Você está na página 1de 25

Sep 09

RENEWABLE ENERGY – NEW TARIFF


GUIDELINES & REC FRAMEWORK

Saurabh Mehta
Asst. Manager (BD – Projects)
Reliance Power
FLOW OF PRESENTATION

 CERC’s new regulation


 Background
 Salient Features
 Wind Energy
 Solar Energy
 National Solar Mission
 Renewable Energy Certificate (REC)
 Background
 REC Concept
 Operational Framework

confidential
CERC’S NEW REGULATION
Background – Pre regulation scenario
 Wind Energy
 Different Tariff regimes for different states
 Large variations – Rajasthan Rs 4.28 / Unit v/s Tamilnadu Rs.
3.39 / Unit
 Similar tariff for different wind zones in a state
 No clarity for CDM Benefits sharing
 Fixed project cost without any indexing
 Fixed ROE throughout the project life
 Solar Energy
 Different Tariff regimes for different states
 No clarity of tariff determination methodology
 Large portions of tariff (Rs. 10 to 12) to come from GOI as
Generation Based Incentive (GBI)

CERC’s new regulation addresses the issues of Renewable Energy Tariff Determination

confidential
CERC’S NEW REGULATION
Salient Features
 Eligibility criteria

SN. RE Source Criteria

1 Wind Minimum Wind Power Density – 200 w/m2 @ 50 m hub height

2 Solar PV Technologies approved by MNRE

3 Solar Thermal (CSP) Technologies approved by MNRE

4 Biomass Restriction on fossil fuel use up to 15%

5 Small Hydro Power Capacity lower than or equal to 25 MW

confidential
CERC’S NEW REGULATION
Salient Features contd.
 Review Period – 3 years
 Tariff Period –
 Small Hydro Projects : 35 years
 Solar PV & Solar Thermal : 25 years
 Other RE Projects : 13 years
 Useful life –
 Wind Projects : 25 years
 Biomass Projects : 20 years
 Small Hydro Projects : 35 years
 Solar PV / Solar Thermal Projects : 25 years
 Project Specific Tariff –
May be determined by commission on case to case basis for the following;
 Hybrid Solar Thermal Power Plants
 Municipal solid waste projects
 Any other new renewable technology

confidential
CERC’S NEW REGULATION
Salient Features contd.
 Tariff Structure
Single part tariff with following fixed cost components (except for biomass
and non – fossil fuel based cogen plants)
 Return on Equity (ROE)

 Interest on loan capital

 Depreciation

 Interest on working capital

 Operation and maintenance expenses

 Levellised Tariff –
 Discount factor equivalent to weighted average cost of capital (WACC)
 Dispatch Principles –
 “MUST RUN” status for all RE projects except biomass project of 10 MW
and non-fossil fuel based cogen plants.

confidential
CERC’S NEW REGULATION
Financial Principles for Tariff Determination

S.N. Parameter Pre-Regulation As per present regulation

1 Project Cost (Rs. Crs/MW) Fixed Indexed

2 Loan Tenure 10 years 10 Years

3 Debt Equity Ratio 70:30 70:30

4 Interest Rate 12.5 % SBI LTPLR + 150 bps

7% till 10th year.


5 Depreciation 5.28% Balance - spread over remaining
life

19% till 10th year,


6 Return on Equity (ROE) 16% Fixed
24% from 11th year onward

0% in 1st year,
No uniform regulation.
7 CDM Sharing with utility 10% raise till 6th year,
Varying for States
50% -50% thereafter

confidential
CERC’S NEW REGULATION
Financial Principles for Tariff Determination

Capital Cost (Rs O&M Cost Approx PLF Auxiliary


SN. RE Source
Cr/MW) (Lacs/MW) (%) Consumption

1 Wind 5.15 6.5 20% - 30% -

2 Solar PV 17.0 9.0 19% -

3 Solar Thermal (CSP) 13.0 13.0 23% 10%

4 Biomass 4.50 20.25 80% 10%

5 Small Hydro Power 5 to 7# 12 to 21 # 30% & 45% # 1%

Non – fossil fuel based


6 4.45 13.35 45% to 60% # 8.5%
cogen

# - Varying for different states


confidential
CERC’S NEW REGULATION
Levellised Tariff State-wise Comparison
Expected after new regulation
(Wind Zone Wise)
Pre- 1 2 3 4
S.N State
regulation (200 – 250 (250 – 300 (300 – 400 (400 above
W/m2 ) W/m2 ) W/m2 ) W/m2 )
20% 23% 27% 30%

