Escolar Documentos
Profissional Documentos
Cultura Documentos
1. Brief Introduction
2. Applications
3. Meralco Supplied Transformers
4. Vault Requirements for Deadfront DT
5. Vault Requirements for Padmounted DT
ð 13.8Y/7.9 kV
ð Commercial Buildings
2-banks of 1 MVA
ð Industrial
1 MVA
• 1-phase unit
• 2 deadfront primary
bushings
• Spade-type secondary
terminals
• Round tank construction
• Standard DT accessories
Transformers for the New Service Voltage
Meralco-supplied Transformer Capacity
• 3-167 kVA, 3-250 kVA & 3-333 kVA transformer units to
be installed indoors in a PEC-approved transformer vault
• Maximum of one (1) bank or 1000 kVA for solely-served
loads
APPROVED LOCATIONS
ð Ground floor
ð Second floor
CONSTRUCTION
ð Reinforced concrete walls (‘buhos’), 150-mm
thick
ð Reinforced concrete floor (‘buhos’), 100-mm thick
when in contact with earth, 150 mm when above
another storey
ð No openings such as doors or vents to any part of
the building interior
ð Provided with 150-mm high door sill for liquid
confinement
2/F
TRANSFORMER
INSTALLATION
NOTE: Signboard obstruction
CO CHIN LENG BLDG.
Q. Paredes St., Binondo, Manila.
2/F TRANSFORMER
INSTALLATION
NOTE: Facade obstruction
P.C.T. BUILDING
311 Muelle de Binondo St., Binondo,
Manila
Presentation to IIEE Oct. 26, 2006
/RRM
Accessibility Problem
2/F TRANSFORMER
INSTALLATION
NOTE: Signboard obstruction
5/F TRANSFORMER
INSTALLATION
LOCATION 1-BANK
Ground Floor
(W) 5 m X (D) 4 m
2nd Floor
X (H) 3 m
1st Basement
NOTE: W = Width
D = Depth
H = Height (Headroom)
ELECTRONIC
4500
POLYPHASE
METER
PRIMARY CABLE EQUIPMENT
CABINET
TRENCH EXHAUST ACCESS
FAN DOORWAY
2000
4000
MAIN
BREAKER
2000
EXHAUST
FAN
EXHAUST
DUCT
MAIN
BREAKER
3000
DEADFRONT
DT
LOW-VOLTAGE
Presentation to IIEE Oct. 26, 2006 SERVICE CABLES
/RRM
GROUND FLOOR 4000
TRANSFORMER VAULT 2000 2000
(SIDE ELEVATION)
EXHAUST
EXHAUST FAN
DUCT
DEADFRONT
1000
800
TO
DT
2000
LOUVERED
STEEL
1000
DOOR
SETBACK
ACCESS ROAD
(VARIES)
600
900
SERVICE
CABLES
STAIRCASE
2500
MAIN
4000
BREAKER
1500
ENTRANCE
EXHAUST
FAN
EXHAUST
DUCT
1000
800
TO
DEADFRONT
DT TRANSFORMER
ACCESS DOOR
1000
PRIMARY CABLE
300
900
REINFORCED
CONCRETE
600
LEDGE
400
1300
SECONDARY
700 700
CABLES SETBACK ACCESS ROAD
25 25 (VARIES)
GROUND
ROD
Presentation to IIEE Oct. 26, 2006
/RRM
2ND FLOOR
5000
TRANSFORMER VAULT
(FRONT ELEVATION) 1100 1400 1400 1100
EXHAUST
DUCT
MAIN
BREAKER
3000
DEADFRONT
DT
LOW-VOLTAGE
SERVICE CABLES
GROUND FLOOR
