Chapter 3
Project Management
1-2
3
OBJECTIVES
1-3
4
Project Management
Defined
Gantt Chart
Vertical Axis:
Always Activities Horizontal bars used to denote length
or Jobs of time for each activity or job.
Activity 1
Activity 2
Activity 3
Activity 4
Activity 5
Activity 6
Pure Project
1-6
7
Structuring Projects
Pure Project: Disadvantages
• Duplication of resources
• Organizational goals and policies
are ignored
• Lack of technology transfer
• Team members have no functional
area "home"
1-7
8
Functional Project
President
Research and
Engineering Manufacturing
Development
Structuring Projects
Functional Project: Advantages
1-9
10
Structuring Projects
Functional Project: Disadvantages
1-10
11
President
Research and
Engineering Manufacturing Marketing
Development
Manager
Project A
Manager
Project B
Manager
Project C
1-11
12
Structuring Projects
Matrix: Advantages
• Pinpointed responsibility
1-12
13
Structuring Projects
Matrix: Disadvantages
1-13
14
1 Project 1 Project 2
1-14
15
Network-Planning Models
1-15
16
1-16
17
1-17
18
• 1. Activity Identification
• 2. Activity Sequencing and
Network Construction
• 3. Determine the critical path
– From the critical path all of the
project and activity timing
information can be obtained
1-18
19
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
D(2)
G F 1
E(5)
1-20
21
ES=4
EF=6
1-21
22
Determine late starts and late finish times Hint: Start with LF=15
or the total time of the
ES=4 project and go
EF=6 backward in the
network from G to A.
ES=0 ES=2 ES=3 D(2)
ES=9 ES=14
EF=2 EF=3 EF=4 LS=7 EF=14 EF=15
LF=9
A(2) B(1) C(1) F(5) G(1)
ES=4
LS=0 LS=2 LS=3 EF=9 LS=9 LS=14
LF=2 LF=3 LF=4 LF=14 LF=15
E(5)
LS=4
LF=9
1-22
23
ES=4
Slack=(7-4)=(9-6)= 3 Wks
EF=6
1-23
24
Immediate
Task Predecesors Optimistic Most Likely Pessimistic
A None 3 6 15
B None 2 4 14
C A 6 12 30
D A 2 5 8
E C 5 11 17
F D 3 6 15
G B 3 9 27
H E,F 1 4 7
I G,H 4 19 28
1-24
25
ET(A)= 3+4(6)+15
Immediate Expected 6
Task Predecesors Time
A None 7 ET(A)=42/6=7
B None 5.333
C A 14 Immediate
Task Predecesors Optimistic Most Likely Pessimistic
D A 5 A None 3 6 15
E C 11 B None 2 4 14
C A 6 12 30
F D 7 D A 2 5 8
E C 5 11 17
G B 11 F D 3 6 15
H E,F 4 G B 3 9 27
H E,F 1 4 7
I G,H 18 I G,H 4 19 28
Immediate Expected
ET(B)= 2+4(4)+14
Task Predecesors Time 6
A None 7
B None 5.333 ET(B)=32/6=5.333
C A 14
D A 5 Immediate
E C 11 Task Predecesors Optimistic Most Likely Pessimistic
A None 3 6 15
F D 7 B None 2 4 14
G B 11 C A 6 12 30
D A 2 5 8
H E,F 4 E C 5 11 17
F D 3 6 15
I G,H 18 G B 3 9 27
H E,F 1 4 7
I G,H 4 19 28
Example 2. Network
Duration = 54 Days
C(14) E(11)
A(7) H(4)
D(5) F(7)
I(18)
B G(11)
(5.333)
1-28
29
p(t < D)
D=53
t
TE = 54
D - TE
Z =
cp
2
1-29
30
P essim . - O ptim . 2
A ctivity v ariance, 2
= ( )
6
1-30
31
p(t < D)
t
D=53 TE = 54
D - TE 53 - 54
Z = = = -.156
cp
2 41
1-32
33
p(t < D)
t
TE = 54
D=56
D - TE 56 - 54
Z = = = .312
cp
2 41
Time-Cost Models
1-34
35
CPM Assumptions/Limitations
End of Chapter 3
1-36