Escolar Documentos
Profissional Documentos
Cultura Documentos
NICHOLAS LONGLEY
PARTNER
T: +61 3 8601 4585
E: NICK.LONGLEY@HFW.COM
INTRODUCTION
• Energy
• Construction
• Shipping
• Aviation
• Commodities
• Insurance
3
HFW CONSTRUCTION
• Introduction
• Session 1: Overview
– What is FIDIC
– The FIDIC Rainbow of Contracts
– 2017 Editions Underlying Principles
– 2017 Editions Main Changes
– Risk Allocation
• Session 2: The Parties and their Obligations
• Session 3: Contract Administration
• Session 4: Variations
SESSION 1:
OVERVIEW OF "NEW" FIDIC RAINBOW SUITE
"NEW" RED, YELLOW AND SILVER BOOKS
FIDIC'S APPROACH TO RISK ALLOCATION
SUMMARY OF CHANGES IN THE SECOND EDITIONS
WHAT IS FIDIC?
9
FIDIC 2017
CONTRACT RELEASE HISTORY
12
FIDIC 2017
SOME THEMES TO THE CHANGES
13
FIDIC 2017
LAYOUT AND STRUCTURAL CHANGES
• Structure of General Conditions remains familiar but almost every clause has been
changed
• Structural changes:
- now 21 Clauses (as opposed to 20 clauses in FIDIC 1999)
- definitions alphabetically listed
- new definitions include “Cost Plus Profit”; “Notice”; “Claims” and “Disputes”
- greater use of abbreviations: NOD, IPC, EOT
- different terminology, e.g. Particular Conditions:
- Part 1: [Appendix to Tender] Contract Data
- Part 2: Special Conditions
14
FIDIC 2017
LAYOUT AND STRUCTURAL CHANGES
– limitation of liability clause now at clause 1.15, rather than clause 17.6
– clause 17 concerning care of the Works has been re-named, and re-ordered
– clause 18 [Force Majeure Exceptional Events] and Clause 19 [Insurance] reversed
– clauses broken down into numbered sub-paragraphs and lists
• New, expanded Guidance Notes, with more example alternative clauses for use in
Special Conditions
15
FIDIC 2017
CLAUSE OUTLINE
17
FIDIC CONTRACTS
DOCUMENTS AND PRIORITY – CLAUSE 1.5
19
FIDIC CONTRACTS
ALLOCATION OF RISK
20
ALLOCATION OF RISKS
HOW IS IT DONE IN THE FIDIC CONTRACTS?
• Starting point: Contractor bears all risks for completing Works in accordance with the
Contract within the Time for Completion
unless
– risk is expressly allocated to Employer or
– contract provides that the Contractor is entitled to more money and/or more time as a
result of the risk (subject to governing law)
‒ EOT, Cost and/or Cost Plus Profit
21
FIDIC CONTRACTS
ALLOCATION OF RISK
Employer Contractor
Risk Risk
Risk Transfer
22
FIDIC CONTRACTS
ALLOCATION OF RISK
23
ALLOCATION OF KEY RISKS
DIFFERENCES BETWEEN FIDIC BOOKS
CONTRACTOR’S RISK?
Design ✓ ✓
Unforeseeable ground conditions ✓
Quantities / lump sum price ✓ ✓
Employer as contract administrator ✓
24
ALLOCATION OF SPECIFIC RISKS
CONTRACTOR’S ENTITLEMENTS
Sub- Silver
EOT Cost Profit
Clause Book?
Delayed drawings or instructions 1.9 (R) ✓ ✓ ✓
Errors in Employer’s Requirements 1.9 (Y) ✓ ✓ ✓
Employer’s delay or failure to obtain permits New 1.13 ✓ ✓ ✓ ✓ 1.12
Delay in access to Site 2.1 ✓ ✓ ✓ ✓
Unforeseeable co-operation 4.6 ✓ ✓ ✓ ✓
Errors in setting-out data 4.7 ✓ ✓ ✓
Unforeseeable physical conditions 4.12.4 ✓ ✓
Changes to access route New 4.15 ✓ ✓ ✓
Discovery of archaeological findings 4.23 ✓ ✓ ✓
25
ALLOCATION OF SPECIFIC RISKS
CONTRACTOR’S ENTITLEMENTS
Sub- Silver
EOT Cost Profit
Clause Book?
Instructions / delay in testing 7.4 ✓ ✓ ✓ ✓
Remedial work attributable to Employer New 7.6 ✓ ✓ ✓ ✓
Delays caused by Authorities 8.6 ✓ ✓
Suspension by Engineer / Engineer 8.10 ✓ ✓ ✓ ✓
Employer taking over Part of Works 10.2 ✓ ✓
Interference with Tests on Completion 10.3 ✓ ✓ ✓ ✓
Delay in access for remedial work in DNP New 11.7 ✓ ✓ ✓
Costs of searches in DNP 11.8 ✓ ✓ ✓
Delayed Tests after Completion 12.2 (Y) ✓ ✓ ✓
26
ALLOCATION OF SPECIFIC RISKS
CONTRACTOR’S ENTITLEMENTS
Sub- Silver
EOT Cost Profit
Clause Book?
