Escolar Documentos
Profissional Documentos
Cultura Documentos
2
CONTENT
Introduction
Site
Key Plan
Proposal
Conclusion
3
INTRODUCTION
Consultancy Services :
Scope : Lay pipeline to replace
existing ageing A.C. pipes
Length : approx. 18km
Re-estimated Length: approx. 23km
Local Authorities : MBPJ, MPSJ,
MBSA, DBKL
Dateline : 31/10/2007 (Draft TTD)
15/11/2007 (Final TTD)
4
THE SITE
5
THE SITE
No. Areas Pipe Size SYABAS JPT
(mm) Estimated Estimated
Length (km) Length (km)
8
THE SITE– Cont’d
No. Areas Pipe Size SYABAS JPT
(mm) Estimated Estimated
Length (km) Length (km)
10
PROPOSAL
Brief proposal for each site area are
detailed out based on the following:-
•Location Plan and Photos (for better
visualization of the areas)
•Nature of Location (Urban; sub-urban;
residential; commercial/business; traffic
(high/low)
•Estimated Length (in km)
11
PROPOSAL
•Pipe Material (D.I; MS; HDPE)
•Method of Pipe Laying (Open
Trench/normal excavation; Horizontal
Directional Drilling; Pipe Jacking; Pipe
Crossing; Pipe Bursting; etc.)
•Working Hours (Day Time; Night Work)
•Proposed Pipe Alignment (Road
shoulder; Under Premix, Foot walk,etc.)
12
Jln Gajah 2, Kg. Kubu Gajah
13
Jln Gajah 2, Kg. Kubu Gajah
Location : Sub-urban,
residential, low traffic
Estimated Length : 0.80 km
Pipe Material : D I Pipe
Method of Pipe Laying : Open Trench
Working Hours : Day Time
Position of Pipe Trench : Under Road
Pavement & Road Shoulder
14
Lorong 7, Kg. Merbau Sempak
15
Lorong 7, Kg. Merbau Sempak
Location : Sub-urban,
residential, low traffic
Estimated Length : 0.80 km
Pipe Material : D I Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement & Road Shoulder
16
Lorong 1, Kg. Merbau Sempak
17
Lorong 1, Kg. Merbau Sempak
Location : Sub-urban,
residential, low traffic
Estimated Length : 0.40 km
Pipe Material : D I Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement
18
Jln Tempayan Emas 2, Kg. Paya Jaras
19
Jln Tempayan Emas 2, Kg. Paya Jaras
Location : Sub-urban,
residential, low traffic
Estimated Length : 1.60 km
Pipe Material : D I Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement & Road Shoulder
20
Jln Masjid, Kg. Sg. Kayu Ara, PJ
21
Jln Masjid, Kg. Sg. Kayu Ara, PJ
Location : Urban,
residential, medium traffic
Estimated Length : 0.30 km
Pipe Material : D I Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement
22
Location Plan- JlnCempaka, Kg.Sg. Kayu Ara, PJ
23
Jln Cempaka, Kg. Sg. Kayu Ara, PJ
24
Jln Cempaka, Kg. Sg. Kayu Ara, PJ
Location : Urban,
residential, medium traffic
Estimated Length : 1.30 km
Pipe Material : D I Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement
25
Jln Seroja, Kg. Sg. Kayu Ara, PJ
26
Jln Seroja, Kg. Sg. Kayu Ara, PJ
28
Jln SS 16/7, Seksyen 16, PJ
Location : Urban, residential,
low traffic
Estimated Length : 0.50 km
Pipe Material : DI Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road Pavement
No. of house connection: 15
29
Jln SS 16/10C, Seksyen 16, PJ
30
Jln SS 16/10C, Seksyen 16, PJ
31
Jln SS 14/15 & Jln SS 14/15A, Seksyen 14,
PJ
32
Jln SS 14/15, Seksyen 14, PJ
Location : Urban,
residential, medium traffic
Estimated Length : 0.20 km
Pipe Material : DI , MS Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement
No of house connection : 14 33
Jln SS 14/15A, Seksyen 14, PJ
Location : Urban,
residential, low traffic
Estimated Length : 0.10 km
Pipe Material : D I Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement
No of house connection : 10 34
Jln SS 14/46, Seksyen 14, PJ
35
Jln SS 14/46, Seksyen 14, PJ
Location : Urban,
residential, medium traffic
Estimated Length : 0.70 km
Pipe Material : DI Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement
36
Jln SS 14/29, Seksyen 14, PJ
37
Jln SS 14/29, Seksyen 14, PJ
Location : Urban,
residential/commercial, heavy traffic
Estimated Length : 1.70 km
Pipe Material : MS & DI Pipe
Method of Pipe Laying : Open Trench
Working Hours : Day/Night
