Contingencies (0.5 to 3% of
EDC)
Miscellaneous (0.5 to 1 % of
EDC)
Profit 8% (EDC > 5M )
10% (EDC < 5M)
VAT 5% of EDC, OCM & Profit
Contains the instructions and provisions
corresponding to the procurement at hand
Contents
a. Approved Budget for the Contract;
b. Invitation to Bid;
c. Eligibility Requirements;
d. Instruction to Bidders, including scope
of bid, criteria for eligibility, bid
evaluation methodology and post-
qualification,
e. date, time and place of the pre-bid
conference (where applicable),
submission of bids and opening of bids;
f. Scope of work, where applicable;
g. Plans/Drawings and Technical
Specifications;
h. Form of Bid, Price Form, and BOQ
i. Completion Schedule;
j. Form, Amount, and Validity Period of Bid
Security;
k. Form, Amount, and Validity of
Performance Security and Warranty; and
l. Form of Contract and General and
Special Conditions of Contract.
Standard Procedural Steps
Details to be discussed Meeting attended by
ABC and its availability - BAC
Method of procurement and the - TWG
related milestones - End-User or
Completeness and readiness of Implementing Unit
Bidding documents - Secretariat
Scope of Works
Plans and Technical
specifications
Schedules and Timeframes
Emphasize the importance of
confidentiality
Is Detailed Engineering Complete?
Technical
competence & availability of key
technical personnel
availability of major equipment
material testing equipment
performance qualification
Performance Qualification
negative slippage >
15% in one project
10% in 2 or more projects
failure to commence repair works in ongoing works
failure to commence work for projects with pending
certificate of acceptance
substandard work
Note:
BAC shall recommend the award of contract at its
submitted bid price or its calculated bid price,
whichever is lower.
Contract shall be awarded to the
bidder with the Lowest Calculated
and Responsive Bid (LCRB) at its
submitted price or total calculated
bid price, whichever is lower
Start of Completion of
Acceptance
Contract Contract
CARI
PAYMENTS
Advance
Progress
Final
Retention
Warranty Security
1 year validity
Warranty Period
2 to 15 years
Bidding Stage
Bid Security
1 year Defects
Liability Period
Start of Completion of
Acceptance
Contract Contract
CARI
PAYMENTS
Advance
Progress Warranty Security
1 year validity
Final
Retention
Warranty Period
2 to 15 years
Permanent Structures (15 yrs)
Buildings Types 4 & 5, bridges, flyovers, ports, dams,
Semi-Permanent (5 yrs)
Buildings Types 1, 2, 3, concrete roads, concrete river
control, drainage
References:
R.A. 9184 & its IRR
GPPB References
DPWH D.O.