SITE GRADING OF PETCOKE HANDLING FACILITIES

Limay, Bataan

PROGRESS ACCOMPLISHMENT

As of:
July 7, 2015
Project Status Report
(Based on Consolidated Schedule)

OVERALL ACCOMPLISHMENT AS OF JULY 7, TIME PROJECT


2015 Site
Site Grading
Development
Start of Project 6-May-14 28-May-14
Projected: 100%
Target
20-Jul-14 13-Aug-14
Actual: Completion

Previous 77.56% Time Elapse 416 Days

Present 0%

To date 77.56%

VARIANCE -22.44%

No. of Days
93Days
Delayed
ACCOMPLISHMENT:
ROAD A: 100% Completed
ROAD 1A: 100% Completed
ROAD B: 100% completed up to selected borrow
only
ROAD C: 100% completed up to selected
borrow.
ROAD D: 29% completed
ON GOING ACTIVITIES – PHASE I

ACTIVITIES REQUIRED ACTUAL BALANCE COMPLETION REMARKS


DATE

A. ROAD NETWORK:

Road B – (Road 124LM - -


30 days to
going to Daelim) complete To be started upon
completion of Petcoke
Road C- (Road at 15 days to clearing/hauling
South Side of RMP- 160LM 60LM 100LM
2)
complete

Road D – (Road at
South Side of 205LM 60LM 145LM 30 days On going leveling
Storage Area)
ADDITIONAL WORKS FOR PETCOKE PHASE -I:

REQUIR
ACTIVITIES ED
ACTUAL BALANCE COMPLETION REMARKS
DATE
1. Retaining Wall at 135 0
135 cu.m. June 7, 2015 Completed.
South Slope of Road-D CU.M. CU.M.
1. This can only be done mostly
by manual application due to
2. Paving @ Crusher 91 171 various obstruction underneath
262 cu.m. August 16, 2015
area cu.m. cu.m. the crusher bldg.
2. On going laying/installation of
RSB/concreting

3. Perimeter fence @ On going construction of footing


108 lm - - August 16, 2015
Crusher area & pedestal.

4. Liquid Starter Vault. 1 unit 73.92% 26.08% July 18, 2015 On going.
PROGRESS PHOTO – PHASE 1
LIQUID STARTER VAULT:
PAVEMENT BESIDE CRUSHER B: CONCRETING
PERIMETER FENCE AT CRUSHER AREA: FOOTING FOUNDATION
PREPARATION OF ROAD D (South Lane)
ACCOMPLISHMENT:
OILY SEWER LINE (B.I. PIPE) : 100% Completed
SLOPE PROTECTION @ SOUTH & WEST: 75%
Completed
Demolition and relocation works: 100%
completed
ROAD E: Completed cutting to desired elevation
ON GOING ACTIVITIES – ADDITIONAL WORKS (PHASE II)

ACTIVITIES REQUIRED ACTUAL BALANCE COMPLETION REMARKS


DATE

A. OTHER ACTIVITIES: (PART OF ARCHEN ADDITIONAL WORKS-PHASE II)


1. STOREYARD
STORM SEWER
WITH OILY WATER:
1.1 TRENCH CANAL
WITH STAINLESS 107.60LM 107.60LM 0 - Completed except for gratings.
MESH GRATING:
1.2 CARBON STEEL
PIPE 8” DIA. (B.I. 150.2LM 150.2LM 0 Completed.
PIPE)
1.3 CATCH BASIN 5 UNITS 5 UNITS 0 Unit - Completed.
Completed cutting to desired
2. ROAD E. 179LM - -
elevation.
3. SLOPE AT SOUTH
1,023 769 254 On going concreting at West &
& WEST SIDE OF -
sq.m. sq.m. sq.m. South side
PHASE II

4. Open Canal at the On going laying of pre-fabricated


256LM 115LM 141LM
base of Slope; open canal
INSTALLED PRE-FABRICATED OPENCANAL: SOUTH SIDE OF PHASE II
THANK YOU!