Escolar Documentos
Profissional Documentos
Cultura Documentos
Resource Allocation
1
‘Step Wise’ – Project Planning
0.Select
1. Identify project 2. Identify project
project objectives infrastructure
3. Analyse
project
characteristics
Review
4. Identify products
and activities
5. Estimate effort
Lower for activity
For each
level
6. Identify activity activity
detail
risks
10. Lower level
7. Allocate
planning
resources
8. Review/ publicize
9. Execute plan plan
2
7.1 Identify and allocate resources to activities
– Type of staff needed
– Numbers
– Staff availability
– Non-project activities
– Resource Schedule.
– Cost Schedule.
6
8.2 Nature of resources
• Labour : Even the project manager
• Time
– Task Complexity: 5.
– Task Category: Skilled (other categories may be
Management, Leadership, Expert)
8.4 Resource Scheduling
• Precedence graph
• Resource histograms
12
Activity bar chart
13
Resource histograms
14
Resource smoothing
• It is usually difficult to get specialist staff who will work odd days
to fill in gaps – need for staff to learn about application etc
15
Before And after smoothing
Resource clashes
• Where same resource needed in more than one place at the
same time
• delaying start of one activity until finish of the other activity that
resource is being used on - puts back project completion
17
Prioritizing activities
18
Total Float Priority
2. Critical activities.
5. Non-critical activities.
• Availability
• Criticality
• Risk
• Training
23
8.8 Publishing the resource schedule
Costs include:
• Staff costs
• Overheads
• Usage charges
Staff costs – includes not just salary, but also social security
contributions by the employer, holiday pay etc. Timesheets are often used
to record actual hours spent on each project by an individual. One issue
can be how time when a staff member is allocated and available to the
project, but is not actually working on the project, is dealt with.
Overheads - e.g. space rental, service charges etc. Some overheads
might be directly attributable to the project; in other cases a percentage of
departmental overheads may be allocated to project costs.
Usage charges – some charges can be on a ‘pay as you go’ basis e.g.
telephone charges, postage, car mileage – at the planning stage an
estimate of these may have to be made
26
8.10 The Scheduling Sequence
31
Balancing concerns:
adjusted accordingly.
Balancing concerns
33
Example to solve Histogram
Id. Duration Precedents Resource
A 2 4
B 2 A 4
C 2 A 6
D 2 B 3
E 4 C 1
F 1 C,E 2
34
Example to solve Histogram
35
Example to solve Histogram
36
Example to solve Histogram
37