Delay in access for remedial work 12.4 (Y) ✓ ✓ ✓
Changes in Laws* 13.6 ✓ ✓ ✓
Contractor suspension 16.1 ✓ ✓ ✓ ✓
Damage to Works due to an Employer’s risk 17.2 ✓ ✓ ✓ ✓
Exceptional Events 18.4 ✓ ✓† ✓
27
SESSION 2:
THE PARTIES AND THEIR OBLIGATIONS
THE CONTRACTOR'S KEY OBLIGATIONS, INCLUDING DESIGN AND COMPLETION
THE EMPLOYER'S KEY OBLIGATIONS
KEY CHANGES IN THE SECOND EDITIONS
FIDIC 2017
OVERVIEW OF CONTRACT STAGES
Date of Performance
Completion Certificate
remedying
Commencement
defects
Date
Tests on notifying
Completion defects
Tests after
Completion
Delay Performance
Damages Damages
• Permits (1.13)
• Performance Security (4.2)
30
FITNESS FOR PURPOSE
CHANGES IN FIDIC 2017
31
FITNESS FOR PURPOSE
CHANGES IN FIDIC 2017 – INDEMNITY & INSURANCE
• Fitness for purpose obligation now backed by new indemnity at clause 17.4 (YB):
“The Contractor shall also indemnify and hold harmless the Employer against all acts, errors or
omissions by the Contractor in carrying out the Contractor’s design obligations that result in the
Works (or Section of Part or major item of Plant, if any), when completed, not being fit for the
purpose(s) for which they are intended under Sub-Clause 4.1”
• Guidance notes include an ‘Advisory Note’ on BIM (including which clauses would need to
be amended if BIM used)
33
DESIGN (2)
ERRORS IN EMPLOYER’S REQUIREMENTS
• Responsibility for errors in Employer’s Requirements different between Yellow Book and
Silver Book:
– Silver Book: Contractor is responsible for errors
– Yellow Book: FIDIC 2017 (1.9) follows similar principles to FIDIC 1999:
‒ if error would not have been discovered by an experienced contractor exercising due
care, Variation mechanism applies for measures to deal with error
‒ Contractor entitled to Cost Plus Profit
‒ But silent if error should have been discovered
34
LIMITATION OF LIABILITY
CHANGES IN FIDIC 2017
35
LIMITATION OF LIABILITY
CHANGES IN FIDIC 2017
• Carve-outs from exclusion of liability for indirect losses and loss of profit now include:
– Employer:
‒ Delay Damages
‒ Claims under intellectual property indemnities
– Contractor:
‒ Variations
‒ losses in respect of omission of work to give it to third parties
‒ losses following a termination for convenience under clause 15.7
36
SESSION 3:
CONTRACT ADMINISTRATION
THE ROLE OF THE ENGINEER
REPORTING REQUIREMENTS
THE ENHANCED ENGINEER'S DETERMINATION PROVISIONS IN THE SECOND EDITIONS
CONTRACT ADMINISTRATION
ROLE OF THE ENGINEER IN FIDIC CONTRACTS (1)
• Engineer:
– deemed to act for the Employer
– shall act as skilled professional New
– authority and role defined by Contract
– not a Party to the Contract
– no authority to amend Contract
– no authority to relieve Party of duty or responsibility except as stated
‒ if Employer’s approval required, then deemed given
– constraints on authority to be specified
‒ no constraint under clause 3.7 New
38
CONTRACT ADMINISTRATION
ROLE OF THE ENGINEER IN FIDIC CONTRACTS (2)
39
CONTRACT ADMINISTRATION
WHO IS THE ENGINEER?
• Engineer may delegate certain (but not all) duties to suitably qualified assistants (3.3/3.4)
• Engineer may appoint Engineer’s Representative to act on Engineer’s behalf on Site (3.3)
New
40
CONTRACT ADMINISTRATION
PROCEDURES – CHANGES IN FIDIC 2017
41
CONTRACT ADMINISTRATION
TIME LIMITS, DEEMING PROVISIONS AND TIME-BARS
42
CONTRACT ADMINISTRATION
COMMUNICATIONS – CLAUSE 1.3
• Communications to be sent:
– by hand, mail or courier (against receipt) → received when delivered
– by electronic transmission system stated in Contract Data → deemed to have been
received day after transmission
New
if no non-delivery notification
43
CONTRACT ADMINISTRATION
FIDIC 2017 – NOTICES (1)
44
CONTRACT ADMINISTRATION
FIDIC 2017 – NOTICES (2)
• Other Notices
– Notice of Dissatisfaction (NOD)
– Notice to Correct (15.1)
– Notice of Claim (20.2.1)
45
CONTRACT ADMINISTRATION
FIDIC 2017 – COMMUNICATIONS AND PARTIES
46
ENGINEER’S DETERMINATION
FIDIC 1999 – CLAUSE 3.5 TIMELINE
Engineer’s
determination
Start
No agreement
Engineer
proceeds with
Consultation determination
? days ? days
47
ENGINEER’S DETERMINATION
FIDIC 2017 – CLAUSE 3.7 TIMELINE
Notice of the
Engineer’s Notice of
Notice of
Determination Dissatisfaction
corrected
Start determination with the
Engineer’s
No agreement Determination
Notice
of error
Engineer
proceeds with
Consultations determination
48
ENGINEER’S DETERMINATION
CHANGES IN FIDIC 2017 (1)
49
ENGINEER’S DETERMINATION
CHANGES IN FIDIC 2017 (2)
• If agreement → Notice of the Parties’ Agreement, signed by Parties = final and binding
New
• If no agreement within 42 days → Engineer to make determination within 42 days
• If Engineer does not issue Notice of the Engineer’s Determination within 42 days:
→ Claim deemed rejected
→ “matter” deemed to be a Dispute and may be referred to DAAB without Notice of New
Dissatisfaction
50
ENGINEER’S DETERMINATION
DUTY TO ACT NEUTRALLY
51
SESSION 4:
VARIATIONS AND PAYMENT
WHAT IS A VARIATION?
