Escolar Documentos
Profissional Documentos
Cultura Documentos
7SD52
EV-S_V13_17.07.00- 1
Protection and Substation Control
Protection and communication join together
Three benefits of the 7SD52
Differential protection for the
universal use with easy to handle
settings
Two up to six line ends , for serial and parallel
compensated lines, handles transformers and
compensation coils within the protection zone,
tripping time approx. 15 ms with fast high set element
Distance relay
7SA52
X21
G703.1 PCM SDH PCM
820 nm e multi- multi-
o
Option: max. o comms-network e
3 km
plexer plexer
I-REGB Comms-
time converter
synchronisation G703.1: 64 kBit
X21: N*64 kBit (1N8)
EV-S_V13_17.07.00- 3
Protection and Substation Control
Scope of functions / Hardware options
Options for the Protection Interface
Scope of functions Relay Hardware
820 nm
- Fast high set element O ST- 1,5 / 3 km
3Iph, and IE connector multimode
with charge comparision 4U
- Sensitive normal trip 8 binary inputs internal
16 contacts
stage with vector 1 - 2 protection interfaces
summation principle System interface O ST- 1300 nm
- Autoreclosure 1/3 pole PC-interface connector 10 km
Time synchronisation monomode
- Communication features
- Commissioning aid ½*19´´ internal
- Overload protection
16 binary inputs
- Backup-/emergency 24 contacts O 1300 nm
FC-
overcurrent connector 35 km
- Multiterminal extention 24 binary inputs monomode
32 contacts internal
- Switch on to fault
protection Option: 5 fast
Electrical
trip contacts
- 4 remote commands 820 nm E X21
24 remote signals 1,5 km G703.1
1*19´´
ST-
connectors O interface
External converter
EV-S_V13_17.07.00- 4
Protection and Substation Control
Hardware option of the comms interfaces
Protection interface 2
Port E
Remote line end 2
Synchronous N x 64kB/sec
Plug in
modules
Protection interface 1
Remote line end 1 Port D
Synchronous N x 64kB/sec
EV-S_V13_17.07.00- 5
Protection and Substation Control
Main board of the relay with it´s
Communication - Interfaces
Main processor
board of the relay
EV-S_V13_17.07.00- 6
Protection and Substation Control
Main protection function
Features of the differential function
EV-S_V13_17.07.00- 7
Protection and Substation Control
Adaptive differential relaying
Consideration of CT- errors and comms-errors
I1 I2
IDiff
IN
Tripping I2 I3
I3 area
Restraint I1
area
IDiff>
I1
I
Phasor summation: IDiff = I1 + I2 + I3 IN
Error summation: I = IDiff> + Linear CT-error ( IK) + Syncronization error
Trip, if diff.current exceeds the max. permissible error
EV-S_V13_17.07.00- 8
Protection and Substation Control
To complete the 7SD52
Additional functions
EV-S_V13_17.07.00- 9
Protection and Substation Control
Familiar with digital communication networks
Features of the relay to relay communication
EV-S_V13_17.07.00- 10
Protection and Substation Control
Ring and Chain topologie
Automatic change from
side 2 closed ring to chain, if side 2
one connection is lost
or not available
I2 I2 side 3
Connection to
side 3
other diff. relays
I3 I3+I1 I2 I3
I1+I2 I3
I1 I1
I3+I1
I1+I2
side 1 side 1
PI - Protection Interface
PI1
EV-S_V13_17.07.00- 12
Protection and Substation Control
Topologies: Ring topology, 6 line ends
PI2 PI1
PI - Protection Interface
EV-S_V13_17.07.00- 13
Protection and Substation Control
Plug and Protect
Commissiong helps and test features
Signal transmission time
Mean value of transmit and receive direction
Generation of signals for switching test loops
IL1_2
Sending of defined telegram patterns looped back to the
receive input of the transmitting relay
Phi1->2
Absolute value and phase measurement of currents
IL1_1
IL2_1
Local measurement of angle between IL1, IL2, IL3
,Angle between currents of each phase from remote
CB test trip
IL2_2
Counting of faulty telegrams in % per minute and hour
Activation of binary inputs and outputs by operating
IL3_2 software DIGSI 4.
IL3_1 Display of the status of binary inputs
Test telegrams to the substation control system
Automatic Switchover from 3 line to 2 line end
configuration (while commissioning 3rd line end)
Complete commissioning support with DIGSI 4 and
browser based PC-software
EV-S_V13_17.07.00- 14
Protection and Substation Control
Browser based commissioning aid
EV-S_V13_17.07.00- 15
Protection and Substation Control
Comprehensive fault analysis with DIGRA 4
I/A
1,50
1,00
0,50
-0,075 -0,050 -0,025 0,000 0,025 0,050 0,075 0,100 0,125
t/s
-0,00
-0,50
-1,00
-1,50
-2,00
60
40
-20
-40
-60
-80
EV-S_V13_17.07.00- 16
Protection and Substation Control
Prefault and fault conditions in the vector diagram
EV-S_V13_17.07.00- 17
Protection and Substation Control