Escolar Documentos
Profissional Documentos
Cultura Documentos
In
Interstate Transmission system
• Definitions
Contents
• Legal provisions
Ancillary
Market
PX
2008
Open Access
2004
ABT
2002-03
IEGC
Feb.’2000
INDIA August 2006
3,287,263 sq. km area North synchronized
With Central Grid
More than 1 Billion people (2001 census)
Installed Capacity of March 2003
141.08 GW (Jan-08) West synchronized NEW Grid
With East & Northeast
South
October 1991 Grid
East and Northeast
synchronized
Central Grid
North
East
West
Northeast
South Merging of markets along with
Five Regional Grids
Five Frequencies
synchronization of regions
Present Market at a Glance
Schedules
Balancing Market ( UI )
( Real Time Operation )
DEFINITION OF “OPEN ACCESS” IN THE
ELECTRICITY ACT, 2003
• RLDC will check if connectivity with CTU/ ISTS or STU system (as the
P case may be) is established, necessary metering,protection,
R communication are in place, transfer capability upto the CTU network for
O power flow of the quantum of injection/drawal applied for is available on
the date of application and whether the applicant has undertaken to abide
C by the Central Electricity Authority (Technical Standards for Connectivity
E to the Grid) Regulations, 2007.
D
U • Application to be submitted to::
– Nodal RLDC where point of drawal is situated
R
– & also to all RLDCs involved in the transaction
E
S • Application Contents
– Details:: Buyer / Seller / Point of injection/ point of drawal / Contracted
power at supplier interface/ date/ time period (as per (Format-I-
Application for scheduling) alongwith application fee/SLDC
concurrance
Regulation 7: Application Fee
• An application made for each bilateral
transaction or the collective transaction shall
be accompanied by a non-refundable fee of
Rupees five thousand (` 5000/-)only
Adv D OP-1
Application for
M1 FCFS
CONTINGENCY
Adv Application
for M2,
Approvals for
M1
Adv Application
for M3,
Approvals for
M2
Approvals for
M3 Day Ahead / PX
LEGEND:
DOP
OP
: Day of Operation
DLL : Last day of M0
Regulation 9:
Procedure for Advance Scheduling
for bilateral transactions
ADVANCE SCHEDULING
• Advance Scheduling – 3 months in advance
• Separate Application –
– Month wise - each transaction
• Time Line for submission
– Last date for submission ( -10 / -5 / 0 days prior to end of current
month MO – for transaction in M1, M2, M3)
– Cut-off time of application: 17:30 Hrs. of last day (Day 0)
– Request for concurrence (RLDC) – by 12:00 Hrs.(Day 1) (Format- III)
– Concurrence - by 20:00 Hrs (Day 1)
– Congestion Information to Applicant – 12:00 Hrs (Day 2)-Format-
IV(Congestion information-Advance scheduling)
– Revised Request/re-routing – 11:00 HRs. (Day3)-Format-V-Request
for revision due to congestion)
– E-bidding – in case of Congestion (Day 4)
– Acceptance/Refusal of Scheduling Request – (Day5)-Format-VI-
Acceptance for scheduling
Application for advance scheduling
M0 M1 M2 M3
Applicatio
Applicatio
nn
M0 D -03 D0 M2 M3
Processing time
Application
Application
Approval after Collective
• For period of revision/cancellation > two days:: Transmission Charges and Operating
Charges for the period beyond two (2) days shall be payable as per the revised
accepted schedule and for the first two (2) days as per the original schedule .
• Curtailment priority ::
STOA(bilat)Collective(PX)MTOALTA
• Provided that in case the State Commission has not determined the
transmission charges, the charges for use of respective State network
shall be payable at the rate of Rs.80/MWh for the electricity transmitted:
• Provided also that the transmission charges payable for use of the State
network shall be conveyed to the Regional Load Despatch Centre
concerned who shall display these rates on its web site:
• Provided also that the transmission charges payable for use of the State
network shall not be revised retrospectively.
