A-Library, oraccounting library, is a
storehouse of all accounting books,
reviewers and other materials needed by
the students while CPAs in Transit are
those students whom considering
themselves as Certified Public
Accountants but still on their journey as
BSA students.
Implementing College/Unit:
College of Business and Management
(CBM)

Stand Classification: Construction

Project Site: Partido State University

Project Duration: January-August 2018

Total Project Cost: 2,053,395


A-Library for CPAs in Transit will give
every BSA student the opportunity to
learn, to enjoy reading, to create new
knowledge and understanding about
their course.
This library supports the BSA's objective
of equipping the students with thorough
understanding of the concepts and
application of theories.
What is A-Library for CPAs in Transit?

A-Library for CPAs in Transit is a two-storey


building where books, reviewers, notes, test banks
and other related accounting subject will be kept
together.
For whom the library is intended?

BSA students
Faculties
Others students with accounting subject
1. To provide BSA students of the best service
a library can offer.
2. To provide accounting materials that will
stimulate students acquisition of factual
knowledge.
3. To enhance the studying habit of the
students.
4. To develop personality and capabilities of
the students to cope up in the field of
accountancy.
A-Libraryfor CPAs in Transit will aid the
college departments work of literacy and
education.
1. Gathering Information
2. Fund Sourcing
3. Acquisition of Materials for the
Construction
4. Construction of the A- Library
5. Acquisition of Accounting-Related
Educational Materials
6. Ribbon Cutting
Activities Months
January February March April May June July August

1. Gathering of X

Needed Information
2. Submission/ X

Approval of Proposal
3. Acquisition of X

Construction Materials
4. Construction of the X X X X

Two-storey Building
5.Setting up of X

furnitures including
the bookshelves,
tables and chairs
6. Acquisition of X

Accounting Books and


Review Materials
7. Ribbon- Cutting X
Estimated Costs

1. Construction Materials 599,895

2. Furnitures and Fixtures 439,000

3. Labor 715,000

4. Accounting Reviewers 94,500

5. Accounting Books 175,000

6. Other Materials 30,000

2,053,395
Other Review
Accounting Materials, 30,000,
1%
Accounting Books, 175,000,
Reviewers, 9%
94,500, 5% Construction
Materials,
599,895, 29%

Furniture and
Labor, 715,000,
Fixtures , 439,000,
35%
21%

ESTIMATED BUDGET