(JIGCC) Project
Pre-Commissioning Presentation
for
Saudi ARAMCO Management(SA)
Agenda
- The purpose of this document is to describe the specific requirements, principles, and responsibilities
for the preparation, execution, verification, and documentation of PRE-COMMISSIONING and
Turnover phases, leading to Mechanical Completion.
- This plan outlines how CONTRACTOR intend to perform the PRE-COMMISSIONING and Turnover
Activities in order to get a safe, quality, timely and control of the FACILITY based on defined
PRECOMMISSIONING System.
Mechanical Completion
Mechanical Completion will be achieved when all defined Systems & sub-systems have been
turnover to COMPANY, the Turnover Notice issued and available for commissioning.
Partial Mechanical Completion is achieved when a separable System/Sub-system of a facility is
available for commissioning as defined by its portion of the approved scope.
Final Mechanical Completion is achieved when the total facility is available for commissioning.
NOTES
COMPANY will be invited for final review at about 90% completion of the Pre-commissioning stage of
the Subsystem to provide initial comments prior to formal review.
Four weeks prior to the schedule MC(Part) date , CONTRACTOR will notify to the COMPANY that the
System, combination of Systems, or portions thereof are completed with the exception to the Punch
list items and ready for MC inspection.
Completion Reporting
Completion Reporting
The dossier will contain original signed records of the agreed tests, inspections
and checklists which are required to be presented in support of the
application for Turnover.
Punch Lists
Punch List
While the Pre-Commissioning activities have been performed, all the
discrepancies will be recorded in the Punch list. CONTRACTOR will maintain
this punch list of deficient work for use in managing work and that of his
subcontractors. This punch list will be independent of the turnover punch list
although could be requested and provided as reference by COMPANY.
From the construction to the commissioning activities, two punch list priority
levels should be considered:
YES Must be completed before Mechanical Completion Acceptance -
Ready for Commissioning.
NO Must be completed before facility ACCEPTANCE or date specified by
COMPANY.
References
References
Contracts Contracts No. 6600033569(OOK) & 6600033568 (IK)
Drum Screening
Trash Screening
Vertical Centrifugal
Pumps
Blower Various skid
based pumps in EC
Building Submersible
Pumps
Diesel Engine
Over Head Crane
Tanks
Main Piping System
Pressure Gauges
Flow Meters
Temperature Gauges
Pressure Relief Valves
Pneumatic Actuated
Valves
Electrical Actuated
Valves
Instrument Panels
Fire & Gas Detectors
Loop Checking
Telecommunication system