff seeks to recover the amount of the instalment
from the Defendant (who served as guarantor).
ISSUES: Can the plaintiff get his right to the instalment?
HELD:
In this case, since no consideration was executed by the Plaintiff, he
does not 'get' his right to the instalment and thus the purchasers
have a right to recover it.
If there was an express statement saying that he gets to keep the
instalment even in the failure of the contract, he would be able to
retain it. But no such provision exists here.
6.3 RELIEF UNDER SECTION 40 AND
SECTION 65 OF THE CONTRACTS ACT 1950
However, it does not mean that the contract is automatically void. The
innocent party have two choices. Firstly, to either rescind or terminate
the contract. Or secondly, to either continue or affirm with the contract.
Sim Chio Huat v Wong Ted Fui [1983] CLJ Rep 363
Facts:
The respondent agree to sell some housing lots to the appellant where part of
the consideration was to be paid in the form of houses to be built by the
appellant on four of the lots. Time was made the essence of the agreement.
However, the appellant was unable to deliver in time. So, the respondent sued
the appellant for liquidated damages and general damages.
Issue:
Whether a contract that is breach can be continue or not?
Held:
The court held that time was the essence of the contract as the parties
had agreed that it be so. The respondent was entitled to unliquidated
damages for breach of contract as the appellant had failed to build a
temporary house for him as agreed upon.
However, the respondent did not choose to treat the agreement as having
been repudiated. And by allowing the delivery dates to pass and by
acquiescing in the work continuing under the agreement and indeed by
ordering extra work to be done for each of these houses, the appellant
must be held to have waived his right to rescind the agreement on
account of repudiation and also the right to treat himself as discharged
therefrom. He must be deemed to have elected the agreement as still
continuing.
ILLUSTRATIONS
A, a singer, enters into a contract with B, the manager of a theatre, to
sing at his theatre two nights in every week during the next two months,
and B engages to pay her RM100 for each nights performance. On the
sixth night A wilfully absents herself from the theatre. B is at liberty to put
an end to the contract.
Another illustration is A, a singer, enters into a contract with B, the
manager of a theatre, to sing at his theatre two nights in every week
during the next two months, and B engages to pay her at the rate of
RM100 for each night. On the sixth night A wilfully absents herself. With
the assent of B, A sings on the seventh night. B has signified his
acquiescence in the continuance of the contract, and cannot now put an
end to it, but is entitled to compensation for the damage sustained by
him through As failure to sing on the sixth night.
Section 40 of the Contracts Act 1950 (Act 136) embodies the common law
position.
The terms refusal to perform and disabled to perform are interpreted
by courts as reference to the common law concepts of repudiation and
fundamental breach. This view was mentioned by the High Court in the
case of Hwa Chea Lin & Anor v Malim Jaya (Melaka) Sdn Bhd [1996] 1 LNS
70 . Suriyadi J stated that,
In Malaysia, the terminology of fundamental breach, which is a concept of
the common law, though not in exact terms has become a creature of
statute. The relevant position is now enshrined in Section 40 of the
Contracts Act
A) REFUSAL TO PERFORM
When one party of a contract unconditionally refuses
to perform his part of the contract as promised.
Facts:
The plaintiff had agreed to supply the defendant with 3900
tons of railway chairs by instalment and at a fixed price.
The contract stated that the plaintiff will be paid after all
the railway chairs are delivered. When he had delivered
only 1787 tons of railway chairs, the defendant informed
him that they require no more. The plaintiff brought an
action to the court because the defendant did not execute
his part of the contract.
Issue:
Whether the defendant is considered to breach the contract when he
stop the order of the railway chairs?
Held:
It was held that the plaintiff could bring his action immediately and
that he would succeed as he was obviously willing to perform his part
of the contract but could not do so because of the defendant
company. If one party by his own actions makes it impossible for
himself to perform the contract, the other party may treat the
contract as renounced and commence an action at once. Hence, the
plaintiff decided to put an end to the contract with the defendant.
CHOO YIN LOO V. VISUVALINGAM (1930) 7
FMSLR 135
Facts:
The plaintiff contracted to perform certain work on the defendants land. It
was agreed that the work should be done expeditiously by having 30 workers
on the land at all times. If on any day there should be less than 30 workers,
the plaintiff should be paid $1 per day for every worker short of the stipulated
numbers. The defendant agreed to pay fortnightly 70 percent of the value of
work completed. Work commenced and regular payments were made for a
time but the defendant later ceased further payment on the allegation that
there was shortage of the stipulated number of workers which entitled him to
damages amounted to $3,845. The plaintiff who to date have employed only
a total of 3,355 workers when he ought to have employed 7,200, stopped
work on account of the non-payment. He then proceeded to sue the defendant
for damages, claiming that he had been prevented by the defendants default
from completing the contract. The defendant counter claimed for damages.
Issue:
Whether the plaintiff is liable to be sued by the defendant for breach of
contract?
Held:
It was held that since the plaintiff had agreed to carry out the work
expeditiously, his action in employing less than half the number of
workers constituted a breach which entitles the defendant to put an end
to the contract.
