Você está na página 1de 38

PT.

Surya Energi Indotama


About Us

• PT. SURYA ENERGI INDOTAMA (SEI) a subsidiary of PT. LEN


Industri (Persero), a state own company who has a reputation for
developing Solar Power Plant in Indonesia since 1997

• SEI focuses its business activities as Engineering, Procurement &


Construction (EPC) company in renewable energy such as solar,
wind, micro-hydro and geothermal.

• Endorsed by more than 50 experties, SEI has dealt with


hundreds of renewable energy project from both goverment and
private agencies which spread all over Indonesia, including the
outer, the farthest and isolated islands.
About Us

Vision and Mission

VISION
“Becoming the leader of Engineering, Procurement and
Construction in the field of Renewable Energy tha Provides the
best ultilization solution for the users as their needs”.

MISSION
“Improving the welfare of Stake Holder through the fulfillment of
competitive, innovative and efficient Renewable Energy needs
and utilization can be done wherever, whenever and by anyone”.
About Us
Our Business

• System Design
System Solution • Engineering
• System Integration

• Instalasi
Services • Testing & Commisioning
• Training

• Centralized Solar Power Plant (Off Grid)


• Hybrid Power Plant
• On Grid Power Plant
Sales & • Solar Tree
Marketing • Rooftop Power Plant
• Solar Street Lighting
• Another Renewable Energy products
About Us

Human Resources

BOD
3%
Finance
23%
Skilled
Technician
46%

Sales
Marketing
8%

Certified Engineers
Certified
Engineers Drafter Electrical
20% 3% Engineer
28%
Civil Engineer
Skilled 2%
Technician
67%

Employee : 109 employee ( Aug 2018) + sufficient number of outsource workers


About Us

Company Certification

ISO 9001 : 2015 OHSAS 18001 : 2007 ISO 14001 : 2004


About Us
Personal Certification

SKKTK PLTS

TUV PV Designer

SKK, SKA Sipil, SKA Teknik Tenaga Listrik & Manajemen


Proyek HSE
Our Product

Centralized Solar Power Plant (Off Grid)

Hybrid Power Plant

On Grid Power Plant

Solar Tree

Rooftop Power Plant

Solar Street Lighting

Another Renewable Energy products


Our Experience

Installed system : 20 Mwp ; Install Energy Production : 26.280 MWh/year ;


Carbon Reduction : 17.517 tonnes/year ; Tree Saved : 86.348 trees/year
Our Experience

Off-Grid Solar PV Distributed System

Pemilik Proyek : MCA Indonesia


Lokasi Pemasangan : MCA Sumbar
Kapasitas : 480 KWp
Jumlah Rumah : 909 Rumah
Tahun Anggaran : 2017
Our Experience

On-Grid Power Plant 1 MWp

Pemilik Proyek : PT. Pertamina Power Indonesia


Lokasi Pemasangan : PT Badak NGL, Bontang, Kalimantan Timur
Kapasitas : 1 MWp
Tahun Anggaran : 2017
Our Experience

On-Grid Power Plant

Pemilik Proyek : ESDM


Lokasi Pemasangan : Bandar Udara Kalimarau, Berau
Kapasitas : 315 kWp
Tahun Anggaran : 2016
Our Experience

On-Grid Power Plant 2 MWp

Pemilik Proyek : ESDM


Lokasi Pemasangan : PLTS Manokwari
Kapasitas : 2 MWp
Tahun Anggaran : 2016
Our Experience

Project Owner : PT Len Industri (Persero)


Location : NTT Kupang
Capacity : 5 MWp
Year : 2015

Grid Connected PV System 5 MWp KUPANG


Our Experience

Project Owner : ESDM


Location : Bali
Capacity : 1 MWp
Year : 2012

Grid Connected PV System 2 X 1 MWP BALI


Our Experience

Solar Street Light

Project Owner : Badan Geolog


Location : Badan Geologi Bandung
Capacity : 80 Watt
Year : 2013
Our Experience

Solar Tree System Location : Badan Geologi Bandung


Capacity : 1,8 Kwp
Year : 2013
Our Experience

Stand Alone PV System

Project Owner : Kementrian ESDM ; Year : 2013 ; Capacity : 15 kWp


Location : Ds.Sukaraksa, Kec.Tanjungsari, Kab.Bogor, Prov.Jawa Barat
Our Experience

Grid Connected Rooftop PV System


Location : PT. Pertamina (Persero) ; Capacity : 18 kWp ; Year: 2013
Our Experience

Grid Connected Rooftop PV System,


Location : PT. Badak NGL – Bontang ; Capacity : 2 x 75 kWp ; Year : 2013
Our Experience

Stand Alone PV
System Oil and Gas
(Offshore)

Location : PT. Santos


(Selat Madura)
Capacity : 5 kWp
Year : 2013
Our Experience

Project Name : Pengadaan Costal Survailance System dengan PLTS


Project Owner : Direktorat Jenderal Bea dan Cukai, Kementerian Keuangan
Location : Kantor Perwakilan Utama tipe B direktorat jenderal Bea Cukai, Batam Kepulauan Riau
Capacity : PLTS kapasitas 30 kWp
Year : 2015
Our Experience

DEMO PLANT SMART


GRID
Capacity : 500 KWp
Location : Sumba Barat Daya
Year : 2012
Our Experience

HYBRID PV – WIND -
DIESEL
BARON
TECHNOPARK
Capacity : - PV POWER| 36 KWp
- WIND | 15 KWP
- DIESEL | 35 KW
Location : Pantai Baron Yogyakarta
Year : 2012
Our Experience

Location : Batu Kecil Lampung

Location :
P.Sophialouisa
(P.Sepatang) Location : Pulau
Nusa Manuk,
Tenggara Jawa Barat
Barat
Navigation of Shipping
System
Our Client
Technical Information
Proposed SLD
Grid PLN
PV ARRAY INVERTER LVDB

Load

• PV Array adalah rangkaian dari beberapa modul Photovoltaic. PV Array


akan menghasilkan energi listrik (di siang hari) yang akan disalurkan ke
grid untuk menyuplai beban
On Grid
• Inverter mengubah listrik DC yang dihasilkan PV array menjadi listrik AC
untuk disalurkan ke grid System
• LVDB, merupakan panel proteksi listrik
Konfigurasi Sistem PLTS

30
PV Layout
Using Helioscope Simulation

Add a footer 31
PV Syst
Simulation

Add a footer 32
Helioscope
Simulation

Add a footer 33
The Material

JINKO SOLAR SMA


JKM320PP-72 SOLID-Q 50

SMA
DATA MANAGER M
Quotation Price

Equal to $0.96/Wp *

*The price is more accurate depending on the result of the survey


The Price in Pie Chart

Breakdown Price
$0.007

$0.004 $0.115
$0.011

Photovoltaic System
$0.083 Control System
Panels and Cables
Remote Monitoring System
$0.092 Pyranometer
Installation Material
$0.663 Services
The Other Price

O&M Cost 3% from EPC Cost *


*site visit once in a month
module clearing once in two months
O&M for 1 year

Ground Mounted
Add a sipil construction 0.2 USD/Wp
Cables price +0.005 USD/Wp
“It’s time to move into Renewable