1 Maharashtra 4.39 5.64 4.90 4.18 #

2 Tamilnadu 3.39 5.64 4.90 4.18 3.76

3 Gujarat 3.50 5.64 4.90 # #

4 Rajasthan 4.28 5.64 4.90 # #

5 Karnataka 3.40 5.64 4.90 4.18 #

# - Wind zone not present in the state


confidential
WIND ENERGY
Project IRRs w/o depreciation benefit – comparison

Pre-regulation
As per
S.N State
Regulation
MH RJ GJ KA TN

1 Wind Zone 1 8.2% 7.8% 4.9 % 4.6 % - 12.9%

2 Wind Zone 2 10.4 % 10.2% 7.0% 6.5% 6.4% 13.1%

3 Wind Zone 3 13.2 % 13.2 % 9.7% 9.2% 9.2% 13.2%

4 Wind Zone 4 - - - 11.1% 11.0% 13.4 %

Capex @ Rs. 6.0 Crs / MW

confidential
WIND ENERGY
Equity IRRs w/o depreciation benefit – comparison

Pre-regulation
As per
S.N State
Regulation
MH RJ GJ KA TN

1 Wind Zone 1 6.3 % 5.4 % 1.2 % 0.7 % - 13.8%

2 Wind Zone 2 9.7 % 9.2 % 4.0 % 3.3 % 3.3 % 13.9 %

3 Wind Zone 3 14.1 % 14.3 % 8.3 % 7.5 % 7.4 % 14.2 %

4 Wind Zone 4 - - - 10.6 % 10.5 % 14.4 %

Capex @ Rs. 6.0 Crs / MW

confidential
SOLAR ENERGY
Levellised Tariff State-wise Comparison

Pre-regulation
PPA
Tenure Present
S.N. State
(Pre- Solar PV Solar Thermal Regulation
regulation)

Rs. 3.0 /Unit Rs. 3.0 /Unit Solar PV –


1 Maharashtra* 20 Years (May qualify for GBI benefit (May qualify for GBI Rs.18.81
of Rs. 12 /Unit) benefit of Rs. 10 /Unit)
/Unit
Rs. 3.15 /Unit Rs. 3.15 /Unit
2 Tamilnadu* 10 Years (May qualify for GBI benefit (May qualify for GBI
of Rs. 12 /Unit) benefit of Rs. 10 /Unit) Solar
Rs. 13.00 / Unit (till 12th Rs. 10.00 / Unit (till 12th Thermal –
3 Gujarat 25 Years
year) year) Rs. 13.71
Rs. 3.00 / Unit (13 to 25
th th
Rs. 3.00 / Unit (13th to 25th /Unit
year) year)
4 Rajasthan 20 Years Rs. 15.78 /Unit Rs. 13.78 /Unit For 25 years
5 Uttar Pradesh 20 Years Rs. 15.0 /Unit Rs. 13.0 / Unit

* - Projects are under GBI policy with cap of 50 MW


confidential
NATIONAL SOLAR MISSION
OBJECTIVES

 To make India Global leader in solar energy through -


 20,000 MW Generation Capacity by 2020
 100,000 MW Generation Capacity by 2030
 200,000 MW Generation Capacity by 2050
 Cost reduction for solar power to grid parity (Rs 4-5 / kWh) by 2020
 To achieve parity with coal based Thermal Power by 2030
 Mandatory setting of solar plants equivalent to 5% of thermal power plant capacity to
be set by the generation utilities.
 4 – 5 GW of solar manufacturing capacity by 2017

confidential
NATIONAL SOLAR MISSION
MISSION – 20 GW BY 2020

Phase
Phase 11 (2009
(2009 –– 12)
12)

 Consolidating
Consolidating ongoing
ongoing efforts
efforts on
on off
off grid
grid applications
applications

 Demo
Demo utility
utility scale
scale projects
projects (CSP
(CSP –– Solar
Solar Thermal)
Thermal)

 To
To achieve
achieve 11 –– 1.5
1.5 GW
GW during
during this
this phase
phase

Phase
Phase 22 (2012
(2012 –– 17)
17)

 Scaling
Scaling up
up across
across applications
applications &
& Rapid
Rapid cost
cost reduction
reduction

 Deployment
Deployment ofof new
new technologies
technologies –– Concentrating
Concentrating PV,
PV, storage
storage technologies
technologies

 To
To achieve
achieve 66 –– 77 GW
GW during
during this
this phase
phase

Phase
Phase 33 (2017
(2017 –– 20)
20)

 Rapid
Rapid scale
scale up
up across
across all
all applications
applications

 Reduction
Reduction in
in capital
capital subsidies
subsidies

 To
To achieve
achieve the
the target
target of
of 20
20 GW
GW of
of installed
installed capacity
capacity

confidential
NATIONAL SOLAR MISSION
ROAD MAP FOR 20 GW BY 2020

Utility connected power 12000 MW

Rooftop PV
3000 MW
(Captive & Grid connected)
Rural Installation
3000 MW
(Rural grid plants + stand alone)
Other PV applications
2000 MW
(eg telecom towers etc)
Lighting for 20 mn households
Solar lighting, heating & others
Solar collection area for 20 mn sq mtrs for heating