Application of POC methodology
for STOA transactions
Calculation of Nodal POCs
Input Network Parameters
Load & Generation Data
Converged Network
Network
Reduction
Reduced Network
Software for PoC
Line wise YTC Charge & Loss
Computation
• Collective Transaction
– Rs.5000/- per day or part of the day/state to NLDC
– Rs.2000/- per day or part of the day/transaction for each
SLDCs involved
– NLDC to share operating charges with each RLDC
• NLDC keeps Rs.2000/- and Rs.3000/- divided amongst 5
RLDCS @ Rs.600/RLDC
– Clubbing of buyers & sellers within a state
– Each group be considered as single entity for Operating
charges and for scheduling by NLDC
– Each point of drawal & injection shall be counted separately for
the purpose of intra-state transmission charges
Regulation 18: Payment of transmission charges
and operating charges
• Bilateral transaction:
– the applicant to deposit with the nodal agency
transmission charges and operating charges within
three (3) working days of grant of acceptance
• Collective transactions:
– the power exchange shall deposit with the nodal
agency these charges by the next working day falling
after the day on which its application was processed
– the transmission charges for use of State network
and operating charges for SLDC shall be settled
directly by the power exchange with respective
SLDC.
Regulation 19: Default in payment of STOA charges
P
R •Cheque has been dishonored
O – No cheque payment - next three (3) months
C
E – Payment to be made by electronic
D transfer/demand draft
U
R
E
S
C
T
INCORPORATION IN DAILY SCHEDULES
U • Incorporation in Daily Schedules of the Regional Entities
P
• Average energy losses - estimated on weekly basis and
R converted to Tier I, II, III slabs
O
– RLDCs – ISTS (Inter State Control area)
C
E – SLDC – (Intra-State/Control area)
D
U • Resolution of 0.01 MW at each State/inter-Regional
R boundaries.
E
S • Losses on the system to be compensated by Drawing
utility (net drawal schedule after deducting losses) till
30th Sep,2011
The Tier-I, II, II slabs are fixed as per studies & are constant for the review period
are as below
• The transmission charges collected by the nodal agency for use of the
transmission system other than State network, for a bilateral
transaction shall be directly disbursed to CTU.
Reg.25(previous)…Ctd
• The operating charges including application
fees are deposited in LDC Development
Fund.
• The transmission charges collected by the nodal agency for use of the
transmission system other than State network, for both bilateral and
collective transaction shall be given to the CTU for further
disbursement to long-term customers in accordance to Central
Electricity Regulatory Commission (Sharing of Inter State Transmission
Charges and Losses) Regulations, 2010, and the approved detailed
procedure there under for Billing, Collection and Disbursement.
Billing, Collection & Disbursement Procedures Approved by CERC
Vide order dtd.29 th April,2011 – Para &(3) b & c
• For STOA, DIC shall have to pay applicable transmission charges to
the RLDC/NLDC at the time of application. The payment made for the
STOA charges for varying quantum and varying duration with respect to
(i) bilateral transactions to the region of LTA granted and (ii) all
collective transactions, shall be credited to that DIC in the next month
billing subject to the upper limit of the amount paid as LTA charges
after accounting for the MTOA charges, if any, as per 7.2 (b) above,
provided that the STOA is in the direction of the targeted regions
mentioned in the LTA granted to the DIC by the CTU.
• If the STOA is other than the targeted regions mentioned in the LTA,
then such STOA, PoC charges shall not be adjusted against the LTA
granted by the CTU and a separate applicable PoC charges shall have
to be paid by the DIC.
Billing, Collection & Disbursement Procedures Approved by CERC
Vide order dtd.29 th April,2011 – Para &(3) b & c
• Provided that this adjustment shall not be done for collective
transaction and bilateral transactions done through portfolio trader.
EXAMPLE
Source : SAIL
Loss calculation Methodology (upto 30 th Sep,2011)
Contract value 100MW
Transaction Tata steel- DVC - ER – WR – NR – DTL- NDPL
DVC STU loss 3% DVC Inj POC loss 1.5%
Delhi withdrawal POC loss 2% DTL STU loss 1.5% RLDCs need to
show schedules
only upto requisite
control area
97MW
95.55MW periphery
DVC BDY REGIONAL
100MW ER BDY Hence schedule
93.64MW
CONTRACT values only upto
TATA STEEL
DTL BDY DVC boundary &
BDY TATA DTL boundary need
STEEL
be shown by
RLDCs.
WR Accordingly, all
STU losses are not
NDPL required. [Values
NR
are shown for
understanding
only].
92.24MW
NDPL BDY
Loss calculation Methodology (w.e.f 1 st October,2011)
Contract value 100MW
Transaction Tata steel- DVC - ER – WR – NR – DTL- NDPL
DVC STU loss 3% DVC Inj POC loss 1.5%
Delhi withdrawal POC loss 2% DTL STU loss 1.5% RLDCs need to
show schedules
only upto requisite
control area
101.52MW
100MW periphery
DVC BDY CONTRACT
104.66MW ER Hence schedule
98MW
TATA STEEL
values only upto
BDY
DTL BDY DVC boundary &
TATA DTL boundary need
STEEL
be shown by
RLDCs.
