Escolar Documentos
Profissional Documentos
Cultura Documentos
Outline
hj '
may not give a good solution because a production
quantity may not be large enough to meet the
demand between two production runs of the product.
3
EOQ Model for Production Planning
4
Optional
Example
Problem with Separate EPQ Computation
Example 6: Tomlinson Furniture has a single lathe for turning
the wood for various furniture pieces including bedposts,
rounded table legs, and other items. Two products and
some relevant information appear below:
Annual Setup Time Unit Annual
Piece Demand (hours) Cost Production
J-55R 18,000 1.2 $20 33,600
H-223 24,000 0.8 35 52,800
Worker time for setup is valued at $85 per hour, and holding
costs are based on a 20 percent annual interest charge.
Assume 8 hours per day and 240 days per year.
5
Optional
Example
Problem with Separate EPQ Computation
Find the optimal production quantities separately for each
product and show that production quantity of H-223 is not
large enough to meet the demand between two production
runs of H-223.
Product J - 55R :
K set - up time worker time 1.2 85 $102
h Ic 0.20 20 $4/unit/year
18,000
0.5357
P 33,600
h' h1 41 0.5357 $1.8571/unit/year
P 6
Optional
Product J - 55R (continued from the previous slide) :
2 K 2 102 18,000
Q EPQ
*
1,406.1404 units
h' 1.8571
*
Max Inventory, H Q 1 1,406.141 0.5357 652.85 units
P
Q * 1,406.1404
Uptime, T1 240 10.0439 days
P 33,600
Minimum downtime (days), required
Uptime for H - 223 setup time of H - 223
4.2027 days (see the next slide) 0.8 hr/ 8 hr per day
4.3027 days
H 652.8509
Maximum inventory lasts for (days) 240
18,0001
8.7047 days 4.3027 days (downtime demand met) 7
Optional
Product H - 223 :
K set - up time worker time 0.8 85 $68
h Ic 0.20 35 $7 /unit/year
24,000
0.4545
P 52,800
h' h1 71 0.4545 $3.8182 /unit/year
P
2 K 2 68 24,000
Q EPQ
*
924.5848 units
h' 3.8182
*
Max Inventory, H Q 1 924.581 0.4545 504.32 units
P
Q * 924.5848
Uptime, T1 240 4.2027 days
P 52,800
8
Optional
Product H - 223 (continued from the previous slide) :
Minimum downtime (days), required
Uptime for J - 55R setup time of J - 55R
10.0439 days 1.2 hr/ 8 hr per day 10.1939 days
Maximum inventory lasts for (days)
H 504.3190
240
24,000
5.0432 days 10.1939 days
(downtime demand cannot be met)
T s1 T1 s2 T2 sn Tn Idle time
13
EOQ Model for Production Planning
T s1 T1 s2 T2 sn Tn Idle time
s1 T1 s2 T2 sn Tn
1
T T T T T T
n s n T n n
1
1 s j 1
j j j
j 1 T j 1 T T j 1 j 1 Pj
n
s
j 1
j
T n j
1
j 1 Pj 14
EOQ Model for Production Planning
s
n
j 2 K j
j 1
T * Cycle1 T * Cycle2
j 1
n j n
1 h' j j
j 1 Pj j 1
15
Example
EOQ Model for Production Planning
Example 7: Tomlinson Furniture has a single lathe for turning
the wood for various furniture pieces including bedposts,
rounded table legs, and other items. Two products and
some relevant information appear below:
Annual Setup Time Unit Annual
Piece Demand (hours) Cost Production
J-55R 18,000 1.2 $20 33,600
H-223 24,000 0.8 35 52,800
Worker time for setup is valued at $85 per hour, and holding
costs are based on a 20 percent annual interest charge.
Assume 8 hours per day and 240 days per year. Find the
optimal production quantities. 16
n 2
s s
j 1
j
j 1
j s1 s2
n 2
K K
j 1
j
j 1
j K1 K 2
n j 2 j 1 2
P P
j 1 j 1
P1
P2
j j
n 2
h'
j 1
j j h' j j
j 1
h'1 1 h'2 2
17
n
s
j 1
j
Cycle1
n j
1
j 1 Pj
n
2 K j
j 1
Cycle2 n
h'
j 1
j j
downtime of J - 55R
(uptime setup time) of H - 223 (check)
19
Product H - 223 :
Q * T *
Max Inventory, H Q* 1
P
Q*
Uptime, T1
P
Downtime T * Uptime
H
Maximum inventory lasts for (days)
downtime of H - 223
(uptime setup time) of J - 55R (check)
20
J-55R H-223 Total
K, Setup cost, $ 102 68 170
h, Holding cost/unit/year 4 7
demand/production 0.5357 0.4545 0.9903
h' 1.8571 3.8182
h'(demand)
Reading:
Section 4.9 , pp. 226-229 (4th Ed.), pp. 215-220 (5th
Ed.)
Exercise:
29, 30 pp. 230-231(4th Ed.), pp. 219-220 (5th Ed.)
22