General conditions of contract

Construction of Two Tunnel


(Two tubes of Four lane each ( in km 1+040 to km 2+790) 1.75km and km 3+440
to 12+360
(8.92km) for Missing Link under Capacity Augmentation of Mumbai Pune
Expressway (the “Project”) through Engineering, Procurement and Construction
(EPC) Contract

from Notice inviting Tender to First Bill


(clause 1 to 6 Volume-I & clause 1 to 19 Volume-II)
Aim & Objective
• To understand general condition of contract
and Bidding process ..
• Comparison of Navayuga’s BID with contract
conditions.
• To understand General conditions of contact
volume-II EPC agreement from clause no 1 to
19.5
General Terms
• Authority
(MAHARASHTRA STATE ROAD
Athority
DEVELOPMENT CORPORATION
LIMITED)
• Authority’s Engineer Authority’s
Geodata-LB Consortium Engineer
• Contractor
Navayuga Engineering CO. Ltd.
Contractor
Content
• NIT
• Schedule Of BID
• BID General Terms and Docments
• BID Security
• Navayuga’s Actual Bid Document & Contact
Agreement
• Volume II EPC Agreement from clause 1 to
19.5
Notice inviting BID
Schedule of BID Process
• As per clause No 1.3 of Volume-I
• No. Event Description Date
• Period of down loading of RPF From 15/03/2018 to 02/05/2018
• Date of Submission of Bid (online) 02/05/2018
• Date of opening of financial bid of
qualified Applicants. 03/05/2018

• Validity of Bid 180 days from bid Due date 03/05/2018

• As per Corrigendum III of contract page no 605


Date of submission of Bid online changed from 2/05/2018 to 14/05/2018
General Terms of Bidding

• 2.1.1 Not more than one Bid

• Cost of BID 1,00,000

• Bid according to format Appendix-I

• BID Security Clause2.1.6 20.71 cr validity 180 days

• Power of Attorney
Bidding Process
clause No-1.2.

• Authority has adopted two stage Bidding


Process
• 1 Qualification stage
• 2 Bid Stage
Document for Biding
clause2.7 & 2.11
I Letter comprising the Bid
II. Bank Guarantee for Bid Security
III. Power of Attorney for signing of Bid
IV. Power of Attorney for Lead Member of Joint Venture
V. Ministry of Road Transport & Highways Transport Circular
VI. Pre-Qualified Bidders
These docs should be in 3 envelopes
Envelope I BID
Envelope II Enclosure of BID
Envelope III Copy documents (copy of Envelope II)
Navayuga Engineering CO. Ltd. BID
Navayuga’s BID Price
LOA
Contract Agreement
Obligations of contractor
• Contactor have to do survey, investigation, design, engineering, procurment,
construction and miantenance of the project
• Contactor will remedy all loss and demage to the project from the appointment
date to end of the construction period at the contactor,s cost
• Contactor comply with all aplicable law and permits
• Contactor will build temporaty road and maintain it for tunnel or adit approach.
• Contactor can not sub contact any work in more than 49 % of the total length.
• If volume of the sub contact work is more than 10 % of contract price than
contactor will communicate and information regarding sub contract with Authority
prior to entering into any such su-contract
• If contractor is hiring any foreign personnel then contractor should apply through
requisite authority for work permit and visa
• Project or any part of project should not be used of advertisment of commercial
product
• Contactor has to procure of all power, water and other services that is required for
project.
Obligations of Authority
• Correctness of the scpe of the project, Project fecilities,
Specifications and standards and criteria for testing of the work
completed.
• Environmental clearances
• Right of way 90 % with in 30 days of date of appointment
• Authority has to pay damages for delaying in ROW in trem of time
extention or money

• If contractor given written request for support for procuring


Applicable permits then Authority has to support the contractor.
• For obtaining all necessary infrastructure Authority can assisst
contractor but rates should not be less that rates in industries
norms.
Performance Security
• With in 10 days of date of agreement
• Value 5 % of contract price 2697x.05=134.87 cr
• Validity upto 180 days after completion date of defect
liability period
• Additional Performance security required if contract price is
less than 0.9x Estimated project cost.
• If contractor fail to pay PS within 10 days and seek
extension not more than 30 days then there will be fine on
daily basis 0.01* of contract price.
• If contactor pay performance security for two years and for
next year contractor has to submitt that security wirth in 2
months before expire of previous security and return
privious security with in 7 days after submitt new security.
Release of Performance security
The Authority shall return the Performance
Security to the Contractor within 60 (sixty)days
of the later of the expiry of the Maintenance
Period or the Defects Liability Period under this
Agreement. Notwithstanding the aforesaid, the
Parties agree that the Authority shall not be
obliged to release the Performance Security
until all Defects identified during the Defects
Liability Period have been rectified.
Retention Money
• Hold 6% of every payment of work as a
guarantee of performance during construction
period.
• Retention money should not exceed 5% of the
contract price.
Right Of way
• That means giving rights to use the site for
construction and maintenance of project.
• Authorities repersentative and contactor will
make list of inventerory of site that means
vacant land unqcuire land and building
structures road trees or any immovable
property with in 30 days of date of agreement