Resource Mobilization

 Funds of Rs. 80,000 – Rs. 100,000 Crs required over 30 years for incentives like GBI
 Proposed to be supplemented through cess on fossil fuel and thermal projects
 May not be required after the recent regulation of CERC.

confidential
RENEWABLE ENERGY CERTIFICATE
BACKGROUND

 National Action Plan for Climate Change (NAPCC) announced by the Hon. PM of India on
June 30, 2008
 Principles
 Protecting the poor and vulnerable sections through sustainable growth
 Achieving national growth through ecological sustainability
 Demand side management
 Deploying appropriate technology for adaptation and mitigation of GHG
 Engineering new and innovative forms of markets
 Envisages several measures to address global warming

Increases the share of renewable energy in total electricity consumption

confidential
RENEWABLE ENERGY CERTIFICATE
NAPCC PROMOTING RENEWABLE ENERGY

 Target of mandatory 5% Renewable Energy Purchase (RPO) for FY 2009-10 against


current level of around 3.5% by Discoms, Open Access consumers and captive
consumers.
 Target will increase by 1% for next 10 years
 Constitute approx. 15% of the energy mix of India
 Need for innovative financing instruments
 Policy instrument prescribed in NAPCC is Renewable Energy Certificate (REC)
Mechanism to enable RPO implementation.
 Report on Development of Conceptual Framework for REC Mechanism for India - ABPS
Infrastructure Advisory Private Limited submitted to MNRE, June 09

confidential
RENEWABLE ENERGY CERTIFICATE
REC CONCEPT
Electricity generated from RE sources can be divided into two components:
 Electricity component
 Environmental component

The environmental component associated with renewable energy can be carved out as a separate
component and used for the purpose of REC mechanism

SCHEMATIC OF REC CONCEPT

confidential
RENEWABLE ENERGY CERTIFICATE
SALIENT FEATURES OF REC FRAMEWORK

 NOT an incentive scheme. Enable sale and purchase of renewable component


across the State boundaries
 Scheme to come into force on April 1, 2010
 Coexist with all current incentive based schemes
 1 MWhr  1 REC
 Purchase of REC would be considered as purchase of RE
 Not related to carbon credits
 RE generators with capacity untied in PPA will have an option to sell electricity
and REC separately
 REC will be issued to RE Generators only
 Validity of 25 years for REC Framework
 Carry forward allowed for maximum of 25% of REC issued .

confidential
RENEWABLE ENERGY CERTIFICATE
ELIGIBILITY CRITERIA

 Eligible

 RE technologies recognized by MNRE

 Grid connected RE generators of at least 250 KW capacity

 Not eligible

 RE project with existing PPA

 If RE sale at preferential Tariff

confidential
RENEWABLE ENERGY CERTIFICATE
PROPOSED PROCESS OF REC MECHANISM

 Step 1: Electricity Generation and Feeding to the Grid

 Step 2: Request for issuance of REC

 Step 3: Confirmation of Electricity Generation

 Step 4: Creation and Issuance of RECs

 Step 5: REC Sale by RE Generator

 Step 6: Surrender/Redeeming of RECs

 Step 7: Compliance Reporting

confidential
RENEWABLE ENERGY CERTIFICATE
OPERATIONAL FRAMEWORK OF REC MECHANISM - COMPREHENSIVE
Accreditation of RE power plants
1
(State nodal agency: SNA)

Registration of Eligible entities Information related to accreditated RE


2 (Central level agency) plants for registered entities sent to REC
registry

4 5

Issuance of REC exchange


RE Generator REC Central REC
Registry (NLDC)

Information
3
related to
RE
Sale of electricity at par Auditing Panel
generation
with conventional power

6
Discom issuing
RE injection State Load
certificate Despatch Centre
(SLDC) Information on REC
Electricity purchase/redemption
Energy
accounting SERC: Compliance State Nodal
based on SNA Report Agency SNA

confidential
RENEWABLE ENERGY CERTIFICATE
RECOMMENDED METHODOLOGY

 Link the electricity component with normative RE tariff


 REC component with notional fixed price

ISSUES
 Additional benefit to the RE developer …..?
 Whether registration with national registry is mandatory for RE developer ….?
 Price for REC component - Market driven or notional fixed ....?

confidential
RENEWABLE ENERGY CERTIFICATE
SALE AND PURCHASE FOR REC

 Not only obligated entities (Discoms, Open Access Consumers, Captive consumers) but
also other persons shall be allowed to buy RECs
 Redemption of RECs by obligated entities shall be reported to monitoring committee
 Redemption by voluntary buyers will be reported to only Central Regulator
 REC Exchange Platform is expected to provide the services for sale and purchase of
RECs
 The Task Force has agreed with the proposal that ‘one single market’ shall be created in
the country for exchange/transfer of REC
 FOR should undertake the assessment of market, liquidity requirements, costs involved
in setting up of the market and necessary fee structure

confidential
THANK YOU

Você também pode gostar