WR Accordingly, STU
losses are not
NDPL required w.e.f
NR
01/10/11 [Values
are shown for
understanding
96.53MW only].
NDPL BDY
STOA charges calculation Methodology:: Tata Steel-DVC-ER-WR-NR-DTL-
NDPL
Contract value 100MW RTC power x 5 days 12000MWh(total contracted energy)
Transaction Tata steel- DVC - ER – WR – NR – DTL- NDPL
DVC injection POC 14p/unit Rs.140/MWh
Delhi withdrawal POC 10p/unit Rs.100/MWh
DVC STU
DVC injection DTL STU
transmission Delhi
POC transmission
charges = 80 x withdrawal NRLDC
transmission charges =
12000 ER POC operating
charges = 140 41.85 x
DVC SLDC transmission charges =
x 12000 12000
operating charges = 2000 x 5
charges = 100 x 12000
2000 x 5 TATA DTL SLDC
STEEL operating
ERLDC charges =
operating 2000 x 5
charges = WR
2000 x 5
100MW
Upto 30th
CONTRACT NDPL Sep,2011
NR
VALUE Contract value
at sellers’
WRLDC periphery. No
operating
charges = change in
ALL OF ABOVE
2000 x 5 calculations
+
NON REFUNDABLE APPLICATION FEES Rs.5000/-
Sample bill for
the transaction
Regulation 25A:: STOA Not To Be Granted
• The period of Access for categorization of LT cusyomers is not yet uniform across
States e.g for WB >= 15 Yrs, Orissa >=25Yrs, Jharkhand >=10years
OA charges-Transmission charges
• Inter State charges as applicable
• Intra-State charges calculated as follows:
Transmission Charges = ATC/(PLST X365) (in Rs./MW-day)
Where,
ATC= Annual Transmission Charges determined by the Commission
for the State transmission system for the concerned year.
PLST= Peak load projected to be served by the State transmission
system in concerned year
• Transmission charges shall be payable on the basis of contracted Capacity/
Scheduled Load or actual power flow whichever is higher.
• For Open Access for a part of a day, the transmission charges shall be
payable on pro-rata basis:
• Where a dedicated transmission system used for open access has been
constructed for exclusive use of an open access customer, the transmission
charges for such dedicated system shall be worked out by transmission
licensee for their respective systems and got approved by the Commission
and shall be borne entirely by such open access customer till such time the
surplus capacity is allotted and used for by other persons or purposes.
OA charges-Scheduling & System Operation charges
• Intra-State charges for above other than Inter-State as decided
by CERC as follows:
• Long-term access and medium-term open access
– SLDC charges determined by the Commission under sub-
section (3) of section 32 of the Act
• Provided also that an open access customer connected to the STU system
shall be liable to pay the wheeling charges determined under this
regulation, if such customer was paying wheeling charges directly or
indirectly before availing open access.
• In case an Open Access customer continues to pay the fixed charge and
such fixed charge can be attributed to wheeling/distribution network
related cost, partly or fully, SERC may provide for adjustment of such fixed
charges against the wheeling charges determined as above
OA charges-Cross Subsidy Surcharge
• If open access facility is availed of by a subsidising consumer of a distribution
licensee of the State, then such consumer, in addition to transmission and/or
wheeling charges, shall pay cross subsidy surcharge determined by the
Commission.
• Cross subsidy surcharge determined on Per Unit basis shall be payable, on
monthly basis, by the open access consumers based on the actual energy drawn
during the month through open access. The amount of surcharge shall be paid to
the distribution licensee of the area of supply from whom the consumer was
availing supply before seeking open access.
• Cross Subsidy Surcharge formula:
• S = T – [ C (1+ L / 100) + D ]
• S is the surcharge
• T is the Tariff payable by the relevant category of consumers;
• C is the Weighted average cost of power purchase of top 5% at the margin
excluding liquid fuel based generation and renewable power
• D is the Wheeling charge in per kWh basis (to be derived from the wheeling charge
in Rs./MW-Day
• L is the system Losses for the applicable voltage level, expressed as a percentage
• Provided that in case the above formula gives negative value of surcharge, the
same shall be zero:
OA charges-Cross Subsidy Surcharge
• Provided further that the Commission may fix a lower surcharge in the situation of
shortages and load shedding by the distribution licensee:
• Provided also that such cross subsidy surcharge shall not be levied in case
distribution access is provided to a person who has established a captive generation
plant for carrying the electricity to the destination of his own use.
