Limay, Bataan
PROGRESS ACCOMPLISHMENT
As of:
July 7, 2015
Project Status Report
(Based on Consolidated Schedule)
Present 0%
To date 77.56%
VARIANCE -22.44%
No. of Days
93Days
Delayed
ACCOMPLISHMENT:
ROAD A: 100% Completed
ROAD 1A: 100% Completed
ROAD B: 100% completed up to selected borrow
only
ROAD C: 100% completed up to selected
borrow.
ROAD D: 29% completed
ON GOING ACTIVITIES – PHASE I
A. ROAD NETWORK:
Road D – (Road at
South Side of 205LM 60LM 145LM 30 days On going leveling
Storage Area)
ADDITIONAL WORKS FOR PETCOKE PHASE -I:
REQUIR
ACTIVITIES ED
ACTUAL BALANCE COMPLETION REMARKS
DATE
1. Retaining Wall at 135 0
135 cu.m. June 7, 2015 Completed.
South Slope of Road-D CU.M. CU.M.
1. This can only be done mostly
by manual application due to
2. Paving @ Crusher 91 171 various obstruction underneath
262 cu.m. August 16, 2015
area cu.m. cu.m. the crusher bldg.
2. On going laying/installation of
RSB/concreting
4. Liquid Starter Vault. 1 unit 73.92% 26.08% July 18, 2015 On going.
PROGRESS PHOTO – PHASE 1
LIQUID STARTER VAULT:
PAVEMENT BESIDE CRUSHER B: CONCRETING
PERIMETER FENCE AT CRUSHER AREA: FOOTING FOUNDATION
PREPARATION OF ROAD D (South Lane)
ACCOMPLISHMENT:
OILY SEWER LINE (B.I. PIPE) : 100% Completed
SLOPE PROTECTION @ SOUTH & WEST: 75%
Completed
Demolition and relocation works: 100%
completed
ROAD E: Completed cutting to desired elevation
ON GOING ACTIVITIES – ADDITIONAL WORKS (PHASE II)