Escolar Documentos
Profissional Documentos
Cultura Documentos
UDAIPUR
Approved by AICTIE, New Delhi & Affiliated by BTER, Jodhpur (Raj)
PRESENTATION OF TRAINING
AT B.L. MANTRI & ASSOCIATES PVT. LTD
Presented by:
JAYESH KOTHARI
Training Taken At:
Udaipur
FUNCTION OF FOUNDATION –
Foundation Mat:
2800X2200
10#mm@100c/c
Both Ways
Construction of Isolated footing:
1. Excavation
2. Damping the Surface
3. PCC 1:4:8
4. Footing mat is
5. Column is erected
6. Concreting with M20 grade
concrete (1:1.5:3)
D.P.C.
A layer of waterproof material in the wall of a building near the ground, to prevent
rising damp.
A course of some impermeable material laid in the foundation walls of building near
the ground to prevent dampness from rising into the building.
Junction of Beam
SLAB
Slab is a structural element forming floors and roofs of buildings for supporting
load on its surface.
4-25mm# : 4 steel bars of 25mm diameter in top layer of the bean throughout the length of
Top Thru the beam. Stirrups
2-16mm# : 2 Steel bars of 16mm diameter in middle layer of the beam throughout the length. 10mm# @125c/c
Mid Layer
3-25mm# : 3 Steel bar of 25mm diameter in the centre of the beam with 0.15L distance
Bottom Extra from both the sides from centre of support
4-25mm# : 4 steel bars of 25mm diameter in bottom layer of the beam throughout
Bottom Thru out the length of beam.
MIXING
TRANSPORTATION
PLACING
COMPACTION
FINISHING
BATCHING:-
•Batching is measuring and proportioning of ingredients (Cement , Sand, Aggregate,
Water) of concrete.
•Either by volume or by Weight and introducing them into the mixture
MIXING-
•Mixing is preparing a homogeneous mixture of
all the ingredients.
•Ingredients are charged Step-by-Step.
•At our Site – Batch-type Tilting-type Mixer was
deployed
TRANSPORTATION –
•Concrete is transported from place of mixing to
the formwork where it has to be placed
•Transported without Segregation.
IMG-Cable and Hoist arrangement IMG-Chute
At our Site: For vertical transportation Cable and Hoist arrangement was used. On floor
transportation Pan is used.
When concrete was prepared at central plant, It is transported in trimmers of capacity
PLACEMENT:
•Before placing concrete Reinforcement is checked.
•Shuttering is checked.
•Loose props are checked and tightened.
.
COMPACTION:
•The removal of entrapped air from fresh
concrete.
•Increases the density of placed concrete.
•Increases the permeability.
IMG-Compaction by Vibration
FINISHING:
Finishing is important for plane and smooth
surface. After placement and compaction of
concrete the surface of it is leveled by using a
Rafter or Float.
READY MIX CONCRETE
Advantages:
•Quality control of batching.
•Use on congested sites.
•Prevention segregation and maintaining workability.
•Economical when Concreting of large area.
Transportation
Trimmer Emptied in a Pump Pump Pumps Concrete in Pipelines
STONE MASONRY:
• Random Rubble
•For 4” Walls
•For Partition Walls
•Non-load bearing Wall
•Mortar Used is (1:3) or
(1:4)
Stretcher bond
Flemish Bond
SCAFFOLDING
•Scaffolding is a Temporary Structure
construction works
Width 5’3”
Tread 11”
No. of Steps 25
Height 12’6”
Riser 6”
Longitudinal Reinforcement:
10mm# @5” c/c
Lateral Reinforcement:
8mm# @8” c/c
Expansion Joint