• Provided that in case power supply position or the consumer load seeking open
access changes substantially, the Commission may review the Cross Subsidy
Surcharge as and when required
• Provided further that the revised cross subsidy surcharge so determined by the
Commission in subsequent years shall be applicable only to the new Open Access
applicants.
OA charges-Additional surcharge
• Additional surcharge shall become applicable only if the obligation of the
licensee in terms of power purchase commitments has been and continues to
be stranded or there is an unavoidable obligation and incidence to bear fixed
costs consequent to such a contract. However,the fixed costs related to
network assets would be recovered through wheeling charges.
• The distribution licensee shall submit to the Commission on six monthly
basis, a detailed calculation statement of fixed cost which the licensee is
incurring towards his obligation to supply.
• The Commission shall scrutinize the statement of calculation of fixed cost
submitted by the distribution licensee and obtain objections, if any, and
determine the amount of additional surcharge:
• Provided that any additional surcharge so determined by the Commission
shall be applicable only to the new open access customers.
• Additional surcharge determined on Per Unit basis shall be payable, on
monthly basis, by the open access consumers based on the actual energy
drawn during the month through open access:
• Provided that such additional surcharges shall not be levied in case
distribution access is provided to a person who has established a captive
generation plant for carrying the electricity to the destination of his own use
OA charges-Standby charges
• In cases of outages of generator supplying to open access customer
under open access, standby arrangements should be provided by the
distribution licensee for a maximum period of 42 days in a year, subject
to the load shedding as is applicable to the embedded consumer of the
licensee and the licensee shall be entitled to collect tariff under
Temporary rate of charge for that category of consumer in the prevailing
rate schedule subject to the condition that such tariff shall not exceed
the highest consumer retail tariff in the prevailing rate schedule:
• Provided that in cases where temporary rate of charge is not available
for that consumer category, the standby arrangements shall be provided
by the distribution licensee for a maximum of 42 days in a year and on
payment of fixed charges of 42 days and energy charges for that
category of consumer in the prevailing rate schedule:
• Provided further that in case of stand by arrangements sought by
continuous process industries, the licensee shall charge on the basis of
actual costs involved in arranging power:
• Provided also that open access customers would have the option to
arrange stand-by power from any other source.
OA charges-Imbalance Charges
• In case of deviation by open access consumers with load of less than 10
MW, the difference between the applicable sanctioned Open Access load
and the actual drawal shall be accounted through the Time of Day (ToD)
Meters on monthly basis and settled at the rate of the imbalance charge as
determined by the Commission (where imbalance charge has not been
determined by the Commission, UI charges as specified by the Central
Commission shall be applicable).
• In case of underdrawal as a result of non availability of the distribution
system or unscheduled load shedding, the open access consumer shall be
compensated by the distribution licensee at the average power purchase
cost of the distribution licensee.
• Deviations between the schedule and the actual injection/drawal in respect
of open access consumers with load of 10 MW and above and the
Generating Stations irrespective of the capacity, shall be settled based on
the composite accounts for imbalance transactions issued by SLDC on a
weekly cycle based on net metering in accordance with the charges
specified by the State Commission.
• Where the imbalance charges are not specified by State commission UI
charges specified by the Central Commission to be used.
OA charges-Imbalance Charges
• Payment of imbalance charges shall have a high priority and the
concerned constituents (including the licensees or the open access
customers as the case may be) shall pay the indicated amounts
within 10 (ten) days of the issue of the statement, into a State
imbalance pool account operated by the SLDC.
• Recipient would then be paid out from the State imbalance pool
account, within three (3) working days.
• If payments against the above imbalance charges are delayed by
more than two days, i.e., beyond twelve (12) days from the date of
issue of statement, the defaulting party shall have to pay simple
interest @ 0.04% for each day of delay.
• The interest so collected shall be paid to the person who had to
receive the amount, payment of which got delayed.
• Persistent payment defaults, if any, shall be reported by the SLDC
to the Commission, for initiating remedial action.
OA charges- Reactive Energy charges
• In respect of open access consumer having a load of 10 MW or
above, the payment for the reactive energy charges by open access
consumers shall be in accordance with provisions stipulated in the
State Grid Code.
• Where the reactive energy charges are not specified by the State
Commission, charges as per provisions stipulated in the IEGC shall
be applicable