BUILDING WALL ELECTRONIC
POLYPHASE
METER
CABINET
STAIRCASE
PERSONNEL
ACCESS DOOR
1ST BASEMENT TRANSFORMER VAULT
(PLAN)
4500
HATCHWAY OPENING
2500
PRIMARY
CABLE
TRENCH
4000
MAIN
CIRCUIT
BREAKER
1500
STAIRCASE SECONDARY
CABLE
PERSONNEL TRENCH
ACCESS DOOR
ELECTRONIC
POLYPHASE ELEVATED
METER HATCHWAY WITH
CABINET STEEL COVER
SETBACK
(VARIES) ACCESS ROAD
EXHAUST
VENT
500
740
1000
400
600
700 700
25
MAIN
CIRCUIT
BREAKER
3000
SECONDARY
CABLES
LOWEST BASEMENT
GROUND
ROD
Presentation to IIEE Oct. 26, 2006
/RRM
Dead-front Padmounted
Distribution Transformer
APPROVED LOCATIONS
ð Ground floor
ð Second floor
LOCATION 2-BANKS
(W) 8 m X (D) 4 m
Ground Floor
X (H) 3 m
(W) 8 m X (D) 6 m
2nd Floor
X (H) 4 m
(W) 8 m X (D) 6 m
1st Basement
X (H) 3 m
NOTE: W = Width
D = Depth
H = Height (Headroom)
TRANSFORMER TRANSFORMER
BANK #1 BANK #2
EXHAUST FANS
AND DUCTS
PRIMARY TRANSFORMER
CABLE DUCTS ACCESS DOORS
PLAN
EXHAUST FAN
AND DUCT
CUSTOMER’S
MAIN
SECONDARY
CIRCUIT
BREAKER
TRANSFORMER
ACCESS DOOR
TRANSFORMER
SIDE VIEW
PRIMARY SECONDARY
CABLE DUCTS CABLE
Presentation to IIEE Oct. 26, 2006 DUCTS
/RRM
2/F
Transformer CUSTOMER’S MAIN
Vault SECONDARY CIRCUIT
BREAKERS METER #1 METER #2
(Double Bank)
PERSONNEL
ACCESS DOOR
STAIRCASE
TRANSFORMER
ACCESS DOORS
PLAN
Presentation to IIEE Oct. 26, 2006
/RRM
2/F Transformer Vault
HOISTING I-BEAM
EXHAUST FAN
AND DUCT
TRANSFORMER
ACCESS DOOR
HOISTING
FACILITY
PERSONNEL
ACCESS
TRANSFORMER
DOOR
CUSTOMER’S
MAIN
SECONDARY
CIRCUIT
BREAKER
GROUND GRID
SIDE VIEW
Presentation to IIEE Oct. 26, 2006
/RRM
1/B Transformer
Vault with Hatchway
PERSONNEL
ACCESS
DOOR
AIR INTAKE
FAN & VENT
HATCHWAY
STAIRCASE
AIR EXHAUST
METER
FAN & VENT
PLAN
Presentation to IIEE Oct. 26, 2006
/RRM (Ground Floor)
1/B Transformer
Vault with Hatchway
PERSONNEL
ACCESS ELEVATED
DOOR HATCHWAY
WITH STEEL
COVER
AIR AIR
INTAKE EXHAUST
FAN FAN
STAIRCASE
TRANSFORMER
SIDE VIEW
Presentation to IIEE Oct. 26, 2006
/RRM
Presentation to IIEE Oct. 26, 2006
/RRM
2/F Transformer
Vault with CUSTOMER’S MAIN
SECONDARY CIRCUIT
METER #1 METER #2
Hatchway BREAKERS
(Double Bank)
PERSONNEL
ACCESS DOOR
STAIRCASE
HOISTING I-BEAM
HOISTING I-BEAM
HATCHWAYS
PLAN
Presentation to IIEE Oct. 26, 2006
/RRM
2/F Transformer
Vault with Hatchway
HOISTING I-BEAM
EXHAUST FAN
AND DUCT
CUSTOMER’S
MAIN HOISTING
SECONDARY FACILITY
CIRCUIT PERSONNEL
BREAKER
TRANSFORMER
ACCESS
DOOR
HATCHWAY
GROUND GRID
SIDE VIEW
Presentation to IIEE Oct. 26, 2006
/RRM