Position of Pipe Trench : Under Road
Pavement
38
Jln SS 14/20, Seksyen 14, PJ
39
Jln SS 14/20, Seksyen 14, PJ
Location : Urban, commercial,
high traffic
Estimated Length : 0.50 km
Pipe Material : DI Pipe
Method of Pipe Laying : Open Trench
Working Hours : Night Work
Position of Pipe Trench : Under Road Pavement
No of house connection : 35 & 1 of 150mm dia to
supply to Mosque)
40
Jln SS 14/54, Seksyen 14, PJ
41
Jln SS 14/54, Seksyen 14, PJ
43
Jln SS 13/3, Seksyen 13, PJ
44
Jln SS 13/3, Seksyen 13, PJ
46
Jln SS 13/4, Seksyen 13, PJ
Location : Urban, industrial,
congested with traffic
Estimated Length : 0.80 km
Pipe Material : DI Pipe
Method of Pipe Laying : Open Trench
Working Hours : Night Work
Position of Pipe Trench : Under Road
Pavement
47
Jln SS 13/6, Seksyen 13, PJ
48
Jln SS 13/6, Seksyen 13, PJ
50
Jln SS 9A/12, SS 9A, PJ
Location : Urban,
residential, congested traffic
Estimated Length : 0.60 km
Pipe Material : DI Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement
52
Jln PJS 6/1 & Jln PJS 6/1A, PJS 6, PJ
53
Jln PJS 6/1, PJS 6, PJ
56
Jln SS15/4B, Subang Jaya
Location : Urban,
commercial, congested high traffic
Estimated Length : 0.90 km
Pipe Material : DI , MS Pipe
Method of Pipe Laying : Open Trench
Working Hours : Night Work
Position of Pipe Trench : Under Road
Pavement
57
Jln Subang 8, Subang Penaga
Industrial
Park
58
Jln Subang 8, Subang Penaga Industrial
Park
Location : Urban,
industrial, medium traffic
Estimated Length : 0.70 km
Pipe Material : DI Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement 59
Jln Jurutera, Kg. Seri Aman
60
Jln Jurutera, Kg. Seri Aman
Location : Sub-urban, residential,
medium traffic
Estimated Length : 5.0 km
Pipe Material : DI Pipe
Method of Pipe Laying : Dig Open Trench
Time of Laying Pipe : Normal Working Hours
Position of Pipe Trench : Under Road Pavement
& Road Shoulder
61
Jln Kubur, Pantai Dalam, KL
62
Jln Kubur, Pantai Dalam, KL
Location : Sub-urban,
squatter area, medium traffic
Estimated Length : 0.30 km
Pipe Material : DI Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement
63
Jln 14/108, 16/108, 17/108, 23/108, Tmn.
Salak Jaya, KL
64
Jln 14/108, 16/108, 17/108, 23/108, Tmn.
Salak Jaya, KL
Location : Urban, residential,
low traffic
Estimated Length : 0.30 km (Jln 14/108)
0.20 km (Jln 16/108)
0.20 km (Jln 17/108)
0.15 km (Jln 23/108)
Pipe Material : DI Pipe
Method of Pipe Laying : Dig Open Trench
Time of Laying Pipe : Normal Working Hours
Position of Pipe Trench : Under Road Pavement
65
Jln 5/153A, 6/153A, 7/153A, Tmn.
Angkasa, KL
66
Jln 5/153A, 6/153A, 7/153A, Tmn. Angkasa,
KL
Location : Urban, residential,
low traffic
Estimated Length : 0.10 km (Jln 5/153A)
0.15 km (Jln 6/153A)
0.20 km (Jln 7/153A)
Pipe Material : DI Pipe
Method of Pipe Laying : Dig Open Trench
Time of Laying Pipe : Normal Working Hours
Position of Pipe Trench : Under Road Pavement
67
Jln 2/115A, Tmn. Pagar Ruyung, KL
68
Jln 2/115A, Tmn. Pagar Ruyung, KL
70
Jln BS 5/3, Tmn. Bkt. Serdang
Location : Urban, residential,
low traffic
Estimated Length : 1.20 km
Pipe Material : DI, MS Pipe
Method of Pipe Laying : Open Trench
Working Hours : Normal
Position of Pipe Trench : Under Road
Pavement & Road Shoulder
No of house connection : 116 71
CONCLUSION
Due to the congested of utility services
(TNB, TMB, Fibre Optic, Water pipe) under
the road pavement and limited available
width of road shoulder, new pipe
alignment will be located under the road
pavement.
Requires a lot of road restoration.
Method of pipe laying – Open trenching
Pipe bursting not recommended due to
consumer connections
72
CONCLUSION
Parallel Mains in Seksyen 14/29, SS15/4B,
Bkt Serdang
Proposed night work for pipe work at Sek
13/3, 13/4, 13/6, Sek 14/20, and Jln SS
15/4B, Subang Jaya
Hydrant and valves will be proposed where
found necessary
Transfer of Connections at Jln Kubur, Pantai
Dalam
73
CONCLUSION –Cont.
74
CONCLUSION–Cont.
75
76