INDUSTRIAL TRAINING AT PROPOSED

CANCER HOSPITAL SITE - KANDY

DEPARTMENT OF CIVIL & ENVIRONMENTAL ENGINEERING


EG/2013/2207
HULANGAMUWA R.R.V.G.B.C.R.B
16/05/2016
Introduction

Basic introduction about CECB


Basic idea about the construction sites involved
Non-engineering issues encountered in construction sites
Engineering issues encountered in construction sites and
remedies applied.
About CECB

Established in 1973
Play a vital in larger development projects in Sri Lanka and overseas

About CESL
Central Engineering Services (PVT) LTD
Fully owned subsidiary of CECB established under companies act in
November 2009
Construction sites involved
Sports Complex - Digana Hemodialysis Unit Cancer hospital site

1 Finishing work 1 Slab formwork 1 Structural parts


2 Site management 2 Slab reinforcing 2 Concreting walls ,
3 Studying of BOQ 3 Concreting of slabs , columns ,
columns and slabs stair cases etc.
4 Preparing sub-
contractor 4 Formwork for stair 3 Implementing
payments cases QMS
Proposed provincial level sports
complex- Digana
Contractor : CECB

Employer/Client : Ministry of Sports

Employers representative : Provincial sports


development committee.

Engineer/consultant : Department of Building.

Start of Construction : 2013/11/08

Cost of construction : Rs.6,074,819.68


Activities involved at site

Preparing sub contractor payments


Studied about drawings Structural, Architectural, Plumbing, Electrical
Prepared material requirement lists for roofing the main pavilion
Conduct sample setting out for a building
Studied about construction management and labor handling
Studied about BOQ
Learn about basic construction materials and equipment used in site
Leveling for tiers and plumbing
Brick work Smooth and rough plastering

Power trowelling Lintel and tie beam construction


plumbing Floor rendering

Block work Floor concreting


Main issues encountered in the site

Lack of efficiency of unskilled labors


Architectural issues regarding the changing
of roof drawing
Poor material handling
Construction of four storied Hemodialysis
unit at base hospital - Dambulla

Construction work in slab


Estimated concrete (grade 25) 65 cubic meters
Actual concrete usage - 58 cubic meters
Engineering Problem -Verifying the actual
concrete amount delivered to the site?
Slab form work - Steps
Proposed Cancer hospital - Kandy

LINAC therapy Most advanced treatment for brain tumor cancers


Special grade 30 concrete with admixtures
Conplast SP 430
Conplast RP 264

W/C ratio of 0.45


Concrete walls, Buffer Zone , Special formwork designs
Engineering issue - Lack of 3D visualization about the construction site
Type 1 Type 2
Engineering issues

Lack of 3D visualization about the construction work. Introducing


BIM(Building Information Modeling)
Revise of drawings
Lack of covering for RCC walls
THANK YOU