HWA CHEA LIN & ANOR V MALIM JAYA
(MELAKA) SDN BHD [1996] 1 LNS 70
Facts:
The plaintiffs had entered into an agreement with the defendant developer for the purchase of a
single story terrace house. The house was delivered to the plaintiffs. Unfortunately, the evidence
showed that the building was in poor conditions which required massive remedial works and
eventually had to be rebuilt.
Issue:
Whether a party not performing in a contract considered breach of contract?
Held:
The High Court later on held that this is amounted to a fundamental breach on the part of the
defendant which entitled the plaintiff to rescind the contract as the building which was delivered was
not what had been agreed upon.
B) DISABILITY TO PERFORM
Facts:
The plaintiff was a professor and giver of musical entertainments
contracted with the defendants wife where the defendant act as the agent.
Thereupon, in consideration of a certain fee to be paid by the plaintiff to
the defendant, the defendant promised the plaintiff that Arabella Davison,
the wife of the defendant, should perform at a certain musical
entertainment to be given by the plaintiff by playing the piano. However,
she was, on the day in question, unable to perform through illness. The
defendant did not procure a vocalist or piano. The contract contained no
express term as to what was to be done in case of her being too ill to
perform. The plaintiff was unable to give the entertainment, and suffered
loss in consequence.
Issue:
Whether the defendants wife is considered breaching the contract due to
disability to perform?
Held:
The Court held that even though the defendants wife had breach the
contract, it was not her fault that she had a disability to perform. Hence,
the plaintiff cannot claim for damages.
RELIEF UNDER SECTION 65 OF THE
CONTRACTS ACT 1950 (ACT 136)
Held:
The High Court held that the defendant need to pay a sum of
RM3, 575,537 to the plaintiff for the breach of contract. This is because
expenses already incurred by the plaintiff due to almost completion of
phase 1 of the development project.
BAN HONG JOO MINE LTD. V CHEN & YAP
LTD (1969) 2 MLJ 83
Facts:
The plaintiff was hired by the defendant for an earth excavation work of an
area of not less than three acres within a period of four months. The
defendants were to pay a sum of RM2, 000 as an advance as soon as the
plaintiffs conveyed an excavator to the site. The defendant made the first
progress payment of RM1, 500 and the second payment of RM1, 600 on the
first phase of the work. However, when the plaintiff next moved to the
second phase of their work but no progress payments were made in spite
of demands for them. So, the plaintiff decided to bring this issue to the
court.
Issue:
Whether the contract is considered repudiated or not?
Held:
The Federal Court ruled that the deliberate refusal of the appellant to make
fortnightly payments for work already done and their order to the
respondents to stop work left the latter with no option but to treat the
contract as having been repudiated, and to sue for payment of work that
have been done which is a total of RM1, 800.
ABB TRANSMISSION & DISTRIBUTIONS SDN BHD
V SRI ANTAN SDN BHD & ANOR [2008] 10 CLJ 1
Facts:
The first defendant had successfully bid for a TNB contract for the design,
manufacture, testing of supply and erection of switchgears, ancillaries and
civil works for TNB. The first defendant engaged the plaintiff to design and
supply the transmission equipments for the TNB's Contract ("Subcontract").
The plaintiff claimed that the first defendant repudiated the Subcontract
when it not only failed to pay the plaintiff's outstanding invoices but had in
fact diverted monies from the TNB Contract which were supposed to be
assigned to the plaintiff as payment of the plaintiff's invoices to the first
defendant. The plaintiff filed an action against the first defendant claiming,
inter alia for a declaration that the first defendant had by its conduct
repudiated the Subcontract entered into between the plaintiff and the first
defendant. The plaintiff also claimed damages and the retention sum
Held:
The High Court held that the first defendant had breached the Subcontract
by diverting and pocketing the assigned payments from TNB. This act of
diversion alone entitled the plaintiff to treat that the first defendant as
having repudiated the Subcontract. The first defendant's repudiation of the
Subcontract presented the plaintiff with only one option, either, to affirm
the Subcontract or to accept the repudiation. This is an option recognized
by section 40 of the Contracts Act 1950. The plaintiff had chosen the latter
and accepted the first defendant's repudiation. If the contract in question
has been repudiated, both parties are discharge from further performance
of the contract and the retention money held which is trust money has to
be paid back to its rightful owner. In this regard, that would be the plaintiff.
8.4 EFFECT OF BREACH
UNDER ENGLISH LAW
There is no much differences between English law and Contract Act 1950 for the
effect on breach of contract
Lord Ackner, Fercometal Sarl v MSC Mediterranean Shipping Co SA (The
Simona) [1988] 2 Lloyds Rep 199
The English Law does not require a party to perform empty formal gesture in
circumstances where the orther party to the contract has manifested an
unequivocal intention not to perform the contract in any event
Under the common law, there are two situations which give the innocent party
the right to be discharged form the contract
a repudiation/renunciation(abandonment), and
a fundamental breach.
Generally in English Law
There is no restriction impose on parties whom walk away from
agreement when there is issue arises.
Example, speculation of volatile market.
Contracting sides is free to decide whether to upheld their
obligation to contract if another side decide to discontinue
performance of contract.
Example
When one party announce that he is not going to perform, another
party has to elect whether to accept such behavior as repudiation
or not. Until such election has been made there is no breach.
REPUDIATION
Held
Claimant claim is up held as the claimant is said to be suffered loss as the
defendant act on breach of contract.