Escolar Documentos
Profissional Documentos
Cultura Documentos
340401
29 February 2016
Access Ramp
1. The Engineer does not agree that it was armour rock that was
encountered and that they were boulders and that they were
foreseeable from the ground investigation reports available at the
time of tender.
2. The claim is now under arbitration and since the Engineer does
not accept there has been any unforeseen element then there can
be no EOT from the Engineer.
3. If the Chief Engineer were to consider and grant any such EOT
then this would be making an assumption that the arbitration will
find in favour of the Contractor.
4.Time for the Access Ramp works is concurrent with other works
and is not critical and even adding up all the (unaccepted) times
claimed by the Contractor then this would be less than the overall
extension of time already granted. So it has no effect.
2 29 February 2016
Access Ramp SA-1 & SA-2 Restriction
1. Contract Document Serial Page 0069 set out the requirements
for security compliance and the Contractor at the time of tender
was required to make allowance for occasional restrictions.
3 29 February 2016
Access Ramp SA1 & SA2 cont’d
5. The Contractor has not provided a detailed submission for this
claim even after several notices to do so and therefore the
Engineer is unable to give a determination.
4 29 February 2016
FOB Underwater Blasting
1. Agreement on the extent that this was unforeseen has been
agreed with letters D4324 dated 01 Oct 2014 and D5037 dated
May 2015 being relevant.
5 29 February 2016
FOB Underwater Blasting cont’d
5. The Contractor has carried forward to this claim their first
submission of the claimed 155 days without taking into account the
claim settlement and proportioning of that agreed as additional.
7. The Engineer does not accept there to be any additional work for
blasting at the South FOB and the Contractor agreed that in
settlement of their claim for payment for blasting on the North FOB
there would be no claim for the South FOB. Minutes of Meeting
……….
6 29 February 2016
FOB – Time to Remove Sunken Object
1. The wreck encountered was not a jack-up as being suggested
by the Contractor but was a small pontoon of estimated size ????
7 29 February 2016
FOB – Time to Remove Sunken Object cont’d
5. The barge turned out to be much smaller than HCC had claimed
and the area was in fact more a pile of concrete debris which if
properly surveyed and investigated by the Contractor would have
been found much earlier.
8 29 February 2016
FOB – Additional Time for Rock Level
1. The Contractor refers in their claim to a rock level obtained from
a post dredge survey carried out by Essar. This is a bathymetric
survey and can only be used as such i.e. to give a bed level after
dredging rock and/or soft material. It cannot possibly give the rock
quality to be found at that level or lower.
9 29 February 2016
FOB – Additional Time for Rock Level cont’d
10 29 February 2016
FOB – SA-1 & SA-2 Entry Restriction
1. The Engineer has requested the Contractor to submit full details
on this subject but to date the Contractor has failed to do so. Ref;
to letters ????????????
11 29 February 2016
Headwall – Encountering Rock Armour
1. Reference should be made to the Engineer’s response to claims
for the Access Ramp, which claim is now under arbitration.
12 29 February 2016
Headwall – SA-1 & SA-2 Entry Restrictions
13 29 February 2016
Entrance Cofferdam
1. The R0 programme date for commencement of the Entrance
Cofferdam design was 9 April 2011.
14 29 February 2016
Entrance Cofferdam cont’d
4. The R0 programme date for commencement of construction was
13 September 2011 and the varied works did not prevent the
design for this being advanced and completed in line with the
Contractor’s programme.
6. The key problem at this time was that the Contractor’s tender
design was inadequate and would fail.
15 29 February 2016
Entrance Cofferdam cont’d
16 29 February 2016
Entrance Cofferdam cont’d
8. Furthermore the Contractor had again used the Essar
bathymetric survey dredge level as an assumption of sound
structure bearing rock.
9. The Contractor should have used the data from the geotechnical
reports and other records available with him at the time of tender.
10. The Contract Document states that for “Design Criteria” the
“Soil/rock investigations and rock permeability test” the reports of
Afcoms and Cemindia were to be used.
17 29 February 2016
Entrance Cofferdam cont’d
18 29 February 2016
Entrance Cofferdam cont’d
12. The Contractor’s own ground investigation was carried out
between ???????????? And reported on ???????????
13. The necessity for reinforced concrete piles could have been
foreseen had the Contractor used the most appropriate data
available at the time of tender and would have saved the
Contractor time searching and toiling over unsavoury facts that
emerged during detailed design.
14. The Engineer does not believe that additional time is due for
developing the design for the additional cofferdam as the
Contractor was adamant that construction had to start from the
North FOB and that a separate start could not be made at the
South FOB.
19 29 February 2016
Entrance Cofferdam cont’d
15. No EOT is due as a consequence of the Contractor changing
the design from that submitted with the Contractor’s tender as
there were no un-foreseen circumstances as far as ground
conditions were concerned.
20 29 February 2016
Entrance Cofferdam cont’d
17. Stoppage for work to facilitate underwater blasting was taken
from contemporary records where 1 hour was allowed per blast.
The Contractor’s request for consideration of 4 hrs per blast does
not relate to any actual fact or record. An award of ??? Days has
been granted and added to the overall EOT for the Contract.
19. There were also drawings from previous works for dynamic
cone penetration tests that show rock near -14.5mCD adjacent to
borehole MB10.
21 29 February 2016
Entrance Cofferdam cont’d
22 29 February 2016
Entrance Cofferdam cont’d
23 29 February 2016
Entrance Cofferdam cont’d
24 29 February 2016
Entrance Cofferdam cont’d
20. There was other data that showed abruptly changing rock
levels and fall offs.
25 29 February 2016
Entrance Cofferdam cont’d
21. The Contractor’s claimed delays for security alerts have not
been evaluated by the Engineer because the Contractor has not
submitted the requested details. (HCC’s Item k)
26 29 February 2016
Entrance Cofferdam cont’d
25. Claimed Additional Time Required for Demolition of Piles
(HCC Item o)
As previously responded the Engineer has made clear that the
Contractors tender design for the Entrance Cofferdam piles was
inadequate and for construction they had to increase the capacity
of the cofferdam piles. This the Contractor chose to do by installing
reinforced concrete within their steel liner. The responsibility was
the Contractor’s under the Contract and the removal of then is also
the responsibility of the Contractor’s at not cost to the Employer
and with no increase in time allowance or EOT.
27 29 February 2016
Removal of Excess Silt Deposited in Dock Area
28 29 February 2016
Ground Improvement of Dock Master Complex
29 29 February 2016
Extension of Dock Floor
1. The length of the dock has not changed and remains as the
tender design.
30 29 February 2016