Department of Technical Education

Andhra Pradesh
Name : J. Ravi Kumar
Designation : Lecturer
Branch : Civil Engg.
Institute : SRRS GPT, Sircilla
Year/Semester : IV semester
Subject : Quantity Surveying
Subject Code : C404
Topic : Earth Work Calculations
Duration : 50 Minutes
Sub Topic : Problems on Earth Work volume for
roads, canals and earthen bunds
Teaching Aids : PPT
Revised by : 9C404.64
S. Prabhakara Rao 1
Objectives :

On completion of this period ,you would be able to :

• Calculate earthwork volume using

a) Trapezoidal formula

b) Prismoidal formula

9C404.64 2
Recap:

In the previous period, we have learnt about:

• Calculation of volume of earth work in excavation

and embankment.

9C404.64 3
Problem: 1
Estimate the quantity of earthwork for a portion of a
road from the following data
Formation width of road is 12m. Side slopes1 ½ : 1
(H:V) in banking. Assume ground at level across.
The distance in between station is 50m.
Station 0 1 2 3 4 5 6 7

R.L of 102.35 101.80 102.05 102.50 103.15 103.45 103.0 103.55


ground

R.L of formation is 104 meter


9C404.64 4
Step 1 : Calculation of cross selected areas

A0 = bd1 + nd12
= 12 (104 – 102.35) + 1 ½ (104-102.35)2
= 12 x 1.65 +1.5 x 1.652 = 19.8 + 4.084 = 23.884
A1 = 12 (104 -101.80) + 1 ½ (104 – 101.80)2
= 12 x 2.2 + 1.5 x 2.22 = 26.4 + 7.26 = 33.66
A2 = 12 (104 – 102.05) + 1 ½ (104 – 102.05)2
= 12 x 1.95 + 1.5 x 1.952 = 23.4 + 5.704 = 29.104
A3 = 12 (104 -102.50) + 1 ½ (104 – 102.50)2
= 12 x 1.5 + 1.5 x 1.52 = 18 + 3.375 = 21.375
9C404.64 5
A4 = 12 (104 – 103.15) + 1 ½ (104-103.15)2
= 12 x 0.85 +1.5 x 0.852 = 10.2 + 1.084 = 11.284
A5 = 12 (104 -103.45) + 1 ½ (104 – 103.45)2
= 12 x 0.55 + 1.5 x 0.552 = 6.6 + 0.454 = 7.054
A6 = 12 (104 – 103.00) + 1 ½ (104 – 103.00)2
= 12 + 1.5 = 13.5
A7 = 12 (104 -103.85) + 1 ½ (104 – 103.85)2
= 12 x 0.15 + 1.5 x 0.152 = 1.8 + 0.034 = 1.834

9C404.64 6
Using Trapezoidal Rule :
Total Volume of earthwork

V = L/2 [ (A0 + A7) + 2(A1 + A2 + A3 + A4 + A5 + A6 ]

= 50/2 [ (23.884 + 1.834)+ 2(33.66 + 29.104+ 21.375


+ 11.284 + 7.054 + 13.5) ]

= 50/2 [ 23.884 + 1.834 + 231.954]

= 6441.8 Cu. m.

9C404.64 7
Using Prismoidal Rule :
Total Volume of earthwork

V = L/3 [ (A0 + A7) + 4(A1 + A3 + A5) + 2(A2 + A4) ]

= 50/3 [ (23.884 + 1.834) + 4(33.66 + 21.375 + 7.054)


+ 2(29.104 + 11.284) ]

= 50/3 [ 25.718 + 4(62.089) + 2(40.388) ]

= 50/3 [ 25.718 + 248.356 + 80.776 ]

= 5916.167 Cu. m.

9C404.64 8
Problem : 2
Calculate the quantity of each work for 200m length for a
portion of a road in an uniform ground the heights of banks
at the two ends being 1.00m and 1.60m. The formation
width is 1.0 m and side slopes 2:1 (H:V)

Assume that there is no transverse slope use

(i) Mid – ordinate method and

(ii) Mean – sectional area method

9C404.64 9
Solution:
(i) Mid – ordinate method
Given B=10m d1 = 1.00m S=2 L = 200m
d2 = 1.6m

Mean depth, dm = (1.0+1.6)/2 = 1.30m

Quantity of earthwork, V = (Bdm + Sdm2) x L


= (10 x 1.3 + 2 x 1.32) x 200
= (13 + 338) x 200
= 16.38 x 200
V = 3276 Cu. m.
9C404.64 10
(II) Mean – Sectional area method:

A1 = Cross sectional area at one end = Bd1 + Sd12


= 10 x 1 + 2 x 12
= 10 + 2
= 12 sq. m
A2 = Cross sectional area at other end = Bd2 + Sd22
= 10 x 1.6 + 2 x 1.62
= 16 + 2 x 2.56
= 16 + 5.12
= 21.12 sq. m
9C404.64 11
A1 + A2 12 + 21.12
Mean sectional area = =
2 2
33.12
= = 16.56 sq. m
2
A1 + A2
Quantity of earthwork V = ( )
2
= 16.56 x 200
= 33.12 Cu. m.

9C404.64 12
Summary

In the previous period, we have learnt about :

1) Mid – ordinate method

2) Mean sectional area method

3) Prismoidal rule

4) Trapezoidal rule

9C404.64 13
Quiz
1. Earth work calculation is done by using the following
method

a) Rectangle method

b) Triangle method

c) Diagonal method

d) Mid – ordinate method

9C404.64 14
2. In the following method for calculation of earthwork
average ordinate or mean ordinate is taken.

a) Mid rectangle method

b) Mid area method

c) Mid ordinate method

d) Mid quadrilateral method

9C404.64 15
Frequently Asked Questions:

1. Calculate the quantity of each work for 100m length for

a portion of a road in an uniform ground the height of


banks at the two ends being 1.5m and 2.4m. The formation
width is 12m and side slopes 1 ½ :1 (H:V)

Assume that there is no transverse slope use

(i) Mid – ordinate method and

(ii) Mean – sectional area method

9C404.64 16
2. Estimate the quantity of earthwork for a portion of a road
from the following data.
Formation width of road is 9m. Side slopes 2 : 1 (H:V) in
banking. Assume ground at level across.
The distance in between station is 100m.

Station 0 1 2 3 4 5 6
R.L of ground 102.1 101.6 102.15 103.4 103.2 103.6 104.3

Calculate volume of earthwork by using


a) Prismoidal rule
b) Trapezoidal rule
9C404.64 17