THE REVISED VARIATION PROCEDURE AND VALUATION
PAYMENT PROCEDURES
VARIATIONS
INTRODUCTION
• Variation provisions give the Employer (through the Engineer) the unilateral right to vary
or change the Works
• If there were no variation provisions, the Parties would need to agree on:
– scope
– payment (money)
– time consequences
53
VARIATIONS
CHANGES IN FIDIC 2017
• New provisions: Performance Security (4.2) and Employer’s financing arrangements (2.4)
54
VARIATIONS
WHAT IS A VARIATION?
• “Variation” means:
– any change to the Works
– which is instructed as a variation under Clause 13 [Variations and Adjustments]
• Under FIDIC 2017, Variations can be initiated in two ways (clause 13.3):
– greater clarity and detail as to procedures that apply: Variation Instruction required
1. Engineer’s instruction:
‒ Variation instruction by giving a Notice
‒ Contractor to proceed with execution of Variation
‒ Contractor to submit detailed particulars for varied work, time and money within 28 days
‒ Engineer to proceed under clause 3.7 to agree or determine time and money
• In FIDIC 2017, Contractor retains right to object to Variation and grounds for objection
expanded (13.1):
– Contractor cannot readily obtain Goods required for Variation
– adverse impact on achievement of performance guarantees (Yellow & Silver Books)
– if Variation was Unforeseeable having regard to the nature of the Works included in the
Specification / Employer’s Requirements
– adverse impact on Contractor’s ability to comply with HS&E New
– adverse impact on Contractor’s ability to comply with fitness for purpose obligations
(Yellow & Silver Books)
• Contrast with FIDIC 1999: instruction was Variation by nature and not by title
• Advantages and disadvantages: greater certainty v. impasse problem
58
VARIATIONS
VARIATION INSTRUCTIONS (2)
• Valuation of Variations
– Red Book: rates and prices in Bill of Quantities
– Yellow & Silver Books:
‒ Schedule of Rates and Prices
New
‒ if no schedule, Cost Plus Profit
• Omissions: if work omitted, Parties may agree to others carrying out the work, and
Contractor is entitled to loss of profit and other losses / damages
New
60
SPEAKER’S PROFILE
Nick Longley
Partner
Melbourne
T: +61 (0)3 8691 4585
E: Nick.longley@hfw.com
Introduction
Nick advises his clients on matters relating to construction and construction insurance law with a focus on arbitration relating to major
infrastructure and energy-related projects. He advises governments, employers, main contractors, specialist subcontractors, construction
professionals and insurers on all aspects of construction law. He also advises insurers and insureds on policy interpretation and claims.
What the market says about Nick
Nick Longley is highly recommended by Legal 500 Asia Pacific 2017 for Construction.
Nick Longley is listed in International Who's Who within their list of the World's leading construction lawyers 2007 - 2017.
"With his involvement we have confidence that our interests are protected." (Chambers Asia Pacific 2016)
Construction – FIDIC Experience
• Advising a Korean contractor on a dispute under a FIDIC Yellow Book contract for a paper mill in Vietnam. The main issues included claims for
variations and liability for defects Advising Korean Contractors on issues in connection with a FIDIC White Book project for a stay cable bridge
in India.
• Advising Korean contractors on issues arising under a FIDIC Red Book contract for a road project in Kazakhstan. The primary issue concerned
the application of Clause 13.8
• Advising Korean contractors on a road project in Vietnam under a FIDIC Red Book.
• Advising contractors on a Pink Book project issued by the Asia Development Bank for the construction of a University in the Solomon Islands.
61
© 2018 Holman Fenwick Willan LLP. All rights reserved
Whilst every care has been taken to ensure the accuracy of this information
at the time of publication, the information is intended as guidance only.
It should not be considered as legal advice.
Beirut Brussels Dubai Geneva Hong Kong Houston Jakarta Kuwait London Melbourne Paris Perth Piraeus Riyadh São Paulo Shanghai Singapore Sydney