Installing New Workshop for Soil Testing
Dr. HENG Sokchhay
Group-3
HAK Lyhour, HEANG Borin, HEAP Sothea, HENG Kimsan, HENG Rachana
Hydraulic Structure 2
Group-3

Content
1. Introduction
2. Methodology
3. Result and Discussion
4. Conclusion
Hydraulic Structure 3
Group-3

1. Introduction
Problem
Students have to do experiment outside the laboratory
Samples can not be stored properly
We do not have enough space to keep big amount of samples
Testing under inappropriate condition (temperature.)
Hydraulic Structure 4
Group-3

1. Introduction
Objective
Students will work conveniently
We can get more accurate result
Keeping our laboratory clean and tidy
Hydraulic Structure 5
Group-3

1. Introduction

Our new workshop is located


behind the Building D (Existing
laboratory), in the Institute of
Technology of Cambodia. Russian Conf.
Blvd
Latitude : 11O3413.31 Building
N D
Longtitude:104O5348.29E

Figure.1 Project Location


Hydraulic Structure 6
Group-3

Figure.2 Left View Figure.3 Right View


Hydraulic Structure 7
Group-3

2. Methodology
Construction Criteria:
Slab (thickness 150mm, area 45m2)
Steel selection (deform bar)
Strength of Concrete
Roof
Other materials
Hydraulic Structure 8
Group-3

Fibro Cement Steel

Mortar Brick
Hydraulic Structure 9
Group-3

3. Bill of Quantity (BOQ)

Cost of Construction include the price of :


Material ( Mortar, Steel, Fibro cement)
Labor (Foreman and Workman)
Hydraulic Structure 10
Group-3
SUMMARY Door
Quantity Unit price Price
Description V steel 30mm*30mm*2.3mm 2 bar $ 14.50 $ 29.00
Concrete for ground floor
Rolled steel solid 16 2 bar $ 12.50 $ 25.00
Concrete 9m 3
$ 80.00 $ 720.00
Square steel 30mm*30mm*2mm 2 bar $ 12.00 $ 24.00
Deform bar (12mm) 20 pieces $ 6.00 $ 120.00
Zinc sheet 2.25m2 $ 6.50 $ 13.00
Brick wall

Hallow clay brick 3300 pieces $ 0.05 $ 178.38


Roller 4 pieces $ 2.50 $ 10.00

Cement-platering 15 bags $ 5.16 $ 73.71 Roof

Fine sand 3 m3 $ 10.00 $ 30.00 Rectangle steel 40mm*80mm*2mm 34 bar $ 12.00 $ 408.00
Skin coat plaster 5 bags $ 10.00 $ 50.00 Rectangle steel 25mm*25mm*2mm 22 bar $ 6.00 $ 132.00
Piant wall 40 l $ 110.00 $ 220.00
Fibro cement 65m2 $ 5.50 $ 357.50
Steel wall
Labor
Steel plate 20mm*5mm 6 bar $ 6.00 $ 36.00
Foremen 1 $ 294.84
Rolled steel solid 16 30 bar $ 12.50 $ 375.00
Workmen 5 $ 1,031.94
Column

Steel tube 100*2.3mm 2 bar $ 15.00 $ 30.00 Total Price $ 4,158.37


Hydraulic Structure 11
Group-3
Cost for each element:
Slab : $ 840.00
Wall : $ 963.00
Column : $ 30.00
Door : $ 101.00
Roof : $ 898.00
Labor : $1,327.00

Total Cost: Approximated $4,200.00


Hydraulic Structure 12
Group-3

4. Conclusion
This new workshop will benefit students and teachers having more free area
to do experiment and store sample and equipment properly. We will only spend
around 4200$, to build this new workshop. So, it should be build to help students
perform their experiment and learn more from the accurate result that they get.
